Requirements for Record Documents. The Contractor shall maintain at the Site one copy of all Drawings, Specifications, addenda, approved submittals, contract modifications, and all Project correspondence. The Contractor shall keep current and maintain Drawings and Specifications in good order with postings and markings to record actual conditions of Work and show and reference all changes made during construction. The Contractor shall provide Owner and A/E access to these documents. 6.2.1 The Contractor shall maintain the record set of Drawings and Specifications which reflect the "As Constructed" conditions and representations of the Work performed, whether it be directed by addendum, Change Order or otherwise. The Contractor shall make available all records prescribed herein for reference and examination by the Owner and its representatives and agents. 6.2.2 The Contractor shall update the "As-Constructed" Drawings and Specifications monthly prior to submission of periodic partial pay estimates. Failure to maintain such records constitutes cause for denial of a progress payment otherwise due. 6.2.3 Prior to requesting the Substantial Completion Inspection by the ODR and A/E, the Contractor shall furnish the ODR a complete set of the marked up “As-Constructed” set maintained at the Site and one photocopy of same. Concurrently with furnishing these record drawings, the Contractor shall furnish a preliminary copy of each operating and maintenance manual (O&M) required by the Contract Documents, for review by the A/E and the ODR. 6.2.4 Once determined acceptable, the Contractor shall provide to Owner mylar prints of professionally drafted “As-Constructed” drawings, along with an electronic copy on CD, “As-Constructed” specifications in bound volume(s) along with an electronic copy on CD, two sets of photocopies or prints of the mylar “As-Constructed” drawings, two sets of operating and maintenance manuals, two sets of approved submittals, and other record documents as required elsewhere in the Contract Documents. All electronic copies shall be provided in a format acceptable to the ODR.
Appears in 34 contracts
Samples: Construction Contract, Construction Contract, Construction Management Agreement
Requirements for Record Documents. The Contractor shall maintain shall:
6.2.1 Maintain at the Site one copy of all Drawings, Specifications, addenda, approved submittals, contract Contract modifications, and all Project correspondence. The Contractor shall keep Keep current and maintain Drawings and Specifications in good order with postings and markings to record actual conditions of Work and show and reference all changes made during construction. The Contractor shall provide Provide Owner and A/E access to these documents.
6.2.1 The Contractor shall maintain 6.2.2 Maintain the record set of Drawings and Specifications Record Documents which reflect the "As Constructed" actual field conditions and representations of the Work performed, whether it be directed by addendum, Change Order or otherwise. The Contractor shall make Make available the Record Documents and all records prescribed herein for reference and examination by the Owner and its representatives and agents.
6.2.2 The Contractor shall update 6.2.3 Update the "As-Constructed" Drawings and Specifications Record Documents at least monthly prior to submission of periodic partial pay estimates. Failure to maintain such records current Record Documents constitutes cause for denial of a progress payment otherwise due.
6.2.3 6.2.4 Prior to requesting the Substantial Completion Inspection by the ODR and A/E, the inspection Contractor shall furnish the ODR a complete set copy of the marked its marked-up “As-Constructed” set maintained at the Site Record Documents and one photocopy of same. Concurrently with furnishing these record drawings, the Contractor shall furnish a preliminary copy of each instructional manual, maintenance and operating manual, parts catalog, wiring diagrams, spare parts, specified written warranties and maintenance manual (O&M) required by the Contract Documentslike publications, or parts for review by the A/E and the ODR.
6.2.4 Once determined acceptableall installed equipment, the Contractor shall provide to Owner mylar prints of professionally drafted “As-Constructed” drawings, along with an electronic copy on CD, “As-Constructed” specifications in bound volume(s) along with an electronic copy on CD, two sets of photocopies or prints of the mylar “As-Constructed” drawings, two sets of operating and maintenance manuals, two sets of approved submittalssystems, and other record documents like items and as required elsewhere described in the Contract Documents. All .
6.2.5 Once determined acceptable by ODR with input from A/E, provide one (1) reproducible copy and one (1) electronic copies shall be provided media copy in a format acceptable to the ODRODR `of all Record Documents, unless otherwise required by the Owner’s Special Conditions.
6.2.6 Contractor shall be responsible for updating the Record Documents for all Contractor initiated documents and changes to the Contract Documents due to coordination and actual field conditions, including RFIs.
6.2.7 A/E shall be responsible for updating the Record Documents for any addenda, Change Orders, A/E supplemental instructions and any other alterations to the Contract Documents generated by A/E or Owner.
