Storage Voltage Support Service Verification. Prior to COD, Owner and CHGE shall test and certify the Project’s ability to both produce and absorb reactive power (collectively, “Voltage Stability Services”) as defined in the NYISO tariff. Such testing and verification shall be done in coordination with NYISO and according to the test procedures detailed by NYISO Manual 2 “Ancillary Services” or by successor requirements as determined by NYISO. At minimum, a Project must verify it can:
Appears in 2 contracts
Samples: Storage Services Agreement, Energy Storage Services Agreement
Storage Voltage Support Service Verification. Prior to COD, Owner and CHGE CECONY shall test and certify the Project’s ability to both produce and absorb reactive power (collectively, “Voltage Stability Services”) as defined in the NYISO tariff. Such testing and verification shall be done in coordination with NYISO and according to the test procedures detailed by NYISO Manual 2 “Ancillary Services” or by successor requirements as determined by NYISO. At minimum, a Project must verify it can:
Appears in 2 contracts
Samples: Storage Services Agreement, Storage Services Agreement
Storage Voltage Support Service Verification. Prior to COD, Owner and CHGE RG&E shall test and certify the Project’s ability to both produce and absorb reactive power (collectively, “Voltage Stability Services”) as defined in the NYISO tariff. Such testing and verification shall be done in coordination with NYISO and according to the test procedures detailed by NYISO Manual 2 “Ancillary Services” or by successor requirements as determined by NYISO. At minimum, a Project must verify it can:
Appears in 1 contract
Samples: Storage Services Agreement
Storage Voltage Support Service Verification. Prior to COD, Owner and CHGE shall test and certify the Project’s ability to both produce and absorb reactive power (collectively, “Voltage Stability Services”) as defined in the NYISO tariff. Such testing and verification shall be done in coordination with NYISO and according to the test procedures detailed by NYISO Manual 2 “Ancillary Services” or by successor requirements as determined by NYISOXXXXX. At minimum, a Project must verify it can:
Appears in 1 contract
Samples: Energy Storage Services Agreement
Storage Voltage Support Service Verification. Prior to COD, Owner and CHGE RG&E shall test and certify the Project’s ability to both produce and absorb reactive power (collectively, “Voltage Stability Services”) as defined in the NYISO tariff. Such testing and verification shall be done in coordination with NYISO and according to the test procedures detailed by NYISO Manual 2 “Ancillary Services” or by successor requirements as determined by NYISOXXXXX. At minimum, a Project must verify it can:
Appears in 1 contract
Samples: Storage Services Agreement
Storage Voltage Support Service Verification. Prior to COD, Owner and CHGE CECONY shall test and certify the Project’s ability to both produce and absorb reactive power (collectively, “Voltage Stability Services”) as defined in the NYISO tariff. Such testing and verification shall be done in coordination with NYISO and according to the test procedures detailed by NYISO Manual 2 “Ancillary Services” or by successor requirements as determined by NYISOXXXXX. At minimum, a Project must verify it can:
Appears in 1 contract
Samples: Storage Services Agreement
Storage Voltage Support Service Verification. Prior to COD, Owner and CHGE NYSEG shall test and certify the Project’s ability to both produce and absorb reactive power (collectively, “Voltage Stability Services”) as defined in the NYISO tariff. Such testing and verification shall be done in coordination with NYISO and according to the test procedures detailed by NYISO Manual 2 “Ancillary Services” or by successor requirements as determined by NYISOXXXXX. At minimum, a Project must verify it can:
Appears in 1 contract
Samples: Energy Storage Services Agreement