Common use of Suspension by the University for Convenience Clause in Contracts

Suspension by the University for Convenience. 9.02.1 The University may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the University may determine. 9.02.2 An adjustment shall be made for increases in the Contract Sum and/or Time of Completion of the Contract, including profit on the increased cost of performance, caused by suspension, delay or interruption. No adjustment shall be made to the extent: (1) that performance is, was or would have been so suspended, delayed or interrupted by another cause for which the Contractor is responsible; or (2) that an equitable adjustment is made or denied under another provision of this Contract. The Contractor shall not be paid on account of loss of anticipated profits or revenue or other economic loss or consequential damages arising out of or resulting from such termination. Adjustments made in the cost of performance may have a mutually agreed fixed or percentage fee.

Appears in 2 contracts

Samples: Contract for Construction Management Services, Construction Services Agreement

AutoNDA by SimpleDocs

Suspension by the University for Convenience. 9.02.1 12.02.1 The University may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the University may determine. 9.02.2 12.02.2 An adjustment shall be made for increases in the Contract Sum cost and/or Time time of Completion performance of the Contract, including profit on the increased cost of performance, caused by suspension, delay or interruption. No adjustment shall be made to the extent: (1) that performance is, was or would have been so suspended, delayed or interrupted by another cause for which the Contractor is responsible; or (2) that an equitable adjustment is made or denied under another provision of this Contract. The Contractor shall not be paid on account of loss of anticipated profits or revenue or other economic loss or consequential damages arising out of or resulting from such termination. Adjustments made in the cost of performance may have a mutually agreed fixed or percentage fee.

Appears in 1 contract

Samples: Construction Services Agreement

AutoNDA by SimpleDocs

Suspension by the University for Convenience. 9.02.1 The University may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the University may determine. 9.02.2 An adjustment shall be made for increases in the Contract Sum and/or Time of Completion of the Contract, including profit on the increased cost of performance, caused by suspension, delay or interruption. No adjustment shall be made to the extent: (1) that performance is, was or would have been so suspended, delayed or interrupted by another cause for which the Contractor is responsible; or (2) that an equitable adjustment is made or denied under another provision of this Contract. The Contractor shall not be paid on account of loss of anticipated profits or revenue or other economic loss or consequential damages arising out of or resulting from such termination. Adjustments made in the cost of performance may have a mutually agreed fixed or percentage fee.

Appears in 1 contract

Samples: Contract for Construction Management Services