SUSPENSION BY THE CONTRACTOR FOR CONVENIENCE. § 7.2.1 The Contractor may, without cause, order the Subcontractor in writing to suspend, delay or interrupt the Work of this Subcontract in whole or in part for such period of time as the Contractor may determine. In the event of suspension ordered by the Contractor without fault of the Subcontractor, the Subcontractor may be entitled to an equitable adjustment of the Subcontract Time and Subcontract Sum. § 7.2.2 An adjustment shall be made for increases in the Subcontract Time caused by suspension, delay or interruption. No adjustment shall be made to the extent that
Appears in 3 contracts
Samples: Standard Form of Agreement Between Contractor and Subcontractor, Standard Form of Agreement Between Contractor and Subcontractor, Standard Form of Agreement Between Contractor and Subcontractor
SUSPENSION BY THE CONTRACTOR FOR CONVENIENCE. § 7.2.1 9.3.1 The Contractor may, without cause, order the Subcontractor in writing to suspend, delay delay, or interrupt the Work of this the Subcontract in whole or in part for such period of time as the Contractor may determine. In the event of suspension ordered by the Contractor without fault of the SubcontractorContractor, the Subcontractor may shall be entitled to an equitable adjustment of the Subcontract Time and Subcontract Sum.
§ 7.2.2 An adjustment 9.3.2 The Subcontract Time and Subcontract Sum shall be made adjusted for increases in the Subcontract Time cost and time caused by suspension, delay delay, or interruption. No adjustment shall be made to the extent thatinterruption as described in Section 9.3.1.
Appears in 2 contracts
Samples: Master Agreement, Master Agreement