Reporting Progress of the Installation Services. a. Periodic Estimates/Schedule Updates. (i) CONTRACTOR shall, based on the weekly or bi-weekly Project meetings (as specified above) with 2-3 week look ahead basis, submit to DCAMM (on forms and in the manner prescribed by DCAMM) an estimate showing the total amount of New Equipment/Systems installed to the time of such estimate and the value thereof as approved by DCAMM. It shall be the sole responsibility of CONTRACTOR to deliver or cause to be delivered to DCAMM said periodic estimate in proper form, approved as provided above and mathematically correct. All periodic estimates shall contain such certifications and other evidence supporting CONTRACTOR's progress with the Installation Services. DCAMM’s review of the periodic estimate is intended to be for verification of the status of the Installation Services and does not constitute acceptance of the Installation Services or any payment or other obligations of DCAMM, unless otherwise provided for in Schedule B-6: Payment Terms, Total Contract Value, and Energy Savings. (ii) Each periodic estimate shall constitute CONTRACTOR's representation that the materials, supplies and New Equipment/Systems have been installed and are insured in accordance with the provisions of this Contract. (iii) DCAMM may make reasonable changes in any required periodic estimate submitted by CONTRACTOR. (iv) DCAMM shall not be obligated to make progress payments for the amount of Services included in the periodic estimates. (v) CONTRACTOR’s failure to provide the periodic estimates required in this Section may constitute a “Material Event of Default by CONTRACTOR” as defined in Section 50: Default.
Appears in 2 contracts
Samples: Energy Services Agreement, Energy Services Agreement
Reporting Progress of the Installation Services. a. Periodic Estimates/Schedule Updates.
(i) CONTRACTOR shall, based on the weekly or bi-weekly Project project meetings (as specified above) with 2-3 week look ahead basis, submit to DCAMM (on forms and in the manner prescribed by DCAMM) an estimate showing the total amount of New Equipment/Systems installed to the time of such estimate and the value thereof as approved by DCAMM. It shall be the sole responsibility of CONTRACTOR to deliver or cause to be delivered to DCAMM said periodic estimate in proper form, approved as provided above and mathematically correct. All periodic estimates shall contain such certifications and other evidence supporting CONTRACTOR's progress with the Installation Services. DCAMM’s review of the periodic estimate is intended to be for verification of the status of the Installation Services and does not constitute acceptance of the Installation Services or any payment or other obligations of DCAMM, unless otherwise provided for in Schedule B-6: Payment Terms, ; Total Contract Value, and Energy Savings.
(ii) Each periodic estimate shall constitute CONTRACTOR's representation that the materials, supplies and New Equipment/Systems have been installed and are insured in accordance with the provisions of this Contract.
(iii) DCAMM may make reasonable changes in any required periodic estimate submitted by CONTRACTOR.
(iv) DCAMM shall not be obligated to make progress payments for the amount of Services included in the periodic estimates.
(v) CONTRACTOR’s failure to provide the periodic estimates required in this Section may constitute a “Material Event of Default by CONTRACTOR” CONTRACTOR as defined in Section 50: Default.
Appears in 2 contracts
Samples: Energy Services Agreement, Energy Services Agreement
Reporting Progress of the Installation Services. a. Periodic Estimates/Schedule Updates.
(i) CONTRACTOR shall, based on the weekly or bi-weekly Project project meetings (as specified above) with 2-3 week look ahead basis, submit to DCAMM (on forms and in the manner prescribed by DCAMM) an estimate showing the total amount of New Equipment/Systems installed to the time of such estimate and the value thereof as approved by DCAMM. It shall be the sole responsibility of CONTRACTOR to deliver or cause to be delivered to DCAMM said periodic estimate in proper form, approved as provided above and mathematically correct. All periodic estimates shall contain such certifications and other evidence supporting CONTRACTOR's progress with the Installation Services. DCAMM’s review of the periodic estimate is intended to be for verification of the status of the Installation Services and does not constitute acceptance of the Installation Services or any payment or other obligations of DCAMM, unless otherwise provided for in Schedule B-6: Payment Terms, ; Total Contract Value, and Energy Savings.
(ii) Each periodic estimate shall constitute CONTRACTOR's representation that the materials, supplies and New Equipment/Systems have been installed and are insured in accordance with the provisions of this Contract.
(iii) DCAMM may make reasonable changes in any required periodic estimate submitted by CONTRACTOR.
(iv) DCAMM shall not be obligated to make progress payments for the amount of Services included in the periodic estimates.
(v) CONTRACTOR’s failure to provide the periodic estimates required in this Section may constitute a “Material Event of Default default by CONTRACTOR” as defined in CONTRACTOR under Section 5051: DefaultTermination.
Appears in 1 contract
Samples: Energy Services Agreement
Reporting Progress of the Installation Services. a. Periodic Estimates/Schedule Updates.
(i) CONTRACTOR shall, based on the weekly or bi-weekly Project meetings (as specified above) with 2-3 week look ahead basis, submit to DCAMM (on forms and in the manner prescribed by DCAMM) an estimate showing the total amount of New Equipment/Systems installed to the time of such estimate and the value thereof as approved by DCAMM. It shall be the sole responsibility of CONTRACTOR to deliver or cause to be delivered to DCAMM said periodic estimate in proper form, approved as provided above and mathematically correct. All periodic estimates shall contain such certifications and other evidence supporting CONTRACTOR's progress with the Installation Services. DCAMM’s review of the periodic estimate is intended to be for verification of the status of the Installation Services and does not constitute acceptance of the Installation Services or any payment or other obligations of DCAMM, unless otherwise provided for in Schedule B-6: Payment Terms, Total Contract Value, and Energy Savings.
(ii) Each periodic estimate shall constitute CONTRACTOR's representation that the materials, supplies and New Equipment/Systems have been installed and are insured in accordance with the provisions of this Contract.
(iii) DCAMM may make reasonable changes in any required periodic estimate submitted by CONTRACTOR.
(iv) DCAMM shall not be obligated to make progress payments for the amount of Services included in the periodic estimates.
(v) CONTRACTOR’s failure to provide the periodic estimates required in this Section may constitute a “Material Event of Default default by CONTRACTOR” as defined in CONTRACTOR under Section 5051: DefaultTermination.
Appears in 1 contract
Samples: Energy Services Agreement