Common use of Relief for Change in Law Clause in Contracts

Relief for Change in Law. 9.2.1 In case Change in Law results in the Power Producer’s costs directly attributable to the Project being decreased or increased by one percent (1%), of the estimated revenue from the Electricity for the Contract Year for which such adjustment becomes applicable or more, during Operation Period, the Tariff Payment to the Power Producer shall be appropriately increased or decreased with due approval of GERC. 9.2.2 In case of Change in Law resulting on account of 9.1 (b) above, the Power Producer shall be allowed an increase / decrease in tariff of 1 paise / unit for every increase / decrease of Rs. 2 Lakh per MW of project capacity (AC) in the Project Cost which shall be allowed upon submission of proof of payment made by the Power Producer towards safeguard duty and/or anti-dumping duty to the concerned Authority and with due approval of GERC. 9.2.3 The Power Procurer / GUVNL or the Power Producer, as the case may be, shall provide the other Party with a certificate stating that the adjustment in the Tariff Payment is directly as a result of the Change in Law and shall provide supporting documents to substantiate the same and such certificate shall correctly reflect the increase or decrease in costs. 9.2.4 The revised tariff shall be effective from the date of such Change in Law as approved by GERC, the Parties hereto have caused this Agreement to be executed by their fully authorised officers, and copies delivered to each Party, as of the day and year first above stated.

Appears in 5 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement (Ppa)

AutoNDA by SimpleDocs

Relief for Change in Law. 9.2.1 In case Change in Law on account of 9.1.1 (a) above results in the Power Producer’s costs directly attributable to the Project being decreased or increased by one percent (1%), of the estimated revenue from the Electricity for the Contract Year for which such adjustment becomes applicable or more, during Operation Period, the Tariff Payment to the Power Producer shall be appropriately increased or decreased with due approval of GERC. 9.2.2 In case of Change in Law resulting on account of 9.1 9.1.1 (b) above, the Power Producer shall be allowed an increase / decrease in tariff of 1 paise / unit for every increase / decrease of Rs. 2 Lakh per MW of project capacity (AC) in the Project Cost which shall be allowed incurred upto the Schedulded Commercial Operation Date upon submission of proof of payment made by the Power Producer towards safeguard duty and/or anti-dumping duty and/or custom duty to the concerned Authority and with due approval of GERC. This increase / decrease in tariff due to this change in cost of solar PV modules shall be limited to actual DC capacity or 150% (One hundred & fifty percent) of contracted AC capacity, whichever is lower. 9.2.3 The Power Procurer / GUVNL or the Power Producer, as the case may be, shall provide the other Party with a certificate stating that the adjustment in the Tariff Payment is directly as a result of the Change in Law and shall provide supporting documents to substantiate the same and such certificate shall correctly reflect the increase or decrease in costs. 9.2.4 The revised tariff shall be effective from the date of such Change in Law as approved by GERC, the Parties hereto have caused this Agreement to be executed by their fully authorised officers, and copies delivered to each Party, as of the day and year first above stated.be

Appears in 3 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement (Ppa), Power Purchase Agreement (Ppa)

Relief for Change in Law. 9.2.1 In case Change in Law on account of 9.1.1 (a) above results in the Power Producer’s costs directly attributable to the Project being decreased or increased by one percent (1%), of the estimated revenue from the Electricity for the Contract Year for which such adjustment becomes applicable or more, during Operation Period, the Tariff Payment to the Power Producer shall be appropriately increased or decreased with due approval of GERC. 9.2.2 In case of Change in Law resulting on account of 9.1 9.1.1 (b) above, the Power Producer shall be allowed an increase / decrease in tariff of 1 paise / unit for every increase / decrease of Rs. 2 Lakh per MW of project capacity (AC) in the Project Cost which shall be allowed incurred upto the Schedulded Commercial Operation Date upon submission of proof of payment made by the Power Producer towards safeguard duty and/or anti-dumping duty to the concerned Authority and/or custom duty and/or Goods and Services Tax and with due approval of GERC. This increase / decrease in tariff due to this change in cost of solar PV modules shall be limited to actual DC capacity or 150% (One hundred & fifty percent) of contracted AC capacity, whichever is lower. 9.2.3 The Power Procurer / GUVNL or the Power Producer, as the case may be, shall provide the other Party with a certificate stating that the adjustment in the Tariff Payment is directly as a result of the Change in Law and shall provide supporting documents to substantiate the same and such certificate shall correctly reflect the increase or decrease in costs. 9.2.4 The revised tariff shall be effective from the date of such Change in Law as approved by GERC, the Parties hereto have caused this Agreement to be executed by their fully authorised officers, and copies delivered to each Party, as of the day and year first above stated.

