SAVINGS/FORCE. MAJEURE A force majeure occurrence is an event or effect that cannot be reasonably anticipated or controlled. Force majeure includes, but is not limited to, acts of God, acts of war, acts of public enemies, strikes, fires, explosions, actions of the elements, floods, or other similar causes beyond the control of the Contractor or the Commissioner in the performance of the Contract which non- performance, by exercise of reasonable diligence, cannot be prevented. Contractor shall provide the Commissioner with written notice of any force majeure occurrence as soon as the delay is known. Neither the Contractor nor the Commissioner shall be liable to the other for any delay in or failure of performance under the Contract due to a force majeure occurrence. Any such delay in or failure of performance shall not constitute default or give rise to any liability for damages. The existence of such causes of such delay or failure shall extend the period for performance to such extent as determined by the Contractor and the Commissioner to be necessary to enable complete performance by the Contractor if reasonable diligence is exercised after the cause of delay or failure has been removed. Notwithstanding the above, at the discretion of the Commissioner where the delay or failure will significantly impair the value of the Contract to the State or to Authorized Users, the Commissioner may: a. Accept allocated performance or deliveries from the Contractor. The Contractor, however, hereby agrees to grant preferential treatment to Authorized Users with respect to Product subjected to allocation; and/or b. Purchase from other sources (without recourse to and by the Contractor for the costs and expenses thereof) to replace all or part of the Products which are the subject of the delay, which purchases may be deducted from the Contract quantities without penalty or liability to the State; or c. Terminate the Contract or the portion thereof which is subject to delays, and thereby discharge any unexecuted portion of the Contract or the relative part thereof.
Appears in 59 contracts
Samples: Food Contract, Food Contract, Contract Agreement
SAVINGS/FORCE. MAJEURE A force majeure occurrence is an event or effect that cannot be reasonably anticipated or controlled. Force majeure includes, but is not limited to, acts of God, acts of war, acts of public enemies, strikes, fires, explosions, actions of the elements, floods, or other similar causes beyond the control of the Contractor or the Commissioner in the performance of the Contract which non- performance, by exercise of reasonable diligence, cannot be prevented. Contractor shall provide the Commissioner with written notice of any force majeure occurrence as soon as the delay is known. Neither the Contractor nor the Commissioner shall be liable to the other for any delay in or failure of performance under the Contract due to a force majeure occurrence. Any such delay in or failure of performance shall not constitute default or give rise to any liability for damages. The existence of such causes of such delay or failure shall extend the period for performance to such extent as determined by the Contractor and the Commissioner to be necessary to enable complete performance by the Contractor if reasonable diligence is exercised after the cause of delay or failure has been removed. Notwithstanding the above, at the discretion of the Commissioner where the delay or failure will significantly impair the value of the Contract to the State or to Authorized Users, the Commissioner may:
a. Accept allocated performance or deliveries from the Contractor. The Contractor, however, hereby agrees to grant preferential treatment to Authorized Users with respect to Product subjected to allocation; and/ortreatment
b. Purchase from other sources (without recourse to and by the Contractor for the costs and expenses thereof) to replace all or part of the Products which are the subject of the delay, which purchases may be deducted from the Contract quantities without penalty or liability to the State; or
c. Terminate the Contract or the portion thereof which is subject to delays, and thereby discharge any unexecuted portion of the Contract or the relative part thereof.
Appears in 49 contracts
Samples: Piggyback Contract for Commodities, Piggyback Contract for Commodities, Piggyback Contract for Commodities
SAVINGS/FORCE. MAJEURE A force majeure occurrence is an event or effect that cannot be reasonably anticipated or controlled. Force majeure includes, but is not limited to, acts of God, acts of war, acts of public enemies, strikes, fires, explosions, actions of the elements, floods, or other similar causes beyond the control of the Contractor or the Commissioner in the performance of the Contract which non- performance, by exercise of reasonable diligence, cannot be prevented. Contractor shall provide the Commissioner with written notice of any force majeure occurrence as soon as the delay is known. Neither the Contractor nor the Commissioner shall be liable to the other for any delay in or failure of performance under the Contract due to a force majeure occurrence. Any such delay in or failure of performance shall not constitute default or give rise to any liability for damages. The existence of such causes of such delay or failure shall extend the period for performance to such extent as determined by the Contractor and the Commissioner to be necessary to enable complete performance by the Contractor if reasonable diligence is exercised after the cause of delay or failure has been removed. Notwithstanding the above, at the discretion of the Commissioner where the delay or failure will significantly impair the value of the Contract to the State or to Authorized Users, the Commissioner may:
a. Accept allocated performance or deliveries from the Contractor. The Contractor, however, hereby xxxxxx agrees to grant preferential treatment to Authorized Users with respect to Product subjected to allocation; and/or
b. Purchase from other sources (without recourse to and by the Contractor for the costs and expenses thereof) to replace all or part of the Products which are the subject of the delay, which purchases may be deducted from the Contract quantities without penalty or liability to the State; or
c. Terminate the Contract or the portion thereof which is subject to delays, and thereby discharge any unexecuted portion of the Contract or the relative part thereof.
