Scope Changes Due to Changes in Applicable Laws Sample Clauses

Scope Changes Due to Changes in Applicable Laws. To the extent an ARCA Delay Event described in clause (e) of the definition thereof causes a material delay in Contractor’s performance of the Work that Contractor cannot, in the absence of incurring material cost or impacting the critical path, overcome the effect thereof, Contractor shall be entitled to claim a Scope Change Order in accordance with the procedures of this Article 12 to appropriately adjust one or more of the Project Schedule, the Payment and Values Schedule and the Guaranteed Substantial Completion Date (but not the Contract Sum). Concessionaire’s obligation to extend the Guaranteed Completion Date as a result of such a Scope Change Order shall be subject to Concessionaire’s receipt of approval thereof from VDOT under the Comprehensive Agreement. Concessionaire shall proceed in accordance with Section 12.15(c) hereof to obtain such approval under the Comprehensive Agreement. The provisions of Section