SUBCONTRACTOR RELATIONS. 5.2.1 Prior to the execution of each subcontract agreement, Contractor shall make available to each proposed Subcontractor, copies of the Contract Documents. Contractor must incorporate the terms of these Contract Documents into each subcontract, so that each Subcontractor will be bound by the terms of these Contract Documents, including, but not limited to, the provisions for dispute resolution. Within thirty (30) Days of the Notice To Proceed, Contractor shall provide City with a complete listing of all Subcontractors, which shall include, but not be limited to, the Work contracted for, Subcontractor’s name, address, telephone and facsimile numbers, form for doing business (i.e, sole proprietor, corporation, partnership), point-of-contact and Subcontractor’s license classification and number. 5.2.2 Any part of the Work performed for Contractor by a first Tier Subcontractor shall be pursuant to a written subcontract. Each such subcontract shall require that the Subcontractor: (i) Perform the Work in accordance with the terms of the Contract Documents. (ii) Assume toward Contractor all the obligations and responsibilities which Contractor assumes towards City by the Contract Documents. (iii) Preserve and protect the rights of City under the Contract Documents with respect to the Work to be performed by the Subcontractor so that subcontracting thereof will not prejudice such rights. (iv) Waive all rights that the Subcontractor may have against City for damages caused by fire or other perils covered by builder's risk property insurance carried by Contractor or City, except for such rights Subcontractor may have to the proceeds of such insurance held by City under Article 11 of these General Conditions. (v) Afford City and entities and agencies designated by City the same rights and remedies with respect to access to and the right to audit and the right to copy at City's cost all of the Subcontractor's books, records, contracts, correspondence, instructions, drawings, receipts, vouchers, purchase orders and memoranda relating to the Work and requiring the Subcontractor to preserve all such records and other items for a period of at least three (3) years after Final Completion. (vi) Recognize the rights of City under Section 5.3 of the General Conditions, Contingent Assignment of Subcontracts, including, without limitation, City’s right to elect to accept assignment of the subcontract and to retain Subcontractor pursuant to the terms of the subcontract, to complete the unperformed obligations under the subcontract and, if requested by City, to execute a written agreement on terms acceptable to City confirming that the Subcontractor is bound to City under the same terms as the subcontract. (vii) Submit Applications for payment, requests for Change Orders and extensions of time and Claims, and to comply with all other notice and submission requirements of the Contract Documents, sufficiently in advance to allow Contractor time to comply with its obligations under the Contract Documents. (viii) Purchase and maintain insurance in accordance with the requirements of the Contract Documents and reserving the right to Owner to purchase, in its sole discretion, such insurance pursuant to an Owner Controlled Insurance or other form of wrap-up program. (ix) Provide the same defense indemnification of the City as is required of the Contractor. (x) Agree to participate in the dispute resolution procedures specified in the Construction Contract, at the election of City. 5.2.3 Contractor shall promptly, after execution, furnish to City true, complete, and executed copies of all subcontracts, and any change orders and modifications thereto. Progress payments shall not be made for items of Work for which City has not received executed subcontracts and, if applicable, Change Orders. 5.2.4 Nothing contained in the Contract Documents shall create any contractual relationship between any Subcontractor and City, except when, and only to the extent that, City elects to accept the assignment of the subcontract with such Subcontractor pursuant to Section 5.3, Contingent Assignment of Subcontracts. Notwithstanding the foregoing, City is deemed a third party beneficiary of each subcontract agreement. 5.2.5 City and the Construction Manager shall have the right to communicate with Contractor’s Subcontractors with respect to matters that are related to Contractor’s performance of its obligations under the Contract Documents. Contractor shall be provided with a copy of all such written communications. Such communications shall not create or be interpreted as creating any contractual relationship between City or the Construction Manager and any such Subcontractor.
Appears in 18 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
SUBCONTRACTOR RELATIONS.
5.2.1 Prior to the execution of each subcontract agreement, Contractor shall make available to each proposed Subcontractor, copies of the Contract Documents. Contractor must incorporate the terms of these Contract Documents into each subcontract, so that each Subcontractor will be bound by the terms of these Contract Documents, including, but not limited to, the provisions for dispute resolution. Within thirty (30) Days of the Notice To Proceed, Contractor shall provide City with a complete listing of all Subcontractors, which shall include, but not be limited to, the Work contracted for, Subcontractor’s name, address, telephone and facsimile numbers, form for doing business (i.e, sole proprietor, corporation, partnership), point-of-contact and Subcontractor’s license classification and number.
5.2.2 Any part of the Work performed for Contractor by a first Tier Subcontractor shall be pursuant to a written subcontract. Each such subcontract shall require that the Subcontractor:
(i) Perform the Work in accordance with the terms of the Contract Documents.
(ii) Assume toward Contractor all the obligations and responsibilities which Contractor assumes towards City by the Contract Documents.
(iii) Preserve and protect the rights of City under the Contract Documents with respect to the Work to be performed by the Subcontractor so that subcontracting thereof will not prejudice such rights.
