Subcontractor. If a Subcontractor does all or part of the changed Work with employees that work directly for the Subcontractor, the Subcontractor's markup for overhead and profit on the Work the Subcontractor performs with its employees shall be twenty-five percent of the first $50,000 of the net Allowable Costs, and twenty percent of the remaining net Allowable Costs, if any. Determination of a Subcontractor’s extended overhead costs, if any, is the responsibility of the Contractor.
Appears in 56 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Subcontractor. If a Subcontractor does all or part of the changed Work with employees that work directly for the Subcontractor, the Subcontractor's markup for overhead and profit on the Work the Subcontractor performs with its employees shall be twenty-five not exceed twenty- percent of the first $50,000 of the net Allowable Costs, and twenty percent of the remaining net Allowable Costs, if any. Determination of a Subcontractor’s extended overhead costs, if any, is the responsibility of the Contractor.
Appears in 19 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Subcontractor. If a Subcontractor does all or part of the changed Work with employees that work directly for the Subcontractor, the Subcontractor's markup for overhead and profit on the Work the Subcontractor performs with its employees shall be not exceed twenty-five percent of the first $50,000 of the net Allowable Costs, and twenty percent of the remaining net Allowable Costs, if any. Determination of a Subcontractor’s extended overhead costs, if any, is the responsibility of the Contractor.
Appears in 16 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Subcontractor. If a Subcontractor does all or part of the changed Work with employees that work directly for the Subcontractor, the Subcontractor's markup for overhead and profit on the Work the Subcontractor performs with its employees shall be twenty-five percent of the first $50,000 of the net Allowable Costs, and twenty percent of the remaining net Allowable Costs, if any. Determination of a Subcontractor’s extended overhead costs, if any, is are the responsibility of the ContractorDesign-Builder.
Appears in 14 contracts
Samples: Design Build Contract, Design Build Contract, Design Build Contract
Subcontractor. If a Subcontractor does all or part of the changed Work with employees that work directly for the Subcontractor, the Subcontractor's markup for overhead and profit on the Work the Subcontractor performs with its employees shall be twenty-five not exceed twenty percent (20%) of the first $50,000 of the his net Allowable Costs, and twenty percent of the remaining net Allowable Costs, if any. Determination of a Subcontractor’s extended overhead costs, if any, is the responsibility of the Contractor.
Appears in 3 contracts
Samples: Construction Management Contract, Construction Management Contract, Construction Management Contract
Subcontractor. If a Subcontractor subcontractor does all or part of the changed Work work with employees that work directly for the Subcontractorsubcontractor, the Subcontractor's subcontractors markup for overhead and profit on the Work work, the Subcontractor subcontractor performs with its employees shall be twenty-five percent of the first $50,000 of the net Allowable Costs, and twenty percent of the remaining net Allowable Costs, if any. Determination of a Subcontractor’s extended overhead allowable costs, if any, is the responsibility of the Contractor.
Appears in 1 contract
Samples: ssl.doas.state.ga.us