Appears in 20 contracts
Samples: Construction Services Agreement, Construction Services Agreement, Construction Manager at Risk Agreement
Requirements for Record Documents. The Contractor shall maintain at the Site one copy of all Drawings, Specifications, addenda, approved submittalsSubmittals, contract Contract modifications, and all Project correspondence. The Contractor shall keep current and maintain Drawings and Specifications in good order with postings and markings to record actual conditions of Work and show and reference all changes made during construction. The Contractor shall provide Owner and A/E AE access to these documents.
6.2.1 The Contractor shall maintain the this record set of Drawings and Specifications which reflect the "As Constructed" conditions and representations of the Work performed, whether it be directed by addendum, Change Order or otherwise. The Contractor shall make available all records prescribed herein for reference and examination by the Owner and its representatives and agents.
6.2.2 The Contractor shall update the "As-Constructed" Drawings and Specifications monthly prior to submission of periodic partial pay estimates. Failure Contractor’s failure to maintain such records constitutes cause for denial of a progress payment otherwise due.
6.2.3 Prior to requesting the Substantial Completion Inspection by the ODR and A/EAE, the Contractor shall furnish the ODR a complete set of the marked up “As-Constructed” set maintained at the Site site and one photocopy of same. Concurrently with furnishing these record drawings, the Contractor shall furnish a preliminary copy of each operating and maintenance manual (O&M) required by the Contract Documents, for review by the A/E AE and the ODR.
6.2.4 Once determined acceptable, the Contractor shall provide to Owner mylar one set of prints of professionally drafted “As-Constructed” drawings, along with an electronic copy on CD, “As-As- Constructed” specifications in bound volume(s) along with an electronic copy on CD, two sets of photocopies or prints of the mylar “As-Constructed” drawings, two sets of operating and maintenance manuals, two sets of approved submittals, and other record documents as required elsewhere in the Contract Documents. All electronic copies shall be provided in a format acceptable to the ODR.
Appears in 1 contract
Samples: Contract
Requirements for Record Documents. The Contractor shall maintain shall:
5.2.1 Maintain at the Site one copy of all Drawings, Specifications, addenda, approved submittals, contract Contract modifications, and all Project correspondence. The Contractor shall keep Keep current and maintain Drawings and Specifications in good order with postings and markings to record actual conditions of Work and show and reference all changes made during construction. The Contractor shall provide Owner Provide City and A/E access to these documents.
6.2.1 The Contractor shall maintain 5.2.2 Maintain the record set of Drawings Record Documents including Drawings, Specifications and Specifications other materials which reflect the "As Constructed" actual field conditions and representations of the Work performed, whether it be directed by addendum, Change Order or otherwise. The Contractor shall make Make available all records prescribed herein for reference and examination by the Owner City and its representatives and agents.
6.2.2 The Contractor shall update 5.2.3 Update the "As-Constructed" Drawings and Specifications Record Documents at least monthly prior to submission of periodic partial pay estimates. Failure to maintain such records current Record Documents constitutes cause for denial of a progress payment otherwise due.
6.2.3 5.2.4 Prior to requesting the Substantial Completion Inspection by the ODR and A/E, the inspection Contractor shall furnish the ODR a complete set copy of the marked its marked-up “As-Constructed” set maintained at the Site Record Documents and one photocopy of same. Concurrently with furnishing these record drawings, the Contractor shall furnish a preliminary copy of each instructional manual, maintenance and operating manual, parts catalog, wiring diagrams, spare parts, specified written warranties and maintenance manual (O&M) required by the Contract Documentslike publications, or parts for review by the A/E and the ODR.
6.2.4 Once determined acceptableall installed equipment, the Contractor shall provide to Owner mylar prints of professionally drafted “As-Constructed” drawings, along with an electronic copy on CD, “As-Constructed” specifications in bound volume(s) along with an electronic copy on CD, two sets of photocopies or prints of the mylar “As-Constructed” drawings, two sets of operating and maintenance manuals, two sets of approved submittalssystems, and other record documents like items and as required elsewhere described in the Contract Documents. All (Unexecuted samples of the aforementioned documentation may be reviewed by City when the absence of substantial completion transactions preclude execution; however, Contractor remains obligated to provide fully executed copies of such materials prior to final payment.)
5.2.5 Once determined acceptable by City with input from A/E, provide one (1) reproducible copy and one (1) electronic copies media copy of all Record Documents, unless otherwise required by the Supplementary General Conditions or Special Conditions.
5.2.6 Contractor shall be provided in a format acceptable responsible for updating the Record Documents for all Contractor initiated documents and changes to the ODRContract Documents due to coordination and actual field conditions, including RFIs.
