SAFETY, SECURITY AND PROTECTION OF THE ENVIRONMENT. Add Sub-Clause-paragraph (d) of Sub-Clause 19 as follows: Notwithstanding the Contractor’s obligation under Sub-Clause-paragraph (a), (b) and 9(c) of Sub-Clause 19.1 of the Conditions of Contract, the Contractor shall observe the following measures with a view to reducing or elimination adverse environmental effects by the site works: (i) All quarries and borrow pits shall be filled and landscaped to their original state after extraction of construction material
Appears in 22 contracts
Samples: Performance Based Contract, Performance Based Contract, Performance Based Contract
SAFETY, SECURITY AND PROTECTION OF THE ENVIRONMENT. Add Sub-Clause-paragraph (d) of Sub-Clause 19 as follows: Notwithstanding the Contractor’s obligation under Sub-Clause-paragraph (a), (b) and 9(c) of Sub-Sub- Clause 19.1 of the Conditions of Contract, the Contractor shall observe the following measures with a view to reducing or elimination adverse environmental effects by the site works:
(i) All quarries and borrow pits shall be filled and landscaped to their original state after extraction of construction material
Appears in 12 contracts
Samples: Performance Based Contract, Performance Based Contract, Performance Based Contract
SAFETY, SECURITY AND PROTECTION OF THE ENVIRONMENT. Add Sub-Clause-paragraph (d) of Sub-Clause 19 as follows: Notwithstanding the Contractor’s obligation under Sub-Clause-paragraph (a), (b) and 9(c) of Sub-Clause Clause
19.1 of the Conditions of Contract, the Contractor shall observe the following measures with a view to reducing or elimination adverse environmental effects by the site works:
(i) All quarries and borrow pits shall be filled and landscaped to their original state after extraction of construction material
Appears in 3 contracts
Samples: Performance Based Contract, Performance Based Contract, Performance Based Contract
SAFETY, SECURITY AND PROTECTION OF THE ENVIRONMENT. Add Sub-Clause-paragraph (d) of Sub-Clause 19 as follows: Notwithstanding the Contractor’s obligation under Sub-Clause-paragraph (a), (b) and 9(c) of Sub-Clause 19.1 of the Conditions of Contract, the Contractor shall observe the following measures with a view to reducing or elimination adverse environmental effects by the site works:
(i) All quarries and borrow pits shall be filled and landscaped to their original state after extraction of construction material
Appears in 3 contracts
Samples: Performance Based Contract, Performance Based Contract, Performance Based Contract
SAFETY, SECURITY AND PROTECTION OF THE ENVIRONMENT. Add Sub-Clause-paragraph (d) of Sub-Clause 19 as follows: Notwithstanding the Contractor’s obligation under Sub-Clause-paragraph (a), (b) and 9(c) of Sub-Clause Clause
19.1 of the Conditions of Contract, the Contractor shall observe the following measures with a view to reducing or elimination adverse environmental effects by the site works:
(i) All quarries and borrow pits shall be filled and landscaped to their original state after extraction of construction material
Appears in 1 contract
Samples: Performance Based Contract
SAFETY, SECURITY AND PROTECTION OF THE ENVIRONMENT. Add Sub-Clause-paragraph (d) of Sub-Clause 19 as follows: Notwithstanding the Contractor’s Contractor‟s obligation under Sub-Clause-paragraph (a), (b) and 9(c) of Sub-Clause 19.1 of the Conditions of Contract, the Contractor shall observe the following measures with a view to reducing or elimination adverse environmental effects by the site works:
(i) All quarries and borrow pits shall be filled and landscaped to their original state after extraction of construction material
Appears in 1 contract
Samples: Performance Based Contract
SAFETY, SECURITY AND PROTECTION OF THE ENVIRONMENT. Add Sub-Clause-paragraph (d) of Sub-Clause 19 as follows: Notwithstanding the Contractor’s obligation under Sub-Clause-paragraph (a), (b) and 9(c) of Sub-Sub- Clause 19.1 of the Conditions of Contract, the Contractor shall observe the following measures with a view to reducing or elimination adverse environmental effects by the site works:
(i) All quarries and borrow pits shall be filled and landscaped to their original state after extraction of construction material
Appears in 1 contract
Samples: Performance Based Contract
SAFETY, SECURITY AND PROTECTION OF THE ENVIRONMENT. Add Sub-Clause-paragraph (d) of Sub-Clause 19 as follows: Notwithstanding the Contractor’s obligation under Sub-Clause-paragraph (a), (b) and 9(c) of Sub-Clause 19.1 of the Conditions of Contract, the Contractor shall observe the following measures with a view to reducing or elimination adverse environmental effects by the site works:
(i) 1. All quarries and borrow pits shall be filled and landscaped to their original state after extraction of construction material
Appears in 1 contract
Samples: Performance Based Contract
SAFETY, SECURITY AND PROTECTION OF THE ENVIRONMENT. Add Sub-Clause-paragraph (d) of Sub-Clause 19 as follows: Notwithstanding the Contractor’s Contractor‟s obligation under Sub-Clause-paragraph (a), (b) and 9(c) of Sub-Clause 19.1 of the Conditions of Of Contract, the Contractor shall observe the following measures with a view to reducing or elimination adverse environmental effects by the site works:
(i) All quarries and borrow pits shall be filled and landscaped to their original state after extraction of construction material
Appears in 1 contract
Samples: Performance Based Contract