Substantial Completion Certificate. See definition in Paragraph 3(a) hereof.
Substantial Completion Certificate. (a) Project Co shall give the Independent Certifier and the WCH Representative at least 10 Business Days’ notice prior to the date upon which Project Co anticipates all requirements for Substantial Completion shall be satisfied.
(b) Project Co shall give the Independent Certifier and the WCH Representative notice (the “Substantial Completion Notice”) upon the satisfaction of all requirements for Substantial Completion, which Substantial Completion Notice shall describe, in reasonable detail, the satisfaction of the requirements for Substantial Completion, together with Project Co’s opinion as to whether the conditions for issuance of the Substantial Completion Certificate have been satisfied.
(c) WCH shall, within 5 Business Days after receipt of the Substantial Completion Notice, provide the Independent Certifier and Project Co with WCH’s opinion as to whether the conditions for issuance of the Substantial Completion Certificate have been satisfied and, if applicable, any reasons as to why it considers that the Substantial Completion Certificate should not be issued.
(d) Within 5 Business Days after Project Co’s receipt of WCH’s opinion pursuant to Section 24.4(c), the Parties shall cause the Independent Certifier to determine whether the conditions for issuance of the Substantial Completion Certificate have been satisfied, having regard for the opinions of both Project Co and WCH, to determine whether any Minor Deficiencies exist, and to issue to WCH and to Project Co either:
(i) the Substantial Completion Certificate, setting out in such certificate the Substantial Completion Date and the Minor Deficiencies List (if applicable) in accordance with Section 24.8; or
(ii) a report detailing the matters that the Independent Certifier considers are required to be performed by Project Co to satisfy the conditions for issuance of the Substantial Completion Certificate.
(e) Where the Independent Certifier has issued a report in accordance with Section 24.4(d)(ii) and Project Co has not referred a Dispute in relation thereto for resolution in accordance with Schedule 27 - Dispute Resolution Procedure, Project Co shall, within 5 Business Days after receipt of such report, provide the Independent Certifier and the WCH Representative with:
(i) a detailed list indicating the rectification actions proposed for all matters raised in such report;
(ii) the schedule for completion of all such rectification actions; and
(iii) any additional Project Co Commissioning that ne...
Substantial Completion Certificate certifying that the construction of Landlord’s Section 2.3 Work has been substantially completed in accordance with this Section 2.3 and specifying the date of that completion. Thereafter, beginning on the Rent Commencement Date and continuing during the rest of the term of this Lease, Tenant shall be responsible (subject, however, to any corrective obligations of Landlord as expressly set forth in this Lease) for maintenance, repair and/or replacement of all such systems and improvements to the extent required under the provisions of Article 8 hereof. If Landlord’s obligations under this paragraph are violated in any respect, then it shall be the obligation of Landlord, after receipt of written notice from Tenant setting forth with specificity the nature of the violation, to correct promptly and diligently, at Landlord’s sole cost, the condition(s) constituting such violation. However, in the case of the requirements set forth in clause (i) of the first sentence of this paragraph, Tenant’s failure to give such written notice to Landlord within six (6) months after the Rent Commencement Date shall give rise to a conclusive and irrebuttable presumption that Landlord has complied with all Landlord’s obligations under such clause (i), and in the case of the requirements set forth in clauses (ii) through (v) of the first sentence of this paragraph (except with respect to latent defects in the case of the requirements set forth in clauses (iii) and (v) of the first sentence of this paragraph), Tenant’ failure to give such written notice to Landlord regarding any alleged violation within one (1) year after the Rent Commencement Date shall give rise to a conclusive and irrebuttable presumption that Landlord has complied with all Landlord’s obligations under such clauses (ii) through (v). TENANT ACKNOWLEDGES THAT THE WARRANTIES AND/OR OBLIGATIONS CONTAINED IN THIS SECTION 2.3 AND IN THE WORKLETTER (IF APPLICABLE) ARE IN LIEU OF ALL OTHER WARRANTIES, EXPRESS OR IMPLIED, WITH RESPECT TO THE PHYSICAL CONDITION OF THE PREMISES, BUILDING SYSTEMS AND EXISTING IMPROVEMENTS (OTHER THAN TENANT IMPROVEMENTS) IN THE PREMISES, AND THAT LANDLORD MAKES NO OTHER WARRANTIES EXCEPT AS EXPRESSLY SET FORTH IN THIS SECTION 2.3 AND, IN THE CASE OF TENANT IMPROVEMENTS CONSTRUCTED BY LANDLORD UNDER THE WORKLETTER, AS EXPRESSLY SET FORTH IN THE WORKLETTER.
