Scheduling of the Initial and Annual Performance Tests. Upon achieving Commercial Operation, the Seller shall give the Department five business days notice before the commencement of the performance test. A capacity and heat rate test of each Unit shall be performed. This performance test shall be paid for by the Seller. Annually in accordance with Section 4.02 (b), a heat rate test shall be performed within thirty days before or after the anniversary of the Commercial Operation Date, or at another time to be mutually agreed. The Seller shall provide 10 business day notice to the Department before the commecement of this performance test. This performance test shall be paid for by the Seller. Periodically in accordance with Section 2.02 (c), the Departement may call for additional performance tests in addition to the required annual test for the determination of Rated Capacity. The incremental costs of this test shall be born by the Department. The Seller shall give the Departement 10 business days notice before the commencement of the performance test.
Appears in 4 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Scheduling of the Initial and Annual Performance Tests. Upon achieving Commercial Operation, the The Seller shall give the Department five business days notice before the commencement of the performance test. A capacity and heat rate test of each Unit shall be performed. This performance test shall be paid for by the Seller. Annually in accordance with Section 4.02 (b), a heat rate test shall be performed within thirty days before or after the anniversary of the Commercial Operation Date, or at another time to be mutually agreed. The Seller shall provide 10 business day notice to the Department before the commecement commencement of this performance test. This performance test shall be paid for by the Seller. Periodically in accordance with Section 2.02 (c), the Departement Department may call for additional performance tests in addition to the required annual test for the determination of Rated Plant Capacity. The incremental costs of this test shall be born by the Department. The Seller shall give the Departement Department 10 business days notice before the commencement of the performance test.
Appears in 3 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Scheduling of the Initial and Annual Performance Tests. Upon achieving Commercial Operation, the Seller shall give the Department five business days notice before the commencement of the performance test. A capacity and heat rate test of each Unit shall be performed. This performance test shall be paid for by the Seller. Annually in accordance with Section 4.02 (b), a heat rate test shall be performed within thirty days before or after the anniversary of the Commercial Operation Date, or at another time to be mutually agreed. The Seller shall provide 10 business day notice to the Department before the commecement of this performance test. This performance test shall be paid for by the Seller. Periodically in accordance with Section 2.02 (c), the Departement may call for additional performance tests in addition to the required annual test for the determination of Rated Plant Capacity. The incremental costs of this test shall be born by the Department. The Seller shall give the Departement 10 business days notice before the commencement of the performance test.
Appears in 1 contract
Samples: Power Purchase Agreement