Right to Open Up. 13.3 Subject to Clause 13.4, the Authority's Representative shall have the right at any time prior to the Actual Completion Date to request Project Co to open up and inspect any part or parts of the Works where the Authority's Representative reasonably believes that such part or parts of the Works is or are defective and Project Co shall comply with such request.
Appears in 1 contract
Samples: www1.ayrshire.ac.uk
Right to Open Up. 13.3 Subject to Clause 13.413.4 (Right to Open Up), the Authority's Representative shall have the right at any time prior to the issue of the Permit to Use [a Phase Actual Completion Date Date] to request Project Co to open up and inspect any part or parts of the Works [relating to the relevant Phase] where the Authority's Representative reasonably believes that such part or parts of the Works [relating to the relevant Phase] is or are defective and Project Co shall comply with such request.
Appears in 1 contract
Samples: llyw.cymru
Right to Open Up. 13.3 Subject to Clause 13.413.4 (Right to Open Up), the Authority's Representative shall have the right at any time prior to the Actual Completion Date [a Phase Actual Completion Date] to request Project Co to open up and inspect any part or parts of the Works [relating to the relevant Phase] where the Authority's Representative reasonably believes that such part or parts of the Works [relating to the relevant Phase] is or are defective and Project Co shall comply with such request.
Appears in 1 contract
Samples: gov.wales
Right to Open Up. 13.3 Subject to Clause 13.4, the Authority's Representative shall have the right at any time prior to the Actual Completion Date [a Phase Actual Completion Date] to request Project Co to open up and inspect any part or parts of the Works [relating to the relevant Phase] where the Authority's Representative reasonably believes that such part or parts of the Works [relating to the relevant Phase] is or are defective and Project Co shall comply with such request.
Appears in 1 contract
Samples: Agreement
Right to Open Up. 13.3 Subject to Clause 13.4, the Authority's Representative shall have the right at any time prior to the issue of the Permit to Use [a Phase Actual Completion Date Date] to request Project Co to open up and inspect any part or parts of the Works [relating to the relevant Phase] where the Authority's Representative reasonably believes that such part or parts of the Works [relating to the relevant Phase] is or are defective and Project Co shall comply with such request.
Appears in 1 contract
Samples: Agreement