REQUIREMENTS FOR NOTICE OF CLAIM. The notice of claim shall clearly state the Contractor’s intention to make claim and the reasons why the Contractor believes that additional compensation, changes or an extension of time may be remedies to which it is entitled. At a minimum, it shall provide the following: 7.25.4.1 Date of the protested order, decision or action; 7.25.4.2 The nature and circumstances which caused the claim; 7.25.4.3 The contract provision(s) that support the claim; 7.25.4.4 The estimated dollar cost, if any, of the protested work and how that estimate was determined; and 7.25.4.5 An analysis of the progress schedule showing the schedule change or disruption if the Contractor is asserting a schedule change or disruption.
Appears in 16 contracts
Samples: Contract for Goods or Services, Contract for Goods or Services, Contract for Goods or Services
REQUIREMENTS FOR NOTICE OF CLAIM. The notice of claim shall clearly state the Contractor’s intention to make claim and the reasons why the Contractor believes that additional compensation, changes or an extension of time may be remedies to which it is entitled. At a minimum, it shall provide the following:
7.25.4.1 Date of the protested order, decision or action;
7.25.4.2 The nature and circumstances which caused the claim;
7.25.4.3 The contract provision(s) that support the claim;
7.25.4.4 The estimated dollar cost, if any, of the protested work and how that estimate was determined; and
7.25.4.5 An analysis of the progress schedule showing the schedule change or disruption if the Contractor is asserting a schedule change or disruption.
7.25.5 If the protest or claim is continuing, the information required in Subsection 7.25.4 REQUIREMENTS FOR NOTICE OF CLAIMS above shall be supplemented as requested by the Project Manager.