Appears in 15 contracts
Samples: Consent to Assignment, Vendor and Supplier Contracts, Contract for Food (Commercial) (Statewide)
SAVINGS/FORCE. MAJEURE A force majeure occurrence is an event or effect that cannot be reasonably anticipated or controlled. Force majeure includes, but is not limited to, acts of God, acts of war, acts of public enemies, strikes, fires, explosions, actions of the elements, floods, or other similar causes beyond the control of the Contractor or the Commissioner in the performance of the Contract which non- performance, by exercise of reasonable diligence, cannot be prevented. Contractor shall provide the Commissioner with written notice of any force majeure occurrence as soon as the delay is known. Neither the Contractor nor the Commissioner shall be liable to the other for any delay in or failure of performance under the Contract due to a force majeure occurrence. Any such delay in or failure of performance shall not constitute default or give rise to any liability for damages. The existence of such causes of such delay or failure shall extend the period for performance to such extent as determined by the Contractor and the Commissioner to be necessary to enable complete performance by the Contractor if reasonable diligence is exercised after the cause of delay or failure has been removed. Notwithstanding the above, at the discretion of the Commissioner where the delay or failure will significantly impair the value of the Contract to the State or to Authorized Users, the Commissioner may:
a. Accept allocated performance or deliveries from the Contractor. The Contractor, however, hereby agrees to grant preferential treatment to Authorized Users with respect to Product subjected to allocation; and/or
b. Purchase from other sources (without recourse to and by the Contractor for the costs and expenses thereof) to replace all or part of the Products which are the subject of the delay, which purchases may be deducted from the Contract quantities without penalty or liability to the State; orthe
c. Terminate the Contract or the portion thereof which is subject to delays, and thereby discharge any unexecuted portion of the Contract or the relative part thereof.
Appears in 14 contracts
Samples: Vendor and Supplier Contracts, Vendor and Supplier Contracts, Vendor and Supplier Contracts
SAVINGS/FORCE. MAJEURE A force majeure occurrence is an event or effect that cannot be reasonably anticipated or controlled. Force majeure includes, but is not limited to, acts of God, acts of war, acts of public enemies, strikes, fires, explosions, actions of the elements, floods, or other similar causes beyond the control of the Contractor or the Commissioner in the performance of the Contract which non- performance, by exercise of reasonable diligence, cannot be prevented. Contractor shall provide the Commissioner with written notice of any force majeure occurrence as soon as the delay is known. Neither the Contractor nor the Commissioner shall be liable to the other for any delay in or failure of performance under the Contract due to a force majeure occurrence. Any such delay in or failure of performance shall not constitute default or give rise to any liability for damages. The existence of such causes of such delay or failure shall extend the period for performance to such extent as determined by the Contractor and the Commissioner to be necessary to enable complete performance by the Contractor if reasonable diligence is exercised after the cause of delay or failure has been removed. Notwithstanding the above, at the discretion of the Commissioner where the delay or failure will significantly impair the value of the Contract to the State or to Authorized Users, the Commissioner may:
a. Accept allocated performance or deliveries from the Contractor. The Contractor, however, hereby xxxxxx agrees to grant preferential treatment to Authorized Users with respect to Product subjected to allocation; and/ortreatment
b. Purchase from other sources (without recourse to and by the Contractor for the costs and expenses thereof) to replace all or part of the Products which are the subject of the delay, which purchases may be deducted from the Contract quantities without penalty or liability to the State; or
c. Terminate the Contract or the portion thereof which is subject to delays, and thereby discharge any unexecuted portion of the Contract or the relative part thereof.
Appears in 8 contracts
Samples: Piggyback Contract for Commodities, Basic Medical Supplies and Equipment Agreement, Fuel Supply Agreement
SAVINGS/FORCE. MAJEURE A force majeure occurrence is an event or effect that cannot be reasonably anticipated or controlled. Force majeure includes, but is not limited to, acts of God, acts of war, acts of public enemies, strikes, fires, explosions, actions of the elements, floods, or other similar causes beyond the control of the Contractor or the Commissioner in the performance of the Contract which non- performance, by exercise of reasonable diligence, cannot be prevented. Contractor shall provide the Commissioner with written notice of any force majeure occurrence as soon as the delay is known. Neither the Contractor nor the Commissioner shall be liable to the other for any delay in or failure of performance under the Contract due to a force majeure occurrence. Any such delay in or failure of performance shall not constitute default or give rise to any liability for damages. The existence of such causes of such delay or failure shall extend the period for performance to such extent as determined by the Contractor and the Commissioner to be necessary to enable complete performance by the Contractor if reasonable diligence is exercised after the cause of delay or failure has been removed. Notwithstanding the above, at the discretion of the Commissioner where the delay or failure will significantly impair the value of the Contract to the State or to Authorized Users, the Commissioner may:
a. Accept allocated performance or deliveries from the Contractor. The Contractor, however, hereby xxxxxx agrees to grant preferential treatment to Authorized Users with respect to Product subjected to allocation; and/or
b. Purchase from other sources (without recourse to and by the Contractor for the costs and expenses thereof) to replace all or part of the Products which are the subject of the delay, which purchases may be deducted from the Contract quantities without penalty or liability to the State; or
c. Terminate the Contract or the portion thereof which is subject to delays, and thereby discharge any unexecuted portion of the Contract or the relative part thereof. In addition, the Commissioner reserves the right, in his/her sole discretion, to make an equitable adjustment in the Contract terms and/or pricing should extreme and unforeseen volatility in the marketplace affect pricing or the availability of supply. "Extreme and unforeseen volatility in the marketplace" is defined as market circumstances which meet the following criteria: (i) the volatility is due to causes outside the control of Contractor; (ii) the volatility affects the marketplace or industry, not just the particular Contract source of supply; (iii) the effect on pricing or availability of supply is substantial; and (iv) the volatility so affects Contractor's performance that continued performance of the Contract would result in a substantial loss.
