Schedule for Facilities Removal. 7.3.1 Should the Secretary render an Affirmative Determination, the Parties agree that the target date to begin Decommissioning the Facilities is January 1, 2020. The Parties agree that preparatory work for Facilities Removal may be undertaken by the DRE before January 1, 2020, consistent with the Secretarial Determination, the Definite Plan, applicable permits, and Section 6 of this Settlement; provided such preparatory work shall not have any negative impact on PacifiCorp’s generation operations at the Facilities. The Parties further agree to a target date of December 31, 2020 for completion of Facilities Removal at least to a degree sufficient to enable a free-flowing Klamath River allowing volitional fish passage.
Appears in 5 contracts
Samples: Settlement Agreement, Settlement Agreement, Settlement Agreement