Substantial Completion Certificate. When the conditions set forth in Section 17.4.1 have occurred, Contractor shall submit to Owner a duly executed and completed Substantial Completion Certificate, which certificate shall set forth the date that Substantial Completion is deemed to have occurred as described above.
Substantial Completion Certificate. 7.3.3.1 Design-Builder’s Issuance of Certificate. When Design-Builder believes that Substantial Completion has occurred, it shall issue a Substantial Completion Certificate, supported by such information required by the Contract Documents.
Substantial Completion Certificate. On or before Substantial Completion Deadline, Tenant shall deliver to Landlord Representative a written certification, which has been executed by the Project Architect (the “Substantial Completion Certificate”), certifying the date upon which Substantial Completion and the Commencement of Operations actually occurred, along with such documentation as is necessary (or as Landlord may reasonably require) to substantiate same.
Substantial Completion Certificate. 13.1.1 The Concessionaire will issue to the Independent Certifier and the Province’s Representative a notice informing the Independent Certifier and the Province’s Representative at least 20 Working Days prior to the date upon which the Concessionaire expects the Works will be Substantially Completed. If the Concessionaire has at any time reason to believe that the said date expected for Substantial Completion as aforesaid will be delayed by more than 5 Working Days, it will issue a fresh notice pursuant to this Section 13.1.1 informing the Independent Certifier and the Province’s Representative of the new date expected for Substantial Completion as aforesaid. Upon the Concessionaire notifying the Independent Certifier and the Province’s Representative that Substantial Completion as aforesaid has occurred and subject to the delivery to the Independent Certifier and the Province’s Representative of a Concessionaire’s Substantial Completion Certificate and all other relevant Certificates and supporting documentation in accordance with Part 3 of Schedule 5 [Design and Certification Procedure], the Province’s Representative and the Concessionaire will cause the Independent Certifier to commence within 10 Working Days of receipt of such notice an inspection of the Works (and the Concessionaire will not object to any Interested Party, any Public Authority to whom any Temporary OffSite Facilities are to be handed over and/or any contractors or consultants retained by the Province or any such Interested Party which has a legal obligation or right to inspect the Works or Public Authority participating in such inspection).
13.1.2 The Province’s Representative and the Concessionaire’s Representative will cause the Independent Certifier within 20 Working Days of the commencement of such inspection to either:
13.1.2.1 if Substantial Completion has been attained, issue a Substantial Completion Certificate to the Province and the Concessionaire; or
13.1.2.2 if Substantial Completion has not been attained, notify the Concessionaire’s Representative and the Province’s Representative of its decision not to issue a Substantial Completion Certificate and issue a report detailing the matters that the Independent Certifier considers are required to be performed by the Concessionaire.
13.1.3 The Independent Certifier will refuse to issue a Substantial Completion Certificate if:
13.1.3.1 the Works have not been Substantially Completed; or
13.1 3.2 satisfactory evidence of compli...
Substantial Completion Certificate. A certificate signed by the Architect stating that Tenant's Work has been substantially completed in accordance with the Final Construction Drawings, with the exception of minor items of incomplete work and so-called "punchlist" items.
Substantial Completion Certificate. Upon completion of the construction of the Rail Line, the Contractor shall apply for the Substantial Completion Certificate, which shall be granted by NI subject to the fulfillment of the following conditions, as shall be approved by NI:
Substantial Completion Certificate. Within ten (10) Days following the receipt of the Certificate of Substantial Completion, Company shall inspect the Facility and review all Work and services performed by Contractor with respect thereto, and shall either (i) deliver to Contractor the Certificate of Substantial Completion countersigned and certifying that the requirements of this Contract applicable to Substantial Completion have been fully satisfied for the Facility and Substantial Completion of the Facility has accordingly been achieved or (ii) if reasonable cause exists for doing so, notify Contractor in writing that Substantial Completion of the Facility has not been achieved, stating in detail the reasons therefore. In the event that Company determines that Substantial Completion has not been achieved and Contractor has not disputed Company’s determination, Contractor shall promptly take such corrective action or perform such additional Work or other services as shall achieve Substantial Completion of the Facility and shall issue to Company another Certificate of Substantial Completion. Such procedure shall be repeated until Substantial Completion of the Facility has been achieved; provided, however, that Company shall respond to any such subsequent Certificate of Subsequent Completion within five (5) Days following the receipt thereof.