(iv) Waive all rights that the Subcontractor may have against City for damages caused by fire or other perils covered by builder's risk property insurance carried by Contractor or City, except for such rights Subcontractor may have to the proceeds of such insurance held by City under Article 11 of these General Conditions.
(v) Afford City and entities and agencies designated by City the same rights and remedies with respect to access to and the right to audit and the right to copy at City's cost all of the Subcontractor's books, records, contracts, correspondence, instructions, drawings, receipts, vouchers, purchase orders and memoranda relating to the Work and requiring the Subcontractor to preserve all such records and other items for a period of at least three (3) years after Final Completion.
(vi) Recognize the rights of City under Section 5.3 of the General Conditions, Contingent Assignment of Subcontracts, including, without limitation, City’s right to elect to accept assignment of the subcontract and to retain Subcontractor pursuant to the terms of the subcontract, to complete the unperformed obligations under the subcontract and, if requested by City, to execute a written agreement on terms acceptable to City confirming that the Subcontractor is bound to City under the same terms as the subcontract.
(vii) Submit Applications for payment, requests for Change Orders and extensions of time and Claims, and to comply with all other notice and submission requirements of the Contract Documents, sufficiently in advance to allow Contractor time to comply with its obligations under the Contract Documents.
(viii) Purchase and maintain insurance in accordance with the requirements of the Contract Documents and reserving the right to Owner to purchase, in its sole discretion, such insurance pursuant to an Owner Controlled Insurance or other form of wrap-up program.
(ix) Provide the same defense indemnification of the City as is required of the Contractor.
(x) Agree to participate in the dispute resolution procedures specified in the Construction Contract, at the election of City.
5.2.3 Contractor shall promptly, after execution, furnish to City true, complete, and executed copies of all subcontracts, and any change orders and modifications thereto. Progress payments shall not be made for items of Work for which City has not received executed subcontracts and, if applicable, Change Orders.
5.2.4 Nothing contained in the Contract Documents shall create any contractual relationship between any Subcontractor and City, except when, and only to the extent that, City elects to accept the assignment of the subcontract with such Subcontractor pursuant to Section 5.3, Contingent Assignment of Subcontracts. Notwithstanding the foregoing, City is deemed a third third-party beneficiary of each subcontract agreement.
5.2.5 City and the Construction Manager shall have the right to communicate with Contractor’s Subcontractors with respect to matters that are related to Contractor’s performance of its obligations under the Contract Documents. Contractor shall be provided with a copy of all such written communications. Such communications shall not create or be interpreted as creating any contractual relationship between City or the Construction Manager and any such Subcontractor.
Appears in 12 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
SUBCONTRACTOR RELATIONS.
5.2.1 Prior to the execution of each subcontract agreement, Contractor shall make available to each proposed Subcontractor, copies of the Contract Documents. Contractor must incorporate the terms of these Contract Documents into each subcontract, so that each Subcontractor will be bound by the terms of these Contract Documents, including, but not limited to, the provisions for dispute resolution. Within thirty (30) Days of the Notice To Proceed, Contractor shall provide City with a complete listing of all Subcontractors, which shall include, but not be limited to, the Work contracted for, Subcontractor’s name, address, telephone and facsimile numbers, form for doing business (i.e, sole proprietor, corporation, partnership), point-of-contact and Subcontractor’s license classification and number.
5.2.2 Any part of the Work work on the Project performed for Contractor the Design Build Entity by a first Tier Subcontractor shall be pursuant to a written subcontract. Each such subcontract shall require that the Subcontractor:
(i) Perform , to the Work in accordance with extent of the work to be performed by the Subcontractor, to be bound to the Design Build Entity by the terms of the Contract Documents.
(ii) Assume , to assume toward Contractor the Design Build Entity all the obligations and responsibilities which Contractor the Design Build Entity assumes towards the City by the Contract Documents.
(iii) Preserve , and to perform such portion of the work on the Project in accordance with the Contract Documents. Each such subcontract shall preserve and protect the rights of the City under the Contract Documents Documents, with respect to the Work work to be performed by the Subcontractor Subcontractor, so that subcontracting thereof will not prejudice such rights.. Where appropriate, the Design Build Entity shall require each Subcontractor to enter into similar agreements with Sub-Subcontractors. The Design Build Entity shall make available to each proposed Subcontractor, prior to the execution of the subcontract agreement, copies of the Contract to which the Subcontractor will be bound. Subcontractors shall similarly make copies of applicable portions of such documents available to their respective proposed Sub-Subcontractors. The Design Build Entity shall cause each such subcontract to expressly include the following requirements:
(iva) Waive Subcontractor waives all rights that the Subcontractor may have against the City for damages caused by fire or other perils covered by builder's ’s risk property insurance carried by Contractor Design Build Entity or the City, except for such rights Subcontractor may have to the proceeds of such insurance held by the City under Article 11 of these General Conditions11.
(vb) Afford The City and entities and agencies designated by the City the same rights and remedies with respect to will have access to and the right to audit and the right to copy at the City's ’s cost all of the Subcontractor's ’s books, records, contracts, correspondence, instructions, drawings, receipts, vouchers, purchase orders orders, and memoranda relating to work on the Work and requiring the Project. Subcontractor to shall preserve all such records and other items for a period of at least three (3) 3 years after Final Completion.
