Rejection of the Project Schedule. (a) Buyer’s Representative shall have the right to reasonably reject, vary, amend, substitute or otherwise change the Project Schedule prior to approval thereof. Any such variation, amendment, substitution, or other change (other than a rejection) shall be considered a Buyer- Initiated Change under Section 13.1 (“Changes”). (b) If, under Section 10.3(a), Buyer’s Representative rejects any Project Schedule submitted by Seller, Seller shall, within seven (7) days of such rejection, submit four (4) copies of the final form of a revised Project Schedule for approval by Buyer’s Representative and of the Project Schedule.
Appears in 3 contracts
Samples: Asset Purchase Agreement, Asset Purchase and Sale Agreement, Asset Purchase and Sale Agreement
Rejection of the Project Schedule.
(a) BuyerCompany’s Representative shall have the right to reasonably reject, vary, amend, substitute or otherwise change the Project Schedule prior to approval thereof. Any such variation, amendment, substitution, substitution or other change (other than a rejection) shall be considered a Buyer- Initiated Company-Proposed Change under Section 13.1 (“Changes”).13.1.
(b) If, under Section 10.3(a10.2(a), BuyerCompany’s Representative rejects any Project Schedule submitted by SellerContractor, Seller Contractor shall, within seven (7) days of such rejection, submit four (4) copies of the final form of a revised Project Schedule Schedule, with the rejected items deleted or modified, for approval by BuyerCompany’s Representative and of the Project ScheduleRepresentative.
Appears in 2 contracts
Samples: Engineering, Procurement and Construction Contract (Chugach Electric Association Inc), Engineering, Procurement and Construction Contract (Chugach Electric Association Inc)
Rejection of the Project Schedule.
(a) Buyer’s Representative shall have the right to reasonably reject, vary, amend, substitute or otherwise change the Project Schedule prior to approval thereof. Any such variation, amendment, substitution, or other change (other than a rejection) shall be considered a Buyer- Buyer-Initiated Change under Section 13.1 (“Changes”).
(b) If, under Section 10.3(a), Buyer’s Representative rejects any Project Schedule submitted by Seller, Seller shall, within seven (7) days of such rejection, submit four (4) copies of the final form of a revised Project Schedule for approval by Buyer’s Representative and of the Project Schedule.
Appears in 1 contract
Samples: Asset Purchase and Sale Agreement
Rejection of the Project Schedule.
(a) Buyer’s Representative shall have the right to reasonably reject, vary, amend, substitute or otherwise change the Project Schedule prior to approval thereof. Any such variation, amendment, substitution, or other change (other than a rejection) shall be considered a Buyer- Initiated Change under Section 13.1 (“Changes”).Changes”).
(b) If, under Section 10.3(a), Buyer’s Representative rejects any Project Schedule submitted by Seller, Seller shall, within seven (7) days of such rejection, submit four (4) copies of the final form of a revised Project Schedule for approval by Buyer’s Representative and of the Project Schedule.
Appears in 1 contract
Samples: Asset Purchase Agreement
Rejection of the Project Schedule.
(a) Buyer’s Representative shall have the right to reasonably reject, vary, amend, substitute or otherwise change the Project Schedule prior to approval thereof. Any such variation, amendment, substitution, or other change (other than a rejection) shall be considered a Buyer- Buyer-Initiated Change under Section 13.1 (“Changes”).
(b) If, under Section 10.3(a), BuyerXxxxx’s Representative rejects any Project Schedule submitted by Seller, Seller shall, within seven (7) days of such rejection, submit four (4) copies of the final form of a revised Project Schedule for approval by BuyerXxxxx’s Representative and of the Project Schedule.
Appears in 1 contract
Samples: Asset Purchase and Sale Agreement