5.2.7 A/E shall be responsible for updating the Record Documents for any addenda, Change Orders, A/E supplemental instructions and any other alterations to the Contract Documents generated by A/E or City.
Appears in 1 contract
Samples: Design Build Services Agreement
Requirements for Record Documents. 4.8.1 The Contractor shall maintain at the Site site one copy of all Drawings, Specifications, addendaAddenda, approved submittals, contract modificationsShop Drawings and Contract Modifications, and all Project project correspondence. The Contractor shall keep current and maintain Drawings and Specifications in good order with postings and markings marked to record actual conditions of Work and show and reference all changes made during construction. The Contractor shall provide keep on the site of Work a copy of the current and updated Contract Drawings and Specifications and shall at all times give the Owner or its representatives and A/E agents access to these documentsthereto.
6.2.1 The 4.8.2 Further, the Contractor shall maintain the this record set of Drawings drawings and Specifications specifications which reflect the "As As-Constructed" conditions and representations of the Work performed, whether it be directed by addendumAddendum, Change Order or otherwise. The Contractor shall make available all All records prescribed herein shall be made available for reference and examination by the Owner and its representatives and agents.
6.2.2 4.8.3 The Contractor shall update the "As-Constructed" Drawings drawing and Specifications specification set monthly prior to submission of periodic partial pay estimates. Failure to maintain such records constitutes shall constitute cause for denial of a progress payment otherwise due.
6.2.3 4.8.4 Prior to requesting the Substantial Completion Inspection by the ODR Owner and AArchitect/EEngineer, the Contractor shall furnish the ODR a complete set of the marked up "xxxx-up" “As-Constructed” set maintained at the Site site and one photocopy of same. Concurrently with furnishing these preliminary record drawingsdocuments, the Contractor shall also furnish a preliminary copy of each operating and maintenance manual (O&M) required by the Contract Documentscontract documents, for review by the AArchitect/E Engineer and the ODROwner.
6.2.4 4.8.5 Once determined acceptable, the Contractor shall provide to Owner mylar prints data files of electronically scanned color images of professionally drafted “As-Constructed” drawings, along with an electronic copy on CD, “As-Constructed” specifications in bound volume(s) along with an electronic copy on CD, two sets of photocopies or prints of the mylar “As-Constructed” drawings, two sets of operating and maintenance manuals, two sets of approved submittals, and other record documents as required elsewhere in the Contract Documents. All electronic copies shall be provided in a format acceptable to the ODRcontract documents.
Appears in 1 contract
Samples: Construction Manager Agreement
Requirements for Record Documents. The Contractor CM-at-Risk shall maintain at the Site one copy of all Drawings, Specifications, addenda, approved submittalsSubmittals, contract Contract modifications, and all Project correspondence. The Contractor CM-at-Risk shall keep current and maintain Drawings and Specifications in good order with postings and markings to record actual conditions of Work and show and reference all changes made during construction. The Contractor CM-at-Risk shall provide Owner and A/E AE access to these documents.
6.2.1 The Contractor CM-at-Risk shall maintain the this record set of Drawings and Specifications which reflect the "As Constructed" conditions and representations of the Work performed, whether it be directed by addendum, Change Order or otherwise. The Contractor CM-at-Risk shall make available all records prescribed herein for reference and examination by the Owner and its representatives and agents.
6.2.2 The Contractor CM-at-Risk shall update the "As-Constructed" Drawings and Specifications monthly prior to submission of periodic partial pay estimates. Failure CM-at-Risk’s failure to maintain such records constitutes cause for denial of a progress payment otherwise due.
6.2.3 Prior to requesting the Substantial Completion Inspection by the ODR and A/EAE, the Contractor CM-at- Risk shall furnish the ODR a complete set of the marked up “As-Constructed” set maintained at the Site site and one photocopy of same. Concurrently with furnishing these record drawings, the Contractor CM-at-Risk shall furnish a preliminary copy of each operating and maintenance manual (O&M) required by the Contract Documents, for review by the A/E AE and the ODR.
6.2.4 Once determined acceptable, the Contractor CM-at-Risk shall provide to Owner mylar one set of prints of professionally drafted “As-Constructed” drawings, along with an electronic copy on CD, “As-As- Constructed” specifications in bound volume(s) along with an electronic copy on CD, two sets of photocopies or prints of the mylar “As-Constructed” drawings, two sets of operating and maintenance manuals, two sets of approved submittals, and other record documents as required elsewhere in the Contract Documents. All electronic copies shall be provided in a format acceptable to the ODR.