SUSPENSION OF THE PAYMENT TIME LIMIT. 1. The contracting authority may at any point suspend the payment time limit if a request for payment cannot be processed because it does not comply with the Contract’s provisions. 2. The contracting authority must notify the Expert of the suspension and the reasons for it. 3. The suspension takes effect on the day notification is sent by the contracting authority. 4. If the condition for suspending the payment time limit as referred to in paragraph 1, Article 13, is no longer met, the suspension will be lifted — and the remaining period will resume. If the suspension exceeds two months, the Expert may ask the contracting authority if the suspension will continue. 5. If the payment time limit has been suspended due to the non-compliance of the reports or deliverables in accordance with Article 2 and the revised report or deliverables or payment request is not submitted or was submitted but is also rejected, the contracting authority may also terminate the Contract as referred to in Article 16.
Appears in 1 contract
SUSPENSION OF THE PAYMENT TIME LIMIT. 1. The contracting authority may at any point suspend the payment time limit if a request for payment cannot be processed because it does not comply with the Contract’s provisions.
2. The contracting authority must notify the Expert of the suspension and the reasons for it.
3. The suspension takes effect on the day notification is sent by the contracting authority.
4. If the condition for suspending the payment time limit as referred to in paragraph 1, Article 1312, is no longer met, the suspension will be lifted — and the remaining period will resume. If the suspension exceeds two months, the Expert may ask the contracting authority if the suspension will continue.
5. If the payment time limit has been suspended due to the non-compliance of the reports or deliverables in accordance with Article 2 3 and the revised report or deliverables or payment request is not submitted or was submitted but is also rejected, the contracting authority may also terminate the Contract as referred to in Article 1615.
Appears in 1 contract
SUSPENSION OF THE PAYMENT TIME LIMIT. 1. The contracting authority may at any point suspend the payment time limit if a request for payment cannot be processed because it does not comply with the Contract’s provisions.
2. The contracting authority must notify the Expert expert of the suspension and the reasons for it.
3. The suspension takes effect on the day notification is sent by the contracting authority.
4. If the condition for suspending the payment time limit as referred to in paragraph 1, Article 13, 1 is no longer met, the suspension will be lifted — and the remaining period will resume. If the suspension exceeds two months, the Expert expert may ask the contracting authority if the suspension will continue.
5. If the payment time limit has been suspended due to the non-compliance of the reports or deliverables in accordance with Article 2 and the revised report or deliverables or payment request is not submitted or was submitted but is also rejected, the contracting authority may also terminate the Contract as referred to in Article 1617.
Appears in 1 contract
Samples: Expert Contract
SUSPENSION OF THE PAYMENT TIME LIMIT. 1. The contracting authority may at any point suspend the payment time limit if a request for payment cannot be processed because it does not comply with the Contract’s provisions.
2. The contracting authority must notify the Expert of the suspension and the reasons for it.
3. The suspension takes effect on the day notification is sent by the contracting authority.
4. If the condition for suspending the payment time limit as referred to in paragraph 1, Article 13, 13 is no longer met, the suspension will be lifted — and the remaining period will resume. If the suspension exceeds two months, the Expert may ask the contracting authority if the suspension will continue.
5. If the payment time limit has been suspended due to the non-compliance of the reports or deliverables in accordance with Article 2 and the revised report or deliverables or payment request is not submitted or was submitted but is also rejected, the contracting authority may also terminate the Contract as referred to in Article 16.