Appears in 2 contracts

Samples: Power Purchase Agreement (Ppa), Power Purchase Agreement

Relief for Change in Law. 9.2.1 In case Change in Law Law. on account of 9.1.1 (a) above results in the Power Producer’s costs directly attributable to the Project being decreased or increased by one percent (1%), of the estimated revenue from the Electricity for the Contract Year for which such adjustment becomes applicable or more, during Operation Period, the Tariff Payment to the Power Producer shall be appropriately increased or decreased with due approval of GERC. 9.2.2 In case of Change in Law resulting on account of 9.1 9.1.1 (b) above, the Power Producer shall be allowed an increase / increase/decrease in tariff of 1 paise / paise/unit for every increase / increase/decrease of Rs. 2 Lakh per MW of project capacity (AC) in the Project Cost which shall be allowed incurred upto the Scheduled Commercial Operation Date upon submission of proof of payment made by the Power Producer towards safeguard duty and/or anti-dumping duty and/or custom duty to the concerned Authority and with due approval of GERC. This increase/decrease in tariff due to this change in cost of solar PV modules shall be limited to actual DC capacity or 150% (One hundred & fifty percent) of contracted AC capacity, whichever is lower. 9.2.3 The Power Procurer / GUVNL DISCOM or the Power Producer, as the case may be, shall provide the other Party with a certificate stating that the adjustment in the Tariff Payment is directly as a result of the Change in Law and shall provide supporting documents including proof of payment to substantiate the same and such certificate shall correctly reflect the increase or decrease in costs. 9.2.4 The revised tariff shall be effective from the date of such Change in Law as approved by GERC, the Parties hereto have caused this Agreement to be executed by their fully authorised officers, and copies delivered to each Party, as of the day and year first above stated.

Appears in 2 contracts

Samples: Power Purchase Agreement (Ppa), Power Purchase Agreement (Ppa)

Relief for Change in Law. 9.2.1 In case Change in Law results in the Power Producer’s costs directly attributable to the Project being decreased or increased by one percent (1%), of the estimated revenue from the Electricity for the Contract Year for which such adjustment becomes applicable or more, during Operation Period, the Tariff Payment to the Power Producer shall be appropriately increased or decreased with due approval of GERC. 9.2.2 In case of Change in Law resulting on account of 9.1 9.1.1 (b) above, the Power Producer shall be allowed an increase / decrease in tariff of 1 paise / unit for every increase / decrease of Rs. 2 Lakh per MW of project capacity (AC) in the Project Cost incurred upto Scheduled Commercial Operation Date which shall be allowed upon submission of proof of payment made by the Power Producer towards safeguard duty and/or anti-dumping duty to the concerned Authority and/or custom duty and/or Goods and Services Tax and with due approval of GERC. This increase / decrease in tariff due to this change in cost of Solar PV modules shall be limited to actual DC capacity or 150% (one hundred and fifty percent) of contracted AC capacity, whichever is lower. 9.2.3 The Power Procurer / GUVNL or the Power Producer, as the case may be, shall provide the other Party with a certificate stating that the adjustment in the Tariff Payment is directly as a result of the Change in Law and shall provide supporting documents to substantiate the same and such certificate shall correctly reflect the increase or decrease in costs. 9.2.4 The revised tariff shall be effective from the date of such Change in Law as approved by GERC, the Parties hereto have caused this Agreement to be executed by their fully authorised officers, and copies delivered to each Party, as of the day and year first above stated.

