SUSPENSION BY THE CONTRACTOR FOR CONVENIENCE. § 7.2.1 The Contractor may, without cause, order the Subcontractor in writing to suspend, delay or interrupt the Work of a Subcontract for a Specific Project in whole or in part for such period of time as the Contractor may determine. In the event of suspension ordered by the Contractor, the Subcontractor shall be entitled to an equitable adjustment of the Subcontract Time and Subcontract Sum. § 7.2.2 An adjustment shall be made for increases in the Subcontract Time caused by suspension, delay or interruption. No adjustment shall be made to the extent that .1 performance is, was or would have been so suspended, delayed or interrupted by another cause for which the Subcontractor is responsible; or .2 an equitable adjustment is made or denied under another provision of this Subcontract.
Appears in 2 contracts
Samples: Master Subcontract Agreement, Standard Form of Agreement Between Contractor and Subcontractor
SUSPENSION BY THE CONTRACTOR FOR CONVENIENCE. § 7.2.1 7.3.1 The Contractor may, without cause, order the Subcontractor in writing to suspend, delay or interrupt the Work of a this Subcontract for a Specific Project in whole or in part for such period of time as the Contractor may determine. In the event of suspension ordered by the Contractor, the Subcontractor shall be entitled to an equitable adjustment of the Subcontract Time and Subcontract Sum.
§ 7.2.2 7.3.2 An adjustment shall be made for increases in the Subcontract Time and Subcontract Sum, including profit on the increased cost of performance, caused by suspension, delay or interruption. No adjustment shall be made to the extent that .1 performance is, was or would have been so suspended, delayed or interrupted by another cause for which the Subcontractor is responsible; or .2 an equitable adjustment is made or denied under another provision of this Subcontract.
Appears in 2 contracts
Samples: Master Agreement, Subcontract Agreement
SUSPENSION BY THE CONTRACTOR FOR CONVENIENCE. § 7.2.1 7.3.1 The Contractor may, without cause, order the Subcontractor in writing to suspend, delay or interrupt the Work de of a this Subcontract for a Specific Project in whole or in part for such period of time as the Contractor may determine. In the event of determ suspension ordered by the Contractor, the Subcontractor shall be entitled to an equitable adjustment of the Subcontract adju Time and Subcontract Sum.
§ 7.2.2 An adjustment 7.3.2 The Subcontract Time and Subcontract Sum shall be made adjusted for increases in the Subcontract Time cost and time caused by suspension, delay or interruption as described in Section 7.3.1. Adjustment of the Subcontract Sum shall include profit on the increased cost of performance caused by suspension, delay, or interruption. No adjustment shall be made to the extent that .1 performance is, was or would have been so suspended, delayed delayed, or interrupted by another cause for which the Subcontractor is responsible; or .2 an equitable adjustment is made or denied under another provision of this Subcontract.
Appears in 1 contract
Samples: Standard Form of Agreement Between Contractor and Subcontractor