Remedy and rectification of Defects and deficiencies. 15.2.1 Without prejudice to the provisions of Clause 15.2.2, the Contractor shall repair or rectify all Defects and deficiencies observed by the Authority Engineer during the Defects Liability Period within a period of 15 (fifteen) days from the date of notice issued by the Authority Engineer in this behalf, or within such reasonable period as may be determined by the Authority Engineer at the request of the Contractor, in accordance with Good Industry Practice. For the purpose of this clause, the time period of 15 days shall be applicable only to those Defects and Deficencies which are not affecting train operations of safety. For any defect noticed affecting train operation of train safety, the Contractor shall arrange to rectify it within such reasonable period as may be determined by the Authority Engineer. If the Contractor’s staffis not able to rectify any fault as decided by the Authority Engineer, the Authority will be at full liberty to make its own efforts to get such defects rectified at Contractor’s cost. 15.2.2 During a period of 2 (two) months from the date of issuance of Completion Certificate, the Contractor shall retain sufficient staff and spares at Project location for procuring prompt replacement, installation or re-installation of any defective parts. The spares for the purpose of this clause, shall be separate from any spares supplied within the scope of the Project.
Appears in 6 contracts
Samples: Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement
Remedy and rectification of Defects and deficiencies. 15.2.1 Without prejudice to the provisions of Clause 15.2.2, the Contractor shall repair or rectify all Defects and deficiencies observed by the Authority SPV’s Engineer during the Defects Liability Period within a period of 15 (fifteen) days from the date of notice issued by the Authority SPV’s Engineer in this behalf, or within such reasonable period as may be determined by the Authority SPV’s Engineer at the request of the Contractor, in accordance with Good Industry Practice. For the purpose of this clause, the time period of 15 days shall be applicable only to those Defects and Deficencies Deficiencies which are not affecting train operations of safety. For any defect noticed affecting train operation of train safety, the Contractor shall arrange to rectify it within such reasonable period as may be determined by the Authority EngineerSPV’s Engineer . If the Contractor’s staffis Contractor is not able to rectify any fault as decided by the Authority EngineerSPV’s Engineer , the Authority SPV will be at full liberty to make its own efforts to get such defects rectified at the Contractor’s cost.
15.2.2 During a period of 2 (two) months from the date of issuance of the Completion Certificate, the Contractor shall retain sufficient staff and spares at Project location for procuring prompt replacement, installation or re-installation of any defective partsparts of (a) the SCADA system; (b) traction sub-stations and switching posts and (c) EI system /Axle Counters/ Automatic Train protection system. The spares for the purpose of this clause, shall be separate from any spares supplied within the scope of the Project.
Appears in 1 contract
Samples: Epc Agreement
Remedy and rectification of Defects and deficiencies. 15.2.1 Without prejudice to the provisions of Clause 15.2.2, the Contractor shall repair or rectify all Defects and deficiencies observed by the Authority Engineer during the Defects Liability Period within a period of 15 (fifteen) days from the date of notice issued by the Authority Engineer in this behalfEngineer, or within such reasonable period as may be determined by the Authority Engineer at the request of the Contractor, in accordance with Good Industry Practice. For the purpose of this clause, the time period of 15 days shall be applicable only to those Defects and Deficencies which are not affecting train operations of safety. For any defect noticed affecting train operation of train safety, the Contractor Contrator shall arrange to rectify it within such reasonable period as may be determined by the Authority Engineer. If the Contractor’s staffis Contrator is not able to rectify any fault as decided by the Authority Engineer, the Authority will be at full liberty to make its own efforts to get such defects rectified at Contractor’s cost.
15.2.2 During a period of 2 (two) months from the date of issuance of Completion Certificate, the Contractor shall retain sufficient staff and spares at Project location for procuring prompt replacement, installation or re-installation of any defective partsparts of
(a) the SCADA system; (b) traction sub-stations and switching posts and (c) EI system /Axle Counters/ Automatic Train protection system. The spares for the purpose of this clause, shall be separate from any spares supplied within the scope of the Project.