Appears in 2 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement

Relief for Change in Law. 9.2.1 In case Change in Law on account of 9.1.1 (a) above results in the Power Producer’s costs directly attributable to the Project being decreased decrease or increased increase by one percent (1%), of ) in the estimated revenue from the Electricity for the Contract Year for which such adjustment becomes applicable or more, during Operation Period, the Tariff Payment to the Power Producer shall be appropriately increased or decreased with due approval of GERC. 9.2.2 In case of Change in Law resulting on account of 9.1 (b) above, the Power Producer shall be allowed an increase / decrease in tariff of 1 paise / unit for every increase / decrease of Rs. 2 Lakh per MW of project capacity (AC) in the Project Cost which shall be allowed upon submission of proof of payment made by the Power Producer towards safeguard duty and/or anti-dumping duty to the concerned Authority and with due approval of GERC. 9.2.3 The Power Procurer / GUVNL or the Power Producer, as the case may be, shall provide the other Party with a certificate stating that the adjustment in the Tariff Payment is directly as a result of the Change in Law and shall provide supporting documents to substantiate the same and such certificate shall correctly reflect the increase or decrease in costs. 9.2.4 The revised tariff shall be effective from the date of such Change in Law as approved by GERC, the Parties hereto have caused this Agreement to be executed by their fully authorised officers, and copies delivered to each Party, as of the day and year first above stated.

Appears in 1 contract

Samples: Power Purchase Agreement

Relief for Change in Law. 9.2.1 In case Change in Law on account of 9.1.1 (a) above results in the Power Producer’s costs directly attributable to the Project being decreased or increased by one percent (1%), of the estimated revenue from the Electricity for the Contract Year for which such adjustment becomes applicable or more, during Operation Period, the Tariff Payment to the Power Producer shall be appropriately increased or decreased with due approval of GERC. 9.2.2 In case of Change in Law resulting on account of 9.1 9.1.1 (b) above, the Power Producer shall be allowed an increase / decrease in tariff of 1 paise / unit for every increase / decrease of Rs. 2 Lakh per MW of project capacity (AC) in the Project Cost which shall be allowed upon submission of proof of payment made by the Power Producer towards safeguard duty and/or anti-dumping duty to the concerned Authority and with due approval of GERC. 9.2.3 The Power Procurer / GUVNL or the Power Producer, as the case may be, shall provide the other Party with a certificate stating that the adjustment in the Tariff Payment is directly as a result of the Change in Law and shall provide supporting documents to substantiate the same and such certificate shall correctly reflect the increase or decrease in costs. 9.2.4 The revised tariff shall be effective from the date of such Change in Law as approved by GERC, the Parties hereto have caused this Agreement to be executed by their fully authorised officers, and copies delivered to each Party, as of the day and year first above stated.

Appears in 1 contract

Samples: Power Purchase Agreement

AutoNDA by SimpleDocs

Relief for Change in Law. 9.2.1 In case Change in Law results in the Power Producer’s costs directly attributable to the Project being decreased or increased by one percent (1%), of the estimated revenue from the Electricity for the Contract Year for which such adjustment becomes applicable or more, during Operation Period, the Tariff Payment to the Power Producer shall be appropriately increased or decreased with due approval of GERC. 9.2.2 In case of Change in Law resulting on account of 9.1 9.1.1 (b) above, the Power Producer shall be allowed an increase / decrease in tariff of 1 paise / unit for every increase / decrease of Rs. 2 Lakh per MW of project capacity (AC) in the Project Cost incurred upto Scheduled Commercial Operation Date which shall be allowed upon submission of proof of payment made by the Power Producer towards safeguard duty and/or anti-anti- dumping duty and/or custom duty to the concerned Authority and with due approval of GERC. This increase / decrease in tariff due to this change in cost of Solar PV modules shall be limited to actual DC capacity or 150% (one hundred and fifty percent) of contracted AC capacity, whichever is lower. 9.2.3 The Power Procurer / GUVNL or the Power Producer, as the case may be, shall provide the other Party with a certificate stating that the adjustment in the Tariff Payment is directly as a result of the Change in Law and shall provide supporting documents to substantiate the same and such certificate shall correctly reflect the increase or decrease in costs. 9.2.4 The revised tariff shall be effective from the date of such Change in Law as approved by GERC, the Parties hereto have caused this Agreement to be executed by their fully authorised officers, and copies delivered to each Party, as of the day and year first above stated.

