Completion of Punch List items. 14.4.1 All items in the Punch List shall be completed by the Concessionaire within 90 (ninety) days of the date of issue of the Provisional Certificate and for any delay thereafter, other than for reasons solely attributable to the Authority or due to Force Majeure, the Authority shall be entitled to recover Damages from the Concessionaire to be calculated and paid for each day of delay until all items are completed, at the lower of (a) 0.1% (zero point one per cent) of the Performance Security, and (b) 0.2% (zero point two per cent) of the cost of completing such items as estimated by the Independent Engineer. Subject to payment of such Damages, the Concessionaire shall be entitled to a further period not exceeding 120 (one hundred and twenty) days for completion of the Punch List items. For the avoidance of doubt, it is agreed that if completion of any item is delayed for reasons solely attributable to the Authority or due to Force Majeure, the completion date thereof shall be determined by the Independent Engineer in accordance with Good Industry Practice, and such completion date shall be deemed to be the date of issue of the Provisional Certificate for the purposes of Damages, if any, payable for such item under this Clause 14.4.1.
Completion of Punch List items xxx.xxxxxx.xxx Downloaded
Completion of Punch List items. Once any Punch List hereunder is agreed upon, Contractor will promptly begin the items thereon. Contractor’s Work on such Punch Lists shall be performed in a manner that does not unreasonably interfere with the commercial operation of the Project. Owner will provide Contractor with reasonable access to the Project Site so that Contractor may perform the Work on the Punch Lists.
Completion of Punch List items. 14.4.1 All items in the Punch List shall be completed by the Concessionaire within 90 (ninety) days of the date of issue of the Provisional Certificate and for any delay thereafter, other than for reasons solely attributable to the Authority or due to Force Majeure, the Authority shall be entitled to recover Damages from the Concessionaire to be calculated and paid for each day of delay until all items are completed, at the lower of (a) 0.1% (zero point one per cent) of the Performance Security or Performance Guarantee, as the case may be, and (b) 0.2% (zero point two per cent) of the cost of completing such items as estimated by the Independent Engineer and/or the Independent Panel, as the case may be. Subject to payment of such Damages, the Concessionaire shall be entitled to a further period not exceeding 120 (one hundred and twenty) days for completion of the Punch List items. For the avoidance of doubt, it is agreed that if completion of any item is delayed for reasons solely attributable to the Authority or due to Force Majeure, the completion date thereof shall be determined by the Independent Engineer and/or the Independent Panel, as the case may be, in accordance with Good Industry Practice, and such completion date shall be deemed to be the date of issue of the Provisional Certificate for the purposes of Damages, if any, payable for such item under this Clause 14.4.1.
Completion of Punch List items. All Punch List Items, other than those ------------------------------- reasonably requiring more than thirty (30) days to complete due to long scheduling or ordering time or other reasonable factors, shall be completed within thirty (30) days after the Completion Date, but in no event later than thirty (30) days after the Outside Completion Date. Any Punch List Items reasonably requiring more than thirty (30) days to complete shall be diligently pursued and completed as promptly as practicable, but in no event later than sixty (60) days after the Outside Completion Date. 2.3
Completion of Punch List items. 14.4.1 All items in the Punch List shall be completed by the Concessionaire within 90 (ninety) days of the date of issue of the Provisional Certificate and for any delay thereafter, other than for reasons solely attributable to the Participating ULBs or due to Force Majeure, which would result in delayed commissioning, the Lead ULB shall encash the Construction Performance Security for construction works as per Clause 9.2.
Completion of Punch List items. 13.4.1. All works in the Punch List shall be completed by the Concessionaire within 90 (ninety) days of the date of issue of the Provisional Certificate and for any delay thereafter, other than for reasons solely attributable to the Authority or due to Force Majeure, the Authority shall be entitled to recover Damages from the Concessionaire for the delay, other than for reasons solely attributable to the Authority or due to Force Majeure, to be calculated and paid for each day of delay until all Punch List items are completed, at 0.1% (zero point one per cent) of the Performance Security. Subject to payment of such Damages, the Concessionaire shall be entitled to a further period not exceeding 90 (ninety) days for completion of the Punch List items. For the avoidance of doubt, it is agreed that if completion of any work is delayed for reasons solely attributable to the Authority or due to Force Majeure, the completion date thereof shall be determined by the Authority’s Chief Engineer in accordance with Good Industry Practice, and such completion date shall be deemed to be the date of issue of the Provisional Certificate for the purposes of Damages, if any, payable for such item under this Clause 13.4.1.
Completion of Punch List items. 6.26.3.1 Before expiration of the Punch List Milestone and before the date of Contract Completion, the CM shall complete all items on the A/E’s Punch List. After completing all items on the A/E’s Punch List, the CM shall provide a written request for Final Inspection of the Work to the A/E.
Completion of Punch List items. 6.26.3.1 Within 30 days after the date of Substantial Completion and before the date of Contract Completion, the DB shall complete all items on the Contracting Authority’s Punch List. After completing all items on the Contracting Authority’s Punch List, the DB shall provide a written request for Final Inspection of the Work to the Contracting Authority.
Completion of Punch List items. All items on the Punch List shall be completed in an expeditious manner in accordance herewith and applicable Laws. In no event shall the completion of all items on a Punch List, including the final Punch List, occur later than thirty (30) days from the Township’s Acceptance of such Punch List, unless such time is extended in writing by the Township.