(vic) Recognize The Design Build Entity is responsible for reviewing and coordinating the rights work of City under Section 5.3 and among his subcontractors and the Design Professional of Record. This review and coordination includes, but is not limited to, resolution of any inconsistencies, errors or omissions.
5.2.2 Upon the request of the General ConditionsCity, Contingent Assignment of Subcontracts, including, without limitation, City’s right to elect to accept assignment of the subcontract and to retain Subcontractor pursuant Design Build Entity shall promptly furnish to the terms of the subcontract, to complete the unperformed obligations under the subcontract and, if requested by City, to execute City a written agreement on terms acceptable to City confirming that the Subcontractor is bound to City under the same terms as the subcontract.
(vii) Submit Applications for payment, requests for Change Orders and extensions of time and Claims, and to comply with all other notice and submission requirements of the Contract Documents, sufficiently in advance to allow Contractor time to comply with its obligations under the Contract Documents.
(viii) Purchase and maintain insurance in accordance with the requirements of the Contract Documents and reserving the right to Owner to purchase, in its sole discretion, such insurance pursuant to an Owner Controlled Insurance or other form of wrap-up program.
(ix) Provide the same defense indemnification of the City as is required of the Contractor.
(x) Agree to participate in the dispute resolution procedures specified in the Construction Contract, at the election of City.
5.2.3 Contractor shall promptly, after execution, furnish to City true, complete, and executed copies of all subcontracts, and any change orders and modifications thereto. Progress payments shall not be made for items of Work for which City has not received executed subcontracts and, if applicable, Change Orders.
5.2.4 Nothing contained in the Contract Documents shall create any contractual relationship between any Subcontractor and City, except when, and only to the extent that, City elects to accept the assignment of the subcontract with such Subcontractor pursuant to Section 5.3, Contingent Assignment of Subcontracts. Notwithstanding the foregoing, City is deemed a third party beneficiary of each subcontract agreement.
5.2.5 City and the Construction Manager shall have the right to communicate with Contractor’s Subcontractors with respect to matters that are related to Contractor’s performance of its obligations under the Contract Documents. Contractor shall be provided with a copy of all such written communications. Such communications shall not create or be interpreted as creating any contractual relationship between City or the Construction Manager and any such Subcontractorsubcontract.
Appears in 1 contract
Samples: Design Build Contract
SUBCONTRACTOR RELATIONS.
5.2.1 Prior to the execution of each subcontract agreement, Contractor shall make available to each proposed Subcontractor, copies of the Contract Documents. Contractor must incorporate the terms of these Contract Documents into each subcontract, so that each Subcontractor will be bound by the terms of these Contract Documents, including, but not limited to, the provisions for dispute resolution. Within thirty (30) Days of the Notice To Proceed, Contractor shall provide City with a complete listing of all Subcontractors, which shall include, but not be limited to, the Work contracted for, Subcontractor’s name, address, telephone and facsimile numbers, form for doing business (i.e, sole proprietor, corporation, partnership), point-of-contact and Subcontractor’s license classification and number.
5.2.2 Any part of the Work performed for Contractor by a first Tier Subcontractor shall be pursuant to a written subcontract. Each such subcontract shall require that the Subcontractor:
(i) Perform the Work in accordance with the terms of the Contract Documents.
(ii) Assume toward Contractor all the obligations and responsibilities which Contractor assumes towards City by the Contract Documents.
(iii) Preserve and protect the rights of City under the Contract Documents with respect to the Work to be performed by the Subcontractor so that subcontracting thereof will not prejudice such rights.
(iv) Waive all rights that the Subcontractor may have against City for damages caused by fire or other perils covered by builder's risk property insurance carried by Contractor or City, except for such rights Subcontractor may have to the proceeds of such insurance held by City under Article 11 of these General Conditions.
(v) Afford City and entities and agencies designated by City the same rights and remedies with respect to access to and the right to audit and the right to copy at City's cost all of the Subcontractor's books, records, contracts, correspondence, instructions, drawings, receipts, vouchers, purchase orders and memoranda relating to the Work and requiring the Subcontractor to preserve all such records and other items for a period of at least three (3) years after Final Completion.
(vi) Recognize the rights of City under Section 5.3 of the General Conditions, Contingent Assignment of Subcontracts, including, without limitation, City’s right to elect to accept assignment of the subcontract and to retain Subcontractor pursuant to the terms of the subcontract, to complete the unperformed obligations under the subcontract and, if requested by City, to execute a written agreement on terms acceptable to City confirming that the Subcontractor is bound to City under the same terms as the subcontract.
(vii) Submit Applications for payment, requests for Change Orders and extensions of time and Claims, and to comply with all other notice and submission requirements of the Contract Documents, sufficiently in advance to allow Contractor time to comply with its obligations under the Contract Documents.
(viii) Purchase and maintain insurance in accordance with the requirements of the Contract Documents and reserving the right to Owner to purchase, in its sole discretion, such insurance pursuant to an Owner Controlled Insurance or other form of wrap-up program.
(ix) Provide the same defense indemnification of the City as is required of the Contractor.