Appears in 1 contract

Samples: Power Purchase Agreement (Ppa)

Relief for Change in Law. 9.2.1 In case Change in Law on account of 9.1.1 (a) above results in the Power Producer’s costs directly attributable to the Project being decreased or increased by one percent (1%), of the estimated revenue from the Electricity for the Contract Year for which such adjustment becomes applicable or more, during Operation Period, the Tariff Payment to the Power Producer shall be appropriately increased or decreased with due approval of GERC. 9.2.2 In case of Change in Law resulting on account of 9.1 9.1.1 (b) above, the Power Producer shall be allowed an increase / decrease in tariff of 1 paise / unit for every increase / decrease of Rs. 2 Lakh per MW of project capacity (AC) in the Project Cost which shall be allowed upon submission of proof of payment made by the Power Producer towards safeguard duty and/or anti-dumping duty to the concerned Authority and with due approval of GERC. 9.2.3 The Power Procurer / GUVNL or the Power Producer, as the case may be, shall provide the other Party with a certificate stating that the adjustment in the Tariff Payment is directly as a result of the Change in Law and shall provide supporting documents to substantiate the same and such certificate shall correctly reflect the increase or decrease in costs. 9.2.4 The revised tariff shall be effective from the date of such Change in Law as approved by GERC, the Parties hereto have caused this Agreement to be executed by their fully authorised officers, and copies delivered to each Party, as of the day and year first above stated.

Appears in 1 contract

Samples: Power Purchase Agreement

Relief for Change in Law. 9.2.1 In case Change in Law results in the Power Producer’s costs directly attributable to the Project being decreased or increased by one percent (1%), of the estimated revenue from the Electricity for the Contract Year for which such adjustment becomes applicable or more, during Operation Period, the Tariff Payment to the Power Producer shall be appropriately increased or decreased with due approval of GERC. 9.2.2 In case of Change in Law resulting on account of 9.1 9.1.1 (b) above, the Power Producer shall be allowed an increase / decrease in tariff of 1 paise / unit for every increase / decrease of Rs. 2 Rs.2 Lakh per MW of project capacity (AC) in the Project Cost incurred upto Scheduled Commencement of Supply Date (SCSD) which shall be allowed upon submission of proof of payment made by the Power Producer towards safeguard duty and/or anti-dumping duty to the concerned Authority and/or custom duty and/or Goods and Services Tax and with due approval of GERC. This increase / decrease in tariff due to this change in cost of Solar PV modules shall be limited to actual DC capacity or 150% (one hundred and fifty percent) of contracted AC capacity, whichever is lower. 9.2.3 The Power Procurer / GUVNL or the Power Producer, as the case may be, shall provide the other Party with a certificate stating that the adjustment in the Tariff Payment is directly as a result of the Change in Law and shall provide supporting documents to substantiate the same and such certificate shall correctly reflect the increase or decrease in costs. 9.2.4 The revised tariff shall be effective from the date of such Change in Law as approved by GERC, the Parties hereto have caused this Agreement to be executed by their fully authorised officers, and copies delivered to each Party, as of the day and year first above stated.

Appears in 1 contract

Samples: Power Purchase Agreement (Ppa)

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!