Common use of Substantial Completion and Final Completion Clause in Contracts

Substantial Completion and Final Completion. 5.2.1 Substantial Completion of the entire Work shall be achieved no later than (DATE) (“Scheduled Substantial Completion Date”) unless otherwise stated in the GMP Exhibit. 5.2.2 Interim milestones and/or Substantial Completion of identified portions of the Work (“Scheduled Interim Milestone Dates”) shall be achieved as follows unless otherwise stated in the GMP Exhibit: 5.2.3 For a minimum of ninety (90) calendar days after Substantial Completion or until Final Completion is achieved, whichever is later, provide adequate qualified on-site staff that is authorized to act on behalf of the Design-Builder to coordinate and insure that any outstanding work items, Punch Lists, testing and commissioning are completed, at no additional cost to the Owner. 5.2.4 Final Completion of the Work or identified portions of the Work shall be achieved as expeditiously as reasonably practicable and within 45 Working days of Substantial Completion, unless otherwise agreed by the PMT. Final Completion is the date when all Work is complete pursuant to the definition of Final Completion set forth in Section 6.5 of the General Conditions. 5.2.5 All of the dates set forth in this Article 5 (collectively the “Contract Time(s)”) shall be subject to adjustment in accordance with the General Conditions.

Appears in 6 contracts

Samples: Preliminary Agreement, Agreement Between Owner and Design Builder Cost Plus Fee With a Guaranteed Maximum Price, Agreement Between Owner and Design Builder Cost Plus Fee With a Guaranteed Maximum Price

AutoNDA by SimpleDocs

Substantial Completion and Final Completion. 5.2.1 Substantial Completion of the entire Work shall be achieved no later than (DATESeptember1, 2020 ( ) calendar days after the Date of Commencement (“Scheduled Substantial Completion Date”) unless otherwise stated in ). The parties agree that the GMP Exhibit. 5.2.2 Interim milestones and/or definition for Substantial Completion of identified portions set forth in Section 1.2.18 of the Work (General Conditions of Contract is hereby modified to read as follows: Scheduled Interim Milestone Dates”) Substantial Completion is the date on which the Work, or an agreed upon portion of the Work, is sufficiently complete in accordance with the Contract Documents so that Owner can occupy and use the Project or a portion thereof for its intended purposes, provided, however, that Substantial Completion shall be deemed to have been achieved as follows unless otherwise stated in no later than the GMP Exhibit:date of issuance of a Temporary Certificate of Occupancy issued by the local building official.” 5.2.3 For a minimum of ninety (90) calendar days after Substantial Completion or until Final Completion is achieved, whichever is later, provide adequate qualified on-site staff that is authorized to act on behalf of the Design-Builder to coordinate and insure that any outstanding work items, Punch Lists, testing and commissioning are completed, at no additional cost to the Owner. 5.2.4 Final Completion of the Work or identified portions of the Work shall be achieved as expeditiously as reasonably practicable and within 45 Working days of Substantial Completion, unless otherwise agreed by the PMTpracticable. Final Completion is the date when all Work is complete pursuant to the definition of Final Completion set forth in Section 6.5 1.2.7 of the General ConditionsConditions of Contract. 5.2.5 5.2.4 All of the dates set forth in this Article 5 (collectively the “Contract Time(s)”) shall be subject to adjustment in accordance with the General ConditionsConditions of Contract.

Appears in 1 contract

Samples: Standard Form of Agreement Between Owner and Design Builder Lump Sum