(x) Agree to participate in the dispute resolution procedures specified in the Construction Contract, at the election of City.
5.2.3 Contractor shall promptly, after execution, furnish to City true, complete, and executed copies of all subcontracts, and any change orders and modifications thereto. Progress payments shall not be made for items of Work for which City has not received executed subcontracts and, if applicable, Change Orders.
5.2.4 Nothing contained in the Contract Documents shall create any contractual relationship between any Subcontractor and City, except when, and only to the extent that, City elects to accept the assignment of the subcontract with such Subcontractor pursuant to Section 5.3, Contingent Assignment of Subcontracts. Notwithstanding the foregoing, City is deemed a third third-party beneficiary of each subcontract agreement.
5.2.5 City and the Construction Manager shall have the right to communicate with Contractor’s Subcontractors with respect to matters that are related to Contractor’s performance of its obligations under the Contract Documents. Contractor shall be provided with a copy of all such written communications. Such communications shall not create or be interpreted as creating any contractual relationship between City or the Construction Manager and any such Subcontractor.
Appears in 1 contract
Samples: Construction Contract
SUBCONTRACTOR RELATIONS.
5.2.1 Prior to the execution of each subcontract agreement, Contractor DBE shall make available to each proposed Subcontractor, copies of the Contract Documents. Contractor DBE must incorporate the terms of these Contract Documents into each subcontract, so that each Subcontractor will be bound by the terms of these Contract Documents, including, but not limited to, the provisions for dispute resolution. Within thirty (30) Days of the Notice To Proceed, Contractor DBE shall provide City with a complete listing of all Subcontractors, which shall include, but not be limited to, the Work contracted for, Subcontractor’s name, address, telephone and facsimile numbers, form for doing business (i.ei.e., sole proprietor, corporation, partnership), point-of-contact and Subcontractor’s license classification and number.
5.2.2 Any part of the Work performed for Contractor DBE by a first Tier Subcontractor shall be pursuant to a written subcontract. Each such subcontract shall require that the Subcontractor:
(i) Perform the Work in accordance with the terms of the Contract Documents.
(ii) Assume toward Contractor DBE all the obligations and responsibilities which Contractor DBE assumes towards City by the Contract Documents.
(iii) Preserve and protect the rights of City under the Contract Documents with respect to the Work to be performed by the Subcontractor so that subcontracting thereof will not prejudice such rights.
(iv) Waive all rights that the Subcontractor may have against City for damages caused by fire or other perils covered by builder's risk property insurance carried by Contractor DBE or City, except for such rights Subcontractor may have to the proceeds of such insurance held by City under Article 11 of these General Conditions.
(v) Afford City and entities and agencies designated by City the same rights and remedies with respect to access to and the right to audit and the right to copy at City's cost all of the Subcontractor's books, records, contracts, correspondence, instructions, drawings, receipts, vouchers, purchase orders and memoranda relating to the Work and requiring the Subcontractor to preserve all such records and other items for a period of at least three (3) years after Final Completion.
(vi) Recognize the rights of City under Section 5.3 of the General Conditions, Contingent Assignment of Subcontracts, including, without limitation, City’s right to elect to accept assignment of the subcontract and to retain Subcontractor pursuant to the terms of the subcontract, to complete the unperformed obligations under the subcontract and, if requested by City, to execute a written agreement on terms acceptable to City confirming that the Subcontractor is bound to City under the same terms as the subcontract.
(vii) Submit Applications for payment, requests for Change Orders and extensions of time and Claims, and to comply with all other notice and submission requirements of the Contract Documents, sufficiently in advance to allow Contractor DBE time to comply with its obligations under the Contract Documents.
(viii) Purchase and maintain insurance in accordance with the requirements of the Contract Documents and reserving the right to Owner City to purchase, in its sole discretion, such insurance pursuant to an Owner City Controlled Insurance or other form of wrap-up programupprogram.
(ix) Provide the same defense indemnification of the City as is required of the ContractorDBE.
(x) Agree to participate in the dispute resolution procedures specified in the Construction Contract, at the election of City.
5.2.3 Contractor DBE shall promptly, after execution, furnish to City true, complete, and executed copies of all subcontracts, and any change orders and modifications thereto. Progress payments shall not be made for items of Work for which City has not received executed subcontracts and, if applicable, Change Orders.
5.2.4 Nothing contained in the Contract Documents shall create any contractual relationship between any Subcontractor and City, except when, and only to the extent that, City elects to accept the assignment of the subcontract with such Subcontractor pursuant to Section 5.3, Contingent Assignment of Subcontracts. Notwithstanding the foregoing, City is deemed a third party beneficiary of each subcontract agreement.
5.2.5 City and the Construction Manager shall have the right to communicate with ContractorDBE’s Subcontractors with respect to matters that are related to ContractorDBE’s performance of its obligations under the Contract Documents. Contractor DBE shall be provided with a copy of all such written communications. Such communications shall not create or be interpreted as creating any contractual relationship between City or the Construction Manager and any such Subcontractor.
Appears in 1 contract
Samples: Design Build Contract
SUBCONTRACTOR RELATIONS.
