SPD’s Obligations. 4.1.1 The SPD undertakes to be responsible, at SPD’s own cost and risk, for: a) The SPD shall be solely responsible and make arrangements for development of the Project and for Connectivity up to the delivery point at the Sub Station of SPV Power Plant for confirming the evacuation of power by the Scheduled Commissioning date and all clearances related thereto; b) Obtaining all Consents, Clearances and Permits as required and maintaining all Consents, Clearances and Permits in full force and effect during the Term of this Agreement. The Solar Power Developer shall, on his own, obtain permissions/ sanctions from Government authorities, if any required for establishing the project. c) Designing, constructing, erecting, commissioning, completing and testing the Power Project in accordance with the applicable Law, the Grid Code, the terms and conditions of this Agreement and Prudent Utility Practices. d) the commencement of supply of power up to the Contracted Capacity to MSPDCL no later than the Scheduled Commissioning Date and continuance of the supply of power throughout the term of the Agreement;
Appears in 1 contract
Samples: Power Purchase Agreement
SPD’s Obligations. 4.1.1 The SPD undertakes to be responsible, at SPD’s own cost and risk, for:
a) The SPD shall be solely responsible and make arrangements for development of the Project and for Connectivity up to the delivery point at the Sub Station of SPV Power Plant for confirming the evacuation of power by the Scheduled Commissioning date and all clearances related thereto;
b) Obtaining all Consents, Clearances and Permits as required and maintaining all Consents, Clearances and Permits in full force and effect during the Term of this Agreement. The Solar Power Developer shall, on his own, obtain permissions/ sanctions from Government authorities, if any required for establishing the project.
c) Designing, constructing, erecting, commissioning, completing and testing the Power Project in accordance with the applicable Law, the Grid Code, the terms and conditions of this Agreement and Prudent Utility Practices.
d) the commencement of supply of power up to the Contracted Capacity to MSPDCL JDA no later than the Scheduled Commissioning Date and continuance of the supply of power throughout the term of the Agreement;
Appears in 1 contract
Samples: Power Purchase Agreement
SPD’s Obligations. 4.1.1 The SPD undertakes to be responsible, at SPD’s own cost and risk, for:
a) The SPD shall be solely responsible and make arrangements for development of the Project and for Connectivity up to the delivery point at the Sub Station of SPV ofSPV Power Plant for confirming the evacuation of power by the Scheduled Commissioning date and all clearances related thereto;
b) Obtaining all Consents, Clearances and Permits as required and maintaining all Consents, Clearances and Permits in full force and effect during the Term of this Agreement. The Solar Power Developer shall, on his own, obtain permissions/ sanctions from Government authorities, if any required for establishing the project.
c) Designing, constructing, erecting, commissioning, completing and testing the Power Project in accordance with the applicable Law, the Grid Code, the terms and conditions of this Agreement and Prudent Utility Practices.
d) the commencement of supply of power up to the Contracted Capacity to MSPDCL no later than the Scheduled Commissioning Date and continuance of the supply of power throughout the term of the Agreement;
Appears in 1 contract
Samples: Power Purchase Agreement
SPD’s Obligations. 4.1.1 The SPD undertakes to be responsible, at SPD’s own cost and risk, for:
a) The SPD shall be solely responsible and make arrangements for development of the Project and for Connectivity up to the delivery point at the Sub Station of SPV Power Plant Electricity Department, A&N for confirming the evacuation of power by the Scheduled Commissioning date and all clearances related thereto;
b) Obtaining all Consents, Clearances and Permits as required and maintaining all Consents, Clearances and Permits in full force and effect during the Term of this Agreement. The Solar Power Developer shall, on his own, obtain permissions/ sanctions from Government authorities, if any required for establishing the project.
c) Designing, constructing, erecting, commissioning, completing and testing the Power Project in accordance with the applicable Law, the Grid Code, the terms and conditions of this Agreement and Prudent Utility Practices.
d) the commencement of supply of power up to the Contracted Capacity to MSPDCL EDA&N no later than the Scheduled Commissioning Date and continuance of the supply of power throughout the term of the Agreement;
Appears in 1 contract
Samples: Power Purchase Agreement