Common use of Reporting of Actual Generation Clause in Contracts

Reporting of Actual Generation. a. During the Guarantee Period, the Client shall collect energy output data for the System from the System’s DAS monitoring system and meters. Client shall provide EPC Contractor with the actual Monthly production in each Month during which this Agreement is in effect or shall provide EPC Contractor with read only, real-time access to its DAS monitoring system. The foregoing requirement for Client to provide Monthly production data to EPC Contractor shall commence as of the last day of the Month commencing after Final Completion and shall be forwarded to EPC Contractor via email to EPC Contractor by the third day of the following calendar Month, if real-time access to its monitoring equipment is not made available to EPC Contractor. b. Within thirty (30) days following the end of the Guarantee Period, the Client shall calculate the cumulative Actual Generation and shall send a written notice to EPC Contractor which shall (i) specify the Guaranteed Level; (ii) the Actual Generation and IEER; (iii) include printouts technical information, computations, data, electronic presentations (but not including native files or live data) used or developed by the Client in determining the Actual Generation and IEER; and (iv) include a form of invoice payable by the EPC Contractor for the Performance Guarantee Damages, if any, resulting from the calculation of the Performance Guarantee Damages made in accordance with this Schedule #7.

Appears in 3 contracts

Samples: Epc Agreement, Epc Agreement, Epc Agreement

AutoNDA by SimpleDocs

Reporting of Actual Generation. a. 4.1 During the Guarantee Period, the Client shall collect energy output data for the System from the System’s DAS monitoring system and meters. Client shall provide EPC Contractor with the actual Monthly production in each Month during which this Agreement is in effect or shall provide EPC Contractor with read only, real-time access to its DAS monitoring system. The foregoing requirement for Client to provide Monthly production data to EPC Contractor shall commence as of the last day of the Month commencing after Final Completion and shall be forwarded to EPC Contractor via email to EPC Contractor by the third day of the following calendar Month, if real-time access to its monitoring equipment is not made available to EPC Contractor. b. 4.2 Within thirty (30) days following the end of the Guarantee Period, the Client shall calculate the cumulative Actual Generation and shall send a written notice to EPC Contractor which shall (i) specify the Guaranteed Level; (ii) the Actual Generation and IEER; (iii) include printouts technical information, computations, data, electronic presentations (but not including native files or live data) used or developed by the Client in determining the Actual Generation and IEER; and (iv) include a form of invoice payable by the EPC Contractor for the Performance Guarantee Damages, if any, resulting from the calculation of the Performance Guarantee Damages made in accordance with this Schedule #7.

Appears in 2 contracts

Samples: Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement

Reporting of Actual Generation. a. 4.1 During the Guarantee Period, the Client shall collect energy output data for the System from the System’s DAS monitoring system and meters. Client shall provide EPC Contractor with the actual Monthly production in each Month during which this Agreement is in effect or shall provide EPC Contractor with read only, real-time access to its DAS monitoring system. The foregoing requirement for Client to provide Monthly production data to EPC Contractor shall commence as of the last day of the Month commencing after Final Completion and shall be forwarded to EPC Contractor via email to EPC Contractor by the third day of the following calendar Month, if real-time access to its monitoring equipment is not made available to EPC Contractor. b. 4.2 Within thirty (30) days following the end of the Guarantee Period, the Client shall calculate the cumulative Actual Generation and shall send a written notice to EPC Contractor which shall (i) specify the Guaranteed Level; (ii) the Actual Generation and IEER; (iii) include printouts technical information, computations, data, electronic presentations (but not including native files or live data) used or developed by the Client in determining the Actual Generation and IEER; and (iv) include a form of invoice payable by the EPC Contractor for the Performance Guarantee Damages, if any, resulting from the calculation of the Performance Guarantee Damages made in accordance with this Schedule #7.

Appears in 2 contracts

Samples: Epc Agreement, Epc Agreement

Reporting of Actual Generation. a. During the Guarantee Period, the Client shall collect energy output data for the System from the System’s DAS monitoring system and meters. Client shall provide EPC Contractor with the actual Monthly production in each Month during which this Agreement is in effect or shall provide EPC Contractor with read only, real-time access to its DAS monitoring system. The foregoing requirement for Client to provide Monthly production data to EPC Contractor shall commence as of the last day of the Month commencing after Final Completion and shall be forwarded to EPC Contractor via email to EPC Contractor by the third day of the following calendar Month, if real-time access to its monitoring equipment is not made available to EPC Contractor. b. Within thirty (30) days Days following the end of the Guarantee Period, the Client shall calculate the cumulative Actual Generation and shall send a written notice to EPC Contractor which shall (i) specify the Guaranteed Level; (ii) the Actual Generation and IEER; (iii) include printouts technical information, computations, data, electronic presentations (but not including native files or live data) used or developed by the Client in determining the Actual Generation and IEER; and (iv) include a form of invoice payable by the EPC Contractor for the Performance Guarantee Damages, if any, resulting from the calculation of the Performance Guarantee Damages made in accordance with this Schedule #7.

