Substantial Completion Date Concurrence Sample Clauses

Substantial Completion Date Concurrence. The Substantial Completion Date shall be the day on which the Substantial Completion Date Conditions have been achieved, as determined in accordance with this Section. If the Design-Builder certifies in writing pursuant to Section 8.1 that the Substantial Completion Date Conditions have been achieved, the City shall determine, within [30] days following its receipt of such report, whether it concurs in such certification. If the City states in writing that it concurs with the Design-Builder’s certification, the Project shall be deemed to have achieved Substantial Completion and the Substantial Completion Date shall be deemed to have been established on the date of the Design-Builder’s original certification.