Common use of Submission Cycles Clause in Contracts

Submission Cycles. The data date for each monthly update shall be the last working day of the month. The analysis report shall be submitted within five (5) working days. The submission shall be in paper in sufficient number of copies as required by Princeton University, in Adobe Acrobat (*.pdf) format, and in electronic format. The Contractor shall furnish to Princeton University, for the review of Princeton University, such reports and information as may be requested by Princeton University, including without limitation, the electronic version of the data on which the reports are based, and the electronic version of the reports themselves. Each Updated Project Schedule shall be sequentially numbered and dated for identification, and Contractor shall separately maintain and archive electronically throughout the term of the Contract (e.g., no Updated Project Schedule shall “over-write” the prior version or versions of the Project Schedule or Updated Project Schedule). Contractor shall post all Primavera files and data associated with the Project Schedule and any revisions thereto to the Princeton University CPMS site.

Appears in 13 contracts

Samples: Design Build Contract, Construction Management GMP Contract, Construction Fixed Price Contract

AutoNDA by SimpleDocs

Submission Cycles. The data date for each monthly update shall be the last working day of the month. The analysis report shall be submitted within five (5) 5 working days. The submission shall be in paper in sufficient number of copies as required by Princeton University, in Adobe Acrobat (*.pdf) format, and in electronic format. The Contractor shall furnish to Princeton University, for the review of Princeton University, such reports and information as may be requested by Princeton University, including without limitation, the electronic version of the data on which the reports are based, and the electronic version of the reports themselves. Each Updated Project Schedule shall be sequentially numbered and dated for identification, and Contractor shall separately maintain and archive electronically throughout the term of the Contract (e.g., no Updated Project Schedule shall “over-write” the prior version or versions of the Project Schedule or Updated Project Schedule). Contractor shall post all Primavera files and data associated with the Project Schedule and any revisions thereto to the Princeton University CPMS PCS site.

Appears in 5 contracts

Samples: Construction Services Basic Ordering Agreement, Preconstruction Services Agreement, Construction Services Basic Ordering Agreement

AutoNDA by SimpleDocs

Submission Cycles. The data date for each monthly update shall be the last working day of the month. The analysis report shall be submitted within five (5) 5 working days. The submission shall be in paper in sufficient number of copies as required by Princeton University, in Adobe Acrobat (*.pdf) format, and in electronic format. The Contractor shall furnish to Princeton University, for the review of Princeton University, such reports and information as may be requested by Princeton University, including without limitation, the electronic version of the data on which the reports are based, and the electronic version of the reports themselves. Each Updated Project Schedule shall be sequentially numbered and dated for identification, and Contractor shall separately maintain and archive electronically throughout the term of the Contract (e.g., no Updated Project Schedule shall “over-writeover‐write” the prior version or versions of the Project Schedule or Updated Project Schedule). Contractor shall post all Primavera files and data associated with the Project Schedule and any revisions thereto to the Princeton University CPMS PCS site.

Appears in 2 contracts

Samples: Basic Ordering Agreement, Preconstruction Services Agreement