Site Logistics Plan Clause Samples

POPULAR SAMPLE Copied 5 times
Site Logistics Plan. 6.16.5.1 The Contractor shall prepare a plan of the Site indicating how the Contractor intends to use the Site. The plan should illustrate, as an example, areas to be used for lay down of material and equipment; office and storage trailer locations; vehicular access gates with ingress and egress routes; locations of wheel wash and concrete truck wash out activities; and offloading and hoisting locations.
Site Logistics Plan. The final GMP/CPFF construction contract shall reflect the following, unless otherwise agreed to by Princeton University: Construction Phase Fee TBD% General Conditions $X,XXX,XXX.XX Fee-Bearing Change Order Threshold $X,XXX,XXX.XX Fee applied to Cost of Work Increases above threshold TBD% Fee reduction applied to Cost of Work Decreases TBD% Agreement with GMP/CPFF Terms and Conditions Yes (in their entirety) Methodology for Charging Vacation and Holidays: The Parties have agreed that vacation and holidays will be charged as follows: [insert appropriate language].
Site Logistics Plan. The Contractor will be responsible for organizing its activities at the Project Site so as to provide proper space for the storage of materials and equipment and construction operations. Within twenty (20) days after the date of execution of this Agreement and prior to mobilization, the Contractor shall prepare and submit to the General Contractor for its approval a site logistics plan (the "Site Logistics Plan"), which will show, at a minimum, the proposed location of the following: (i) the Contractor's trailers; (ii) vehicle parking; (iii) the site entry road; (iv) signs; and (vii) the routing of truck deliveries. The General Contractor's approval of the Site Logistics Plan will not be unreasonably withheld. Upon approval by the General Contractor, the Contractor shall furnish three (3) copies of the Site Logistics Plan to the General Contractor.
Site Logistics Plan. The CMR shall prepare and submit a Preliminary Site Logistics Plan and a Final Site Logistics Plan for review by the A/E, DAS PM, and Agency Representative(s). The Site Logistics Plan shall identify and include, but shall not be limited to, the following:
Site Logistics Plan. The General Contractor will be responsible for organizing its activities at the Project Site so as to provide proper space for the storage of materials and equipment and construction operations. Within twenty (20) days after the date of execution of this Agreement and prior to mobilization, the General Contractor shall prepare and submit to the Owner for its approval a site logistics plan (the "Site Logistics Plan"), which will show, at a minimum, the proposed location of the following: (i) the General Contractor's trailers; (ii) temporary utilities; (iii) vehicle parking; (iv) staging and laydown areas; (v) the site entry road; (vi) signs; and (vii) the routing of truck deliveries. The Owner's 's approval of the Site Logistics Plan will not be unreasonably withheld. Upon approval by the Owner , the General Contractor shall furnish three (3) copies of the Site Logistics Plan to the Owner .

Related to Site Logistics Plan

  • Construction Management Plan Contractor shall prepare and furnish to the Owner a thorough and complete plan for the management of the Project from issuance of the Proceed Order through the issuance of the Design Professional's Certificate of Material Completion. Such plan shall include, without limitation, an estimate of the manpower requirements for each trade and the anticipated availability of such manpower, a schedule prepared using the critical path method that will amplify and support the schedule required in Article 2.1.5 below, and the Submittal Schedule as required in Article 2.2.3. The Contractor shall include in his plan the names and resumés of the Project Superintendent, Project Manager and the person in charge of Safety.

  • Project Management Plan Developer is responsible for all quality assurance and quality control activities necessary to manage the Work, including the Utility Adjustment Work. Developer shall undertake all aspects of quality assurance and quality control for the Project and Work in accordance with the approved Project Management Plan and