5.2.1 Prior to the execution of each subcontract agreement, Contractor shall make available to each proposed Subcontractor, copies of the Contract Documents. Contractor must incorporate the terms of these Contract Documents into each subcontract, so that each Subcontractor will be bound by the terms of these Contract Documents, including, but not limited to, the provisions for dispute resolution. Within thirty (30) Days of the Notice To Proceed, Contractor shall provide City with a complete listing of all Subcontractors, which shall include, but not be limited to, the Work contracted for, Subcontractor’s name, address, telephone and facsimile numbers, form for doing business (i.ei.e., sole proprietor, corporation, partnership), point-of-contact and Subcontractor’s license classification and number.
5.2.2 Any part of the Work performed for Contractor by a first Tier Subcontractor shall be pursuant to a written subcontract. Each such subcontract shall require that the Subcontractor:
(i) Perform the Work in accordance with the terms of the Contract Documents.
(ii) Assume toward Contractor all the obligations and responsibilities which Contractor assumes towards City by the Contract Documents.
(iii) Preserve and protect the rights of City under the Contract Documents with respect to the Work to be performed by the Subcontractor so that subcontracting thereof will not prejudice such rights.
(iv) Waive all rights that the Subcontractor may have against City for damages caused by fire or other perils covered by builder's risk property insurance carried by Contractor or City, except for such rights Subcontractor may have to the proceeds of such insurance held by City under Article 11 of these General Conditions.
(v) Afford City and entities and agencies designated by City the same rights and remedies with respect to access to and the right to audit and the right to copy at City's cost all of the Subcontractor's books, records, contracts, correspondence, instructions, drawings, receipts, vouchers, purchase orders and memoranda relating to the Work and requiring the Subcontractor to preserve all such records and other items for a period of at least three (3) years after Final Completion.
(vi) Recognize the rights of City under Section 5.3 of the General Conditions, Contingent Assignment of Subcontracts, including, without limitation, City’s right to elect to accept assignment of the subcontract and to retain Subcontractor pursuant to the terms of the subcontract, to complete the unperformed obligations under the subcontract and, if requested by City, to execute a written agreement on terms acceptable to City confirming that the Subcontractor is bound to City under the same terms as the subcontract.
(vii) Submit Applications for payment, requests for Change Orders and extensions of time and Claims, and to comply with all other notice and submission requirements of the Contract Documents, sufficiently in advance to allow Contractor time to comply with its obligations under the Contract Documents.
(viii) Purchase and maintain insurance in accordance with the requirements of the Contract Documents and reserving the right to Owner to purchase, in its sole discretion, such insurance pursuant to an Owner Controlled Insurance or other form of wrap-up program.
(ix) Provide the same defense indemnification of the City as is required of the Contractor.
(x) Agree to participate in the dispute resolution procedures specified in the Construction Contract, at the election of City.
5.2.3 Contractor shall promptly, after execution, furnish to City true, complete, and executed copies of all subcontracts, and any change orders and modifications thereto. Progress payments shall not be made for items of Work for which City has not received executed subcontracts and, if applicable, Change Orders.
5.2.4 Nothing contained in the Contract Documents shall create any contractual relationship between any Subcontractor and City, except when, and only to the extent that, City elects to accept the assignment of the subcontract with such Subcontractor pursuant to Section 5.3, Contingent Assignment of Subcontracts. Notwithstanding the foregoing, City is deemed a third third-party beneficiary of each subcontract agreement.
5.2.5 City and the Construction Manager shall have the right to communicate with Contractor’s Subcontractors with respect to matters that are related to Contractor’s performance of its obligations under the Contract Documents. Contractor shall be provided with a copy of all such written communications. Such communications shall not create or be interpreted as creating any contractual relationship between City or the Construction Manager and any such Subcontractor.
Appears in 1 contract
Samples: Construction Contract
SUBCONTRACTOR RELATIONS.
5.2.1 Prior to the execution of each subcontract agreement, Contractor shall make available to each proposed Subcontractor, copies of the Contract Documents. Contractor must incorporate the terms of these Contract Documents into each subcontract, so that each Subcontractor will be bound by the terms of these Contract Documents, including, but not limited to, the provisions for dispute resolution. Within thirty (30) Days of the Notice To Proceed, Contractor shall provide City with a complete listing of all Subcontractors, which shall include, but not be limited to, the Work contracted for, Subcontractor’s name, address, telephone and facsimile numbers, form for doing business (i.e, sole proprietor, corporation, partnership), point-of-contact and Subcontractor’s license classification and number.
5.2.2 Any part of the Work work on the Project performed for Contractor the Design Build Entity by a first Tier Subcontractor shall be pursuant to a written subcontract. Each such subcontract shall require that the Subcontractor:
(i) Perform , to the Work in accordance with extent of the work to be performed by the Subcontractor, to be bound to the Design Build Entity by the terms of the Contract Documents.
(ii) Assume , to assume toward Contractor the Design Build Entity all the obligations and responsibilities which Contractor the Design Build Entity assumes towards the City by the Contract Documents.