Appears in 1 contract
Samples: Engineering, Procurement and Construction (Epc) Agreement
Remedy and rectification of Defects and deficiencies. 15.2.1 Without prejudice to the provisions of Clause 15.2.2, the Contractor shall repair or rectify all Defects and deficiencies observed by the Authority Engineer during the Defects Liability Period within a period of 15 (fifteen) days from the date of notice issued by the Authority Engineer in this behalf, or within such reasonable period as may be determined by the Authority Engineer at the request of the Contractor, in accordance with Good Industry Practice. For the purpose of this clause, the time period of 15 days shall be applicable only to those Defects and Deficencies which are not affecting train operations of safety. For any defect noticed affecting train operation of train safety, the Contractor shall arrange to rectify it within such reasonable period as may be determined by the Authority Engineer. If the Contractor’s staffis staff is not able to rectify any fault as decided by the Authority Engineer, the Authority will be at full liberty to make its own efforts to get such defects rectified at Contractor’s cost.
15.2.2 During a period of 2 (two) months from the date of issuance of Completion Certificate, the Contractor shall retain sufficient staff and spares at Project location for procuring prompt replacement, installation or re-installation of any defective parts. The spares for the purpose of this clause, shall be separate from any spares supplied within the scope of the Project.
Appears in 1 contract
Samples: Standard Engineering, Procurement and Construction (Epc) Agreement
Remedy and rectification of Defects and deficiencies. 15.2.1 Without prejudice to the provisions of Clause 15.2.2, the Contractor shall repair or rectify all Defects and deficiencies observed by the Authority Engineer during the Defects Liability Period within a period of 15 (fifteen) days from the date of notice issued by the Authority Engineer in this behalfEngineer, or within such reasonable period as may be determined by the Authority Engineer at the request of the Contractor, in accordance with Good Industry Practice. For the purpose of this clause, the time period of 15 days shall be applicable only to those Defects and Deficencies Deficiencies which are not affecting train operations of safety. For any defect noticed affecting train operation of train safety, the Contractor shall arrange to rectify it within such reasonable period as may be determined by the Authority Engineer. If the Contractor’s staffis Contractor is not able to rectify any fault as decided by the Authority Engineer, the Authority will be at full liberty to make its own efforts to get such defects rectified at Contractor’s cost.
15.2.2 During a period of 2 (two) months from the date of issuance of Completion Certificate, the Contractor shall retain sufficient staff and spares at Project location for procuring prompt replacement, installation or re-installation of any defective partsparts of (a) the SCADA system; (b) traction sub- stations and switching posts and (c) EI system / Axle Counters / Automatic Train Protection system. The spares for the purpose of this clause, shall be separate from any spares supplied within the scope of the Project.
Appears in 1 contract
Samples: Epc Agreement
Remedy and rectification of Defects and deficiencies. 15.2.1 Without prejudice to the provisions of Clause 15.2.2, the Contractor shall repair or rectify all Defects and deficiencies observed by the Authority Engineer during the Defects Liability Period within a period of 15 (fifteen) days from the date of notice issued by the Authority Engineer in this behalfEngineer, or within such reasonable period as may be determined by the Authority Engineer at the request of the Contractor, in accordance with Good Industry Practice. For the purpose of this clause, the time period of 15 days shall be applicable only to those Defects and Deficencies Deficiencies which are not affecting train operations of safety. For any defect noticed affecting train operation of train safety, the Contractor shall arrange to rectify it within such a reasonable period as may be determined by the Authority Engineer. If the Contractor’s staffis Contractor is not able to rectify any fault as decided by the Authority Engineer, the Authority will be at full liberty to make its own efforts to get such defects rectified at Contractor’s cost.
15.2.2 During a period of 2 (two) months from the date of issuance of Completion Certificate, the Contractor shall retain sufficient staff and spares at Project location for procuring prompt replacement, installation or re-installation of any defective partsparts of (a) the SCADA system; (b) traction sub- stations and switching posts and (c) EI system / Axle Counters / Automatic Train Protection system. The spares for the purpose of this clause, shall be separate from any spares supplied within the scope of the Project.