  • Development Plans Customer has provided Provider with a report attached hereto as Exhibit D (the “Current Development Plan”) describing in detail, as of January 1, 2017, the planned development, drilling, production, processing, treating, marketing and other activities to take place with respect to Dedicated Production and Customer Injected NGLs for the applicable Development Period. The information contained in the Current Development Plan is, with respect to the first three Years covered by the Current Development Plan, on a Quarter-by-Quarter basis, and with respect to the remaining Years covered by the Current Development Plan, on a Year-by-Year basis. The Current Development Plan attached hereto has been approved by the Parties. (a) From time to time during each Year of the Term, the Parties shall meet to discuss the planned development, drilling, production, processing, treating, marketing and other activities that Customer expects to take place with respect to Dedicated Production and Customer Injected NGLs for the then-applicable Development Period. Customer and Provider shall each make their respective representatives available to participate in such meetings and discussions. No later than August 1 of each such Year, Customer shall provide (or cause to be provided) to Provider a proposed update of the then-currently agreed Development Plan, prepared on the same basis as the Current Development Plan and describing in detail the planned development, drilling, production, processing, treating, marketing and other activities to take place with respect to Dedicated Production and Customer Injected NGLs for the then-applicable Development Period (any such update, an “Updated Development Plan” and, together with the Current Development Plan, each, a “Development Plan”). (b) Each proposed Development Plan shall include information as to the following, in each case, broken out, with respect to the first three Years covered by such Development Plan, on a Quarter-by-Quarter basis, and, with respect to the remaining Years covered by such Development Plan, on a Year-by-Year basis: (i) forward-looking production estimates for the applicable time period covered by such Development Plan for all Customer Gas and Customer Injected NGLs (A) that Customer reasonably and in good faith believes will become owned or Controlled by Customer during the time period covered by such Development Plan, and/or (B) that will be produced from (I) in the aggregate, all ▇▇▇▇▇ then-existing and (II) in the aggregate, all ▇▇▇▇▇ that are expected to be drilled during the time period covered by such Development Plan (each such Well reflected in such Development Plan, a “Planned Well” and, such collective estimates described in subsections (A) and (B), both with respect to a particular Quarter and an entire Year, the “Dedicated Production Estimates”); TERMS IN THIS EXHIBIT HAVE BEEN REDACTED BECAUSE CONFIDENTIAL TREATMENT FOR THOSE TERMS HAS BEEN REQUESTED. THE REDACTED MATERIAL HAS BEEN FILED SEPARATELY WITH THE SECURITIES AND EXCHANGE COMMISSION, AND THE TERMS HAVE BEEN MARKED AT THE APPROPRIATE PLACE WITH TWO ASTERISKS (**). (ii) (A) each new receipt point (including the location thereof) proposed by Customer with respect to the Dedicated Production Estimate reflected in such Development Plan (each such receipt point, a “Planned Receipt Point”), (B) each Receipt Point at which Customer expects to Tender Customer Gas or Customer Injected NGLs reflected in such Development Plan into the TGP System, and (C) the estimated portion of the Dedicated Production Estimate contained in such Development Plan that Customer expects to Tender at each such Receipt Point and Planned Receipt Point; (iii) (A) each new delivery point (including the location thereof) proposed by Customer with respect to the Dedication Production Estimate reflected in such Development Plan (each such delivery point, a “Planned Delivery Point”), (B) each Delivery Point at which Customer expects to Nominate Customer Residue Gas or Customer NGLs produced from the Dedicated Production Estimate reflected in such Development Plan to be redelivered to Customer, and (C) the estimated volumes of Customer Residue Gas and Customer NGLs produced from the Dedication Production Estimate contained in such Development Plan that Customer expects to Nominate to each such Delivery Point; (iv) the earliest date on which each Planned Receipt Point and Planned Delivery Point included in the Development Plan is required by Customer to be placed into service, which date shall not be earlier than three Months after the January 1st that is immediately subsequent to the date that the Development Plan that initially reflected such Planned Receipt Point or Planned Delivery Point was delivered to Provider hereunder; (v) the anticipated characteristics of the production from the ▇▇▇▇▇ and Planned ▇▇▇▇▇ reflected in such Development Plan (including liquids content and gas and liquids composition) and the projected production volumes and production pressures applicable thereto; provided that Customer may utilize the existing and historical production information from similarly situated ▇▇▇▇▇; (vi) any (A) proposed revision to the then-existing Dedicated Area and/or any then-existing Dedicated Contract and/or (B) any new contract that Customer proposes to be a Dedicated Contract; and (vii) other information reasonably requested by Provider that is relevant to the design, construction, and operation of the TGP System, including (A) any applicable Plant Expansion or Facilities Modification proposed by Customer, (B) the relevant Receipt Point and Planned Receipt Point facilities applicable to such Development Plan, and (C) the relevant Delivery Point and Planned Delivery Point facilities applicable to such Development Plan. TERMS IN THIS EXHIBIT HAVE BEEN REDACTED BECAUSE CONFIDENTIAL TREATMENT FOR THOSE TERMS HAS BEEN REQUESTED. THE REDACTED MATERIAL HAS BEEN FILED SEPARATELY WITH THE SECURITIES AND EXCHANGE COMMISSION, AND THE TERMS HAVE BEEN MARKED AT THE APPROPRIATE PLACE WITH TWO ASTERISKS (**).

  • Operating Plan To Agent and Lenders, as soon as available, but not later than thirty (30) days after the end of each Fiscal Year, an annual combined operating plan (the "Operating Plan") for Parent and its Subsidiaries, approved by the Board of Directors of Parent, for the following Fiscal Year, which (i) includes a statement of all of the material assumptions on which such plan is based, (ii) includes projected monthly income statement, balance sheets and source and use of funds for the following year and (iii) Borrowing Availability projections, all prepared on the same basis and in similar detail as that on which operating results are reported (and in the case of cash flow projections, representing management's good faith estimates of future financial performance based on historical performance), and including plans for personnel, Capital Expenditures and facilities.

  • Staffing Plan The Board and the Association agree that optimum class size is an important aspect of the effective educational program. The Polk County School Staffing Plan shall be constructed each year according to the procedures set forth in Board Policy and, upon adoption, shall become Board Policy.