(iii) Preserve , and to perform such portion of the work on the Project in accordance with the Contract Documents. Each such subcontract shall preserve and protect the rights of the City under the Contract Documents Documents, with respect to the Work work to be performed by the Subcontractor Subcontractor, so that subcontracting thereof will not prejudice such rights.. Where appropriate, the Design Build Entity shall require each Subcontractor to enter into similar agreements with Sub-Subcontractors. The Design Build Entity shall make available to each proposed Subcontractor, prior to the execution of the subcontract agreement, copies of the Contract to which the Subcontractor will be bound. Subcontractors shall similarly make copies of applicable portions of such documents available to their respective proposed Sub-Subcontractors. The Design Build Entity shall cause each such subcontract to expressly include the following requirements:
(iva) Waive Subcontractor waives all rights that the Subcontractor may have against the City for damages caused by fire or other perils covered by builder's ’s risk property insurance carried by Contractor Design Build Entity or the City, except for such rights Subcontractor may have to the proceeds of such insurance held by the City under Article 11 of these General Conditions11.
(vb) Afford The City and entities and agencies designated by the City the same rights and remedies with respect to will have access to and the right to audit and the right to copy at City's the City have cost all of the Subcontractor's ’s books, records, contracts, correspondence, instructions, drawings, receipts, vouchers, purchase orders orders, and memoranda relating to work on the Work and requiring the Project. Subcontractor to shall preserve all such records and other items for a period of at least three (3) 3 years after Final Completion.
(vic) Recognize The Design Build Entity is responsible for reviewing and coordinating the rights work of City under Section 5.3 and among his subcontractors and the Design Professional of Record. This review and coordination includes, but is not limited to, resolution of any inconsistencies, errors or omissions.
5.2.2 Upon the request of the General ConditionsCity, Contingent Assignment of Subcontracts, including, without limitation, City’s right to elect to accept assignment of the subcontract and to retain Subcontractor pursuant Design Build Entity shall promptly furnish to the terms of the subcontract, to complete the unperformed obligations under the subcontract and, if requested by City, to execute City a written agreement on terms acceptable to City confirming that the Subcontractor is bound to City under the same terms as the subcontract.
(vii) Submit Applications for payment, requests for Change Orders and extensions of time and Claims, and to comply with all other notice and submission requirements of the Contract Documents, sufficiently in advance to allow Contractor time to comply with its obligations under the Contract Documents.
(viii) Purchase and maintain insurance in accordance with the requirements of the Contract Documents and reserving the right to Owner to purchase, in its sole discretion, such insurance pursuant to an Owner Controlled Insurance or other form of wrap-up program.
(ix) Provide the same defense indemnification of the City as is required of the Contractor.
(x) Agree to participate in the dispute resolution procedures specified in the Construction Contract, at the election of City.
5.2.3 Contractor shall promptly, after execution, furnish to City true, complete, and executed copies of all subcontracts, and any change orders and modifications thereto. Progress payments shall not be made for items of Work for which City has not received executed subcontracts and, if applicable, Change Orders.
5.2.4 Nothing contained in the Contract Documents shall create any contractual relationship between any Subcontractor and City, except when, and only to the extent that, City elects to accept the assignment of the subcontract with such Subcontractor pursuant to Section 5.3, Contingent Assignment of Subcontracts. Notwithstanding the foregoing, City is deemed a third party beneficiary of each subcontract agreement.
5.2.5 City and the Construction Manager shall have the right to communicate with Contractor’s Subcontractors with respect to matters that are related to Contractor’s performance of its obligations under the Contract Documents. Contractor shall be provided with a copy of all such written communications. Such communications shall not create or be interpreted as creating any contractual relationship between City or the Construction Manager and any such Subcontractorsubcontract.
Appears in 1 contract
Samples: Design Build Contract
SUBCONTRACTOR RELATIONS.
5.2.1 Prior to the execution of each subcontract agreement, Contractor shall make available to each proposed Subcontractor, copies of the Contract Documents. Contractor must incorporate the terms of these Contract Documents into each subcontract, so that each Subcontractor will be bound by the terms of these Contract Documents, including, but not limited to, the provisions for dispute resolution. Within thirty (30) Days of the Notice To Proceed, Contractor shall provide City with a complete listing of all Subcontractors, which shall include, but not be limited to, the Work contracted for, Subcontractor’s name, address, telephone and facsimile numbers, form for doing business (i.e, sole proprietor, corporation, partnership), point-of-contact and Subcontractor’s license classification and number.
5.2.2 Any part of the Work performed for Contractor by a first Tier Subcontractor shall be pursuant to a written subcontract. Each such subcontract shall require that the Subcontractor:Subcontractor:
(i) Perform the Work in accordance with the terms of the Contract Documents.
(ii) Assume toward Contractor all the obligations and responsibilities which Contractor assumes towards City by the Contract Documents.
(iii) Preserve and protect the rights of City under the Contract Documents with respect to the Work to be performed by the Subcontractor so that subcontracting thereof will not prejudice such rights.
(iv) Waive all rights that the Subcontractor may have against City for damages caused by fire or other perils covered by builder's risk property insurance carried by Contractor or City, except for such rights Subcontractor may have to the proceeds of such insurance held by City under Article 11 of these General Conditions.