Appears in 7 contracts
Samples: Centralized Contract for the Acquisition of Microcomputer Systems and Related Services, Contract for the Acquisition of Assistive Technology for Persons With Disabilities, Centralized Contract for the Acquisition of Power Protection Equipment
SAVINGS/FORCE. MAJEURE A force majeure occurrence is an event or effect that cannot be reasonably anticipated or controlled. Force majeure includes, but is not limited to, acts of God, acts of war, acts of public enemies, strikes, fires, explosions, actions of the elements, floods, or other similar causes beyond the control of the Contractor or the Commissioner in the performance of the Contract which non- performance, by exercise of reasonable diligence, cannot be prevented. Contractor shall provide the Commissioner with written notice of any force majeure occurrence as soon as the delay is known. Neither the Contractor nor the Commissioner shall be liable to the other for any delay in or failure of performance under the Contract due to a force majeure occurrence. Any such delay in or failure of performance shall not constitute default or give rise to any liability for damages. The existence of such causes of such delay or failure shall extend the period for performance to such extent as determined by the Contractor and the Commissioner to be necessary to enable complete performance by the Contractor if reasonable diligence is exercised after the cause of delay or failure has been removed. Notwithstanding the above, at the discretion of the Commissioner where the delay or failure will significantly impair the value of the Contract to the State or to Authorized Users, the Commissioner may:
a. Accept allocated performance or deliveries from the Contractor. The Contractor, however, hereby agrees to grant preferential treatment to Authorized Users with respect to Product subjected to allocation; and/orthe
b. Purchase from other sources (without recourse to and by the Contractor for the costs and expenses thereof) to replace all or part of the Products which are the subject of the delay, which purchases may be deducted from the Contract quantities without penalty or liability to the State; or
c. Terminate the Contract or the portion thereof which is subject to delays, and thereby discharge any unexecuted portion of the Contract or the relative part thereof.
Appears in 2 contracts
Samples: Contract for the Acquisition of Scientific Equipment and Related Accessories, Contract for the Acquisition of Scientific Equipment and Related Accessories
SAVINGS/FORCE. MAJEURE A force majeure occurrence is an event or effect that cannot be reasonably anticipated or controlled. Force majeure includes, but is not limited to, acts of God, acts of war, acts of public enemies, strikes, fires, explosions, actions of the elements, floods, or other similar causes beyond the control of the Contractor or the Commissioner in the performance of the Contract which non- performance, by exercise of reasonable diligence, cannot be prevented. Contractor shall provide the Commissioner with written notice of any force majeure occurrence as soon as the delay is known. Neither the Contractor nor the Commissioner shall be liable to the other for any delay in or failure of performance under the Contract due to a force majeure occurrence. Any such delay in or failure of performance shall not constitute default or give rise to any liability for damages. The existence of such causes of such delay or failure shall extend the period for performance to such extent as determined by the Contractor and the Commissioner to be necessary to enable complete performance by the Contractor if reasonable diligence is exercised after the cause of delay or failure has been removed. Notwithstanding the above, at the discretion of the Commissioner where the delay or failure will significantly impair the value of the Contract to the State or to Authorized Users, the Commissioner may:
a. Accept allocated performance or deliveries from the Contractor. The Contractor, however, hereby agrees to grant preferential treatment to Authorized Users with respect to Product subjected to allocation; and/or
b. Purchase from other sources (without recourse to and by the Contractor for the costs and expenses thereof) to replace all or part of the Products which are the subject of the delay, which purchases may be deducted from the Contract quantities without penalty or liability to the State; or
c. Terminate the Contract or the portion thereof which is subject to delays, and thereby discharge any unexecuted portion of the Contract or the relative part thereof. In addition, the Commissioner reserves the right, in his/her sole discretion, to make an equitable adjustment in the Contract terms and/or pricing should extreme and unforeseen volatility in the marketplace affect pricing or the availability of supply. "Extreme and unforeseen volatility in the marketplace" is defined as market circumstances which meet the following criteria: (i) the volatility is due to causes outside the control of Contractor; (ii) the volatility affects the marketplace or industry, not just the particular Contract source of supply; (iii) the effect on pricing or availability of supply is substantial; and (iv) the volatility so affects Contractor's performance that continued performance of the Contract would result in a substantial loss.
Appears in 1 contract
Samples: Enterprise Systems Base Agreement