Common use of Substantial Completion Notification Clause in Contracts

Substantial Completion Notification. When JOC considers the Work to be complete and ready for its intended use (Substantially Complete), JOC shall notify City’s Project Representative of JOC’s conclusion. City then shall inspect the Work to determine the status of completion. If City finds that the Work has been reached Substantial Completion, City shall issue a Certificate of Substantial Completion. The Certificate shall itemize remaining items to be completed or corrected before final payment of the Job Order. Upon receipt of the itemized list of remaining work (hereafter referred to as the “Punch List”) JOC shall promptly proceed to complete or correct items listed on the Punch List.

Appears in 4 contracts

Samples: Job Order Contracting Agreement, Job Order Contracting Agreement, Job Order Contracting Agreement

AutoNDA by SimpleDocs
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!