(v) Afford City and entities and agencies designated by City the same rights and remedies with respect to access to and the right to audit and the right to copy at City's cost all of the Subcontractor's books, records, contracts, correspondence, instructions, drawings, receipts, vouchers, purchase orders and memoranda relating to the Work and requiring the Subcontractor to preserve all such records and other items for a period of at least three (3) years after Final Completion.
(vi) Recognize the rights of City under Section 5.3 of the General Conditions, Contingent Assignment of Subcontracts, including, without limitation, City’s right to elect to accept assignment of the subcontract and to retain Subcontractor pursuant to the terms of the subcontract, to complete the unperformed obligations under the subcontract and, if requested by City, to execute a written agreement on terms acceptable to City confirming that the Subcontractor is bound to City under the same terms as the subcontract.
(vii) Submit Applications for payment, requests for Change Orders and extensions of time and Claims, and to comply with all other notice and submission requirements of the Contract Documents, sufficiently in advance to allow Contractor time to comply with its obligations under the Contract Documents.
(viii) Purchase and maintain insurance in accordance with the requirements of the Contract Documents and reserving the right to Owner to purchase, in its sole discretion, such insurance pursuant to an Owner Controlled Insurance or other form of wrap-up program.
(ix) Provide the same defense indemnification of the City as is required of the Contractor.
(x) Agree to participate in the dispute resolution procedures specified in the Construction Contract, at the election of City.
5.2.3 Contractor shall promptly, after execution, furnish to City true, complete, and executed copies of all subcontracts, and any change orders and modifications thereto. Progress payments shall not be made for items of Work for which City has not received executed subcontracts and, if applicable, Change Orders.
5.2.4 Nothing contained in the Contract Documents shall create any contractual relationship between any Subcontractor and City, except when, and only to the extent that, City elects to accept the assignment of the subcontract with such Subcontractor pursuant to Section 5.3, Contingent Assignment of Subcontracts. Notwithstanding the foregoing, City is deemed a third party beneficiary of each subcontract agreement.
5.2.5 City and the Construction Manager shall have the right to communicate with Contractor’s Subcontractors with respect to matters that are related to Contractor’s performance of its obligations under the Contract Documents. Contractor shall be provided with a copy of all such written communications. Such communications shall not create or be interpreted as creating any contractual relationship between City or the Construction Manager and any such Subcontractor.
Appears in 1 contract
Samples: Construction Contract
SUBCONTRACTOR RELATIONS.
5.2.1 Prior to the execution of each subcontract agreement, Contractor shall make available to each proposed Subcontractor, copies of the Contract Documents. Contractor must incorporate the terms of these Contract Documents into each subcontract, so that each Subcontractor will be bound by the terms of these Contract Documents, including, but not limited to, the provisions for dispute resolution. Within thirty (30) Days of the Notice To Proceed, Contractor shall provide City with a complete listing of all Subcontractors, which shall include, but not be limited to, the Work contracted for, Subcontractor’s name, address, telephone and facsimile numbers, form for doing business (i.e, sole proprietor, corporation, partnership), point-of-contact and Subcontractor’s license classification and number.
5.2.2 Any part of the Work performed for Contractor by a first Tier Subcontractor shall be pursuant to a written subcontract. Each such subcontract shall require that the Subcontractor:
(i) Perform the Work in accordance with the terms of the Contract Documents.
(ii) Assume toward Contractor all the obligations and responsibilities which Contractor assumes towards City by the Contract Documents.
(iii) Preserve and protect the rights of City under the Contract Documents with respect to the Work to be performed by the Subcontractor so that subcontracting thereof will not prejudice such rights.
(iv) Waive all rights that the Subcontractor may have against City for damages caused by fire or other perils covered by builder's risk property insurance carried by Contractor or City, except for such rights Subcontractor may have to the proceeds of such insurance held by City under Article 11 of these General Conditions.
(v) Afford City and entities and agencies designated by City the same rights and remedies with respect to access to and the right to audit and the right to copy at City's cost all of the Subcontractor's books, records, contracts, correspondence, instructions, drawings, receipts, vouchers, purchase orders and memoranda relating to the Work and requiring the Subcontractor to preserve all such records and other items for a period of at least three (3) years after Final Completion.
(vi) Recognize the rights of City under Section 5.3 of the General Conditions, Contingent Assignment of Subcontracts, including, without limitation, City’s right to elect to accept assignment of the subcontract and to retain Subcontractor pursuant to the terms of the subcontract, to complete the unperformed obligations under the subcontract and, if requested by City, to execute a written agreement on terms acceptable to City confirming that the Subcontractor is bound to City under the same terms as the subcontract.
(vii) Submit Applications for payment, requests for Change Orders and extensions of time and Claims, and to comply with all other notice and submission requirements of the Contract Documents, sufficiently in advance to allow Contractor time to comply with its obligations under the Contract Documents.
(viii) Purchase and maintain insurance in accordance with the requirements of the Contract Documents and reserving the right to Owner to purchase, in its sole discretion, such insurance pursuant to an Owner Controlled Insurance or other form of wrap-up program.
