Common use of Submittal, Approval, and Updates Clause in Contracts

Submittal, Approval, and Updates. Not later than sixty days after the Effective Date of the Contract, but prior to the Proceed Order, the Contractor must submit a Construction Progress Schedule in accordance with Section 2.1.5.

Appears in 39 contracts

Samples: Construction Contract, Construction Contract, Construction Contract

AutoNDA by SimpleDocs

Submittal, Approval, and Updates. Not later than sixty thirty (30) days after the Effective Date of the Contract, but prior to the Proceed Order, the Contractor must submit a Construction Progress Schedule in accordance with Section 2.1.5. The Construction Progress Schedule will include an anticipated Notice to Proceed date and shall be updated based upon the Actual Notice to Proceed within 10 days of receipt of the Proceed Order.

Appears in 35 contracts

Samples: Construction Contract, Construction Contract, Construction Contract

AutoNDA by SimpleDocs

Submittal, Approval, and Updates. Not later than sixty days after the Effective Date of the Contract, but prior to the Proceed Order, the Contractor Design-Builder must submit a Construction Progress Schedule in accordance with Section 2.1.5.

Appears in 17 contracts

Samples: Design Build Contract, Design Build Contract, Design Build Contract