Appears in 2 contracts

Samples: Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement

Reporting of Actual Generation. a. During the Guarantee Period, the Client shall collect energy output data for the System from the System’s DAS monitoring system and meters. Client shall provide EPC Contractor with the actual Monthly production in each Month during which this Agreement is in effect or shall provide EPC Contractor with read only, real-time access to its DAS monitoring system. The foregoing requirement for Client to provide Monthly production data to EPC Contractor shall commence as of the last day of the Month commencing after Final Completion and shall be forwarded to EPC Contractor via email to EPC Contractor by the third day of the following calendar Month, if real-time access to its monitoring equipment is not made available to EPC Contractor. b. . Within thirty (30) days following the end of the Guarantee Period, the Client shall calculate the cumulative Actual Generation and shall send a written notice to EPC Contractor which shall (i) specify the Guaranteed Level; (ii) the Actual Generation and IEER; (iii) include printouts technical information, computations, data, electronic presentations (but not including native files or live data) used or developed by the Client in determining the Actual Generation and IEER; and (iv) include a form of invoice payable by the EPC Contractor for the Performance Guarantee Damages, if any, resulting from the calculation of the Performance Guarantee Damages made in accordance with this Schedule #7. Performance Guarantee Damages.

Appears in 1 contract

Samples: Epc Agreement

AutoNDA by SimpleDocs

Reporting of Actual Generation. a. 4.1 During the Guarantee Period, the Client shall collect energy output data for the System from the System’s DAS monitoring system and meters. Client shall provide EPC Contractor with the actual Monthly production in each Month during which this Agreement is in effect or shall provide EPC Contractor with read only, real-time access to its DAS monitoring system. The foregoing requirement for Client to provide Monthly production data to EPC Contractor shall commence as of the last day of the Month commencing after Final Completion and shall be forwarded to EPC Contractor via email to EPC Contractor by the third day of the following calendar Month, if real-time access to its monitoring equipment is not made available to EPC Contractor. b. 4.2 Within thirty (30) days following the end of the Guarantee Period, the Client shall calculate the cumulative Actual Generation and shall send a written notice to EPC Contractor which shall (i) specify the Guaranteed Level; (ii) the Actual Generation and IEER; (iii) include printouts technical information, computations, data, electronic presentations (but not including native files or live data) used or developed by the Client in determining the Actual Generation and IEER; and (iv) include a form of invoice payable by the EPC Contractor for the Performance Guarantee Damages, if any, resulting from the calculation of the Performance Guarantee Damages made in accordance with this Schedule #720.

Appears in 1 contract

Samples: Engineering, Procurement and Construction Agreement

Reporting of Actual Generation. a. During the Guarantee Period, the Client shall collect energy output data for the System from the System’s DAS monitoring system and meters. Client shall provide EPC Contractor with the actual Monthly production in each Month during which this Agreement is in effect or shall provide EPC Contractor with read only, real-time access to its DAS monitoring system. The foregoing requirement for Client to provide Monthly production data to EPC Contractor shall commence as of the last day of the Month commencing after Final Completion and shall be forwarded to EPC Contractor via email to EPC Contractor by the third day of the following calendar Month, if real-time access to its monitoring equipment is not made available to EPC Contractor. b. . Within thirty (30) days following the end of the Guarantee Period, the Client shall calculate the cumulative Actual Generation and shall send a written notice to EPC Contractor which shall (i) specify the Guaranteed Level; (ii) the Actual Generation and IEER; (iii) include printouts technical information, computations, data, electronic presentations (but not including native files or live data) used or developed by the Client in determining the Actual Generation and IEER; and (iv) include a form of invoice payable by the EPC Contractor for the Performance Guarantee Damages, if any, resulting from the calculation of the Performance Guarantee Damages made in accordance with this Schedule #7.

Appears in 1 contract

Samples: Epc Agreement

Reporting of Actual Generation. a. During the Guarantee Period, the Client shall collect energy output data for the System from the System’s DAS monitoring system and meters. Client shall provide EPC Contractor with the actual Monthly production in each Month during which this Agreement is in effect or shall provide EPC Contractor with read only, real-time access to its DAS monitoring system. The foregoing requirement for Client to provide Monthly production data to EPC Contractor shall commence as of the last day of the Month commencing after Final Completion and shall be forwarded to EPC Contractor via email to EPC Contractor by the third day of the following calendar Month, if real-time access to its monitoring equipment is not made available to EPC Contractor. b. Within thirty (30) days Days following the end of the Guarantee Period, the Client shall calculate the cumulative Actual Generation and shall send a written notice to EPC Contractor which shall (i) specify the Guaranteed Level; (ii) the Actual Generation and IEER; (iii) include printouts technical information, computations, data, electronic presentations (but not including native files or live data) used or developed by the Client in determining the Actual Generation and IEER; and (iv) include a form of invoice payable by the EPC Contractor for the Performance Guarantee Damages, if any, resulting from the calculation of the Performance Guarantee Damages made in accordance with this Schedule #720.

Appears in 1 contract

Samples: Engineering, Procurement and Construction Agreement