(ix) Provide the same defense indemnification of the City as is required of the Contractor.
(x) Agree to participate in the dispute resolution procedures specified in the Construction Contract, at the election of City.
5.2.3 Contractor shall promptly, after execution, furnish to City true, complete, and executed copies of all subcontracts, and any change orders and modifications thereto. Progress payments shall not be made for items of Work for which City has not received executed subcontracts and, if applicable, Change Orders.
5.2.4 Nothing contained in the Contract Documents shall create any contractual relationship between any Subcontractor and City, except when, and only to the extent that, City elects to accept the assignment of the subcontract with such Subcontractor pursuant to Section 5.3, Contingent Assignment of Subcontracts. Notwithstanding the foregoing, City is deemed a third party beneficiary of each subcontract agreement.
5.2.5 City and the Construction Manager shall have the right to communicate with Contractor’s Subcontractors with respect to matters that are related to Contractor’s performance of its obligations under the Contract Documents. Contractor shall be provided with a copy of all such written communications. Such communications shall not create or be interpreted as creating any contractual relationship between City or the Construction Manager and any such Subcontractor.
Appears in 1 contract
Samples: Construction Contract
SUBCONTRACTOR RELATIONS.
5.2.1 Prior to the execution of each subcontract agreement, Contractor DBT shall make available to each proposed Subcontractor, copies of the Contract Documents. Contractor DBT must incorporate the terms of these Contract Documents into each subcontract, so that each Subcontractor will be bound by the terms of these Contract Documents, including, but not limited to, the provisions for dispute resolution. Within thirty (30) Days of the Notice To Proceed, Contractor DBT shall provide City with a complete listing of all Subcontractors, which shall include, but not be limited to, the Work contracted for, Subcontractor’s name, address, telephone and facsimile numbers, form for doing business (i.e, sole proprietor, corporation, partnership), point-of-contact and Subcontractor’s license classification and number.
5.2.2 Any part of the Work performed for Contractor DBT by a first Tier Subcontractor shall be pursuant to a written subcontract. Each such subcontract shall require that the Subcontractor:
(i) Perform the Work in accordance with the terms of the Contract Documents.
(ii) Assume toward Contractor DBT all the obligations and responsibilities which Contractor DBT assumes towards City by the Contract Documents.
(iii) Preserve and protect the rights of City under the Contract Documents with respect to the Work to be performed by the Subcontractor so that subcontracting thereof will not prejudice such rights.
(iv) Waive all rights that the Subcontractor may have against City for damages caused by fire or other perils covered by builder's risk property insurance carried by Contractor DBT or City, except for such rights Subcontractor may have to the proceeds of such insurance held by City under Article 11 of these General Conditions.
(v) Afford City and entities and agencies designated by City the same rights and remedies with respect to access to and the right to audit and the right to copy at City's cost all of the Subcontractor's books, records, contracts, correspondence, instructions, drawings, receipts, vouchers, purchase orders and memoranda relating to the Work and requiring the Subcontractor to preserve all such records and other items for a period of at least three (3) years after Final Completion.
(vi) Recognize the rights of City under Section 5.3 of the General Conditions, Contingent Assignment of Subcontracts, including, without limitation, City’s right to elect to accept assignment of the subcontract and to retain Subcontractor pursuant to the terms of the subcontract, to complete the unperformed obligations under the subcontract and, if requested by City, to execute a written agreement on terms acceptable to City confirming that the Subcontractor is bound to City under the same terms as the subcontract.
(vii) Submit Applications for payment, requests for Change Orders and extensions of time and Claims, and to comply with all other notice and submission requirements of the Contract Documents, sufficiently in advance to allow Contractor DBT time to comply with its obligations under the Contract Documents.Documents.
(viii) Purchase and maintain insurance in accordance with the requirements of the Contract Documents and reserving the right to Owner City to purchase, in its sole discretion, such insurance pursuant to an Owner City Controlled Insurance or other form of wrap-up program.
(ix) Provide the same defense indemnification of the City as is required of the ContractorDBT.
(x) Agree to participate in the dispute resolution procedures specified in the Construction Contract, at the election of City.
5.2.3 Contractor DBT shall promptly, after execution, furnish to City true, complete, and executed copies of all subcontracts, and any change orders and modifications thereto. Progress payments shall not be made for items of Work for which City has not received executed subcontracts and, if applicable, Change Orders.
5.2.4 Nothing contained in the Contract Documents shall create any contractual relationship between any Subcontractor and City, except when, and only to the extent that, City elects to accept the assignment of the subcontract with such Subcontractor pursuant to Section 5.3, Contingent Assignment of Subcontracts. Notwithstanding the foregoing, City is deemed a third party beneficiary of each subcontract agreement.
5.2.5 City and the Construction Manager shall have the right to communicate with ContractorDBT’s Subcontractors with respect to matters that are related to ContractorDBT’s performance of its obligations under the Contract Documents. Contractor DBT shall be provided with a copy of all such written communications. Such communications shall not create or be interpreted as creating any contractual relationship between City or the Construction Manager and any such Subcontractor.
Appears in 1 contract
Samples: Design Build Contract