Common use of SUSPENSION OR ALTERATION Clause in Contracts

SUSPENSION OR ALTERATION. A. The OWNER may order the CONSULTANT in writing to suspend, delay, or interrupt performance of all or any part or the Work for a reasonable period of time as the OWNER may determine. The order shall contain the reason or reasons for issuance which may include, but shall not be limited to, the following: latent field conditions, substantial program revisions, acquisition of rights-of-way or real property, financial crisis, labor disputes, civil unrest, or Acts of God. B. Upon receipt of a suspension order, the CONSULTANT shall, as soon as practicable, cease performance of the Work as ordered and take immediate affirmative measures to protect such Work from loss or damage. C. The CONSULTANT specifically agrees that such suspension, interruption, or delay of the performance of the Work pursuant to this Item shall not increase the cost of performance of the Work of this Contract. D. Time of Completion of the Work may be extended to such time as the OWNER determines shall compensate for the time lost by the suspension, interruption, or delay, such determination to be set forth in writing.

Appears in 12 contracts

Samples: Commissioning Services Agreement, Contract, Consulting Agreement

AutoNDA by SimpleDocs

SUSPENSION OR ALTERATION. A. The OWNER may order the CONSULTANT CONSTRUCTION MANAGER in writing to suspend, delay, or interrupt performance of all or any part or the Work for a reasonable period of time as the OWNER may determine. The order shall contain the reason or reasons for issuance which may include, but shall not be limited to, the following: latent field conditions, substantial program revisions, acquisition of rights-of-way or real property, financial crisis, labor disputes, civil unrest, or Acts of God. B. Upon receipt of a suspension order, the CONSULTANT CONSTRUCTION MANAGER shall, as soon as practicable, cease performance of the Work as ordered and take immediate affirmative measures to protect such Work from loss or damage. C. The CONSULTANT CONSTRUCTION MANAGER specifically agrees that such suspension, interruption, or delay of the performance of the Work pursuant to this Item shall not increase the cost of performance of the Work of this Contract. D. Time of Completion of the Work may be extended to such time as the OWNER determines shall compensate for the time lost by the suspension, interruption, or delay, such determination to be set forth in writing.

Appears in 10 contracts

Samples: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement

SUSPENSION OR ALTERATION. A. The OWNER may order the CONSULTANT PROFESSIONAL in writing to suspend, delay, or interrupt performance of all or any part or the Work for a reasonable period of time as the OWNER may determine. The order shall contain the reason or reasons for issuance which may include, but shall not be limited to, the following: latent field conditions, substantial program revisions, acquisition of rights-of-way or real property, financial crisis, labor disputes, civil unrest, or Acts of God. B. Upon receipt of a suspension order, the CONSULTANT PROFESSIONAL shall, as soon as practicable, cease performance of the Work as ordered and take immediate affirmative measures to protect such Work from loss or damage. C. The CONSULTANT PROFESSIONAL specifically agrees that such suspension, interruption, or delay of the performance of the Work pursuant to this Item shall not increase the cost of performance of the Work of this Contract. D. Time of Completion of the Work may be extended to such time as the OWNER determines shall compensate for the time lost by the suspension, interruption, or delay, such determination to be set forth in writing.

Appears in 2 contracts

Samples: Consulting Agreement, Consulting Agreement

SUSPENSION OR ALTERATION. A. The OWNER may order the CONSULTANT in writing to suspend, delay, or interrupt performance of all or any part or the Work for a reasonable period of time as the OWNER may determine. The order shall contain the reason or reasons for issuance which may include, but shall not be limited to, the following: latent field conditions, substantial program revisions, acquisition of rights-of-way or real property, financial crisis, labor disputes, civil unrest, or Acts of God. B. Upon receipt of a suspension order, the CONSULTANT shall, as soon as practicable, cease performance of the Work as ordered and take immediate affirmative measures to protect such Work from loss or damage. C. The CONSULTANT specifically agrees that such suspension, interruption, or delay of the performance of the Work pursuant to this Item shall not increase the cost of performance of the Work of this Contract. D. Time of Completion of the Work may be extended to such time as the OWNER determines shall compensate for the time lost by the suspension, interruption, or delay, such determination to be set forth in writing.

Appears in 1 contract

Samples: Consulting Agreement

SUSPENSION OR ALTERATION. A. The OWNER X. XXXXX may order the CONSULTANT in writing to suspend, delay, or interrupt performance of all or any part or the Work for a reasonable period of time as the OWNER DASNY may determine. The order shall contain the reason or reasons for issuance which may include, but shall not be limited to, the following: latent field conditions, substantial program revisions, acquisition of rights-of-way or real property, financial crisis, labor disputes, civil unrest, or Acts of God. B. Upon receipt of a suspension order, the CONSULTANT shall, as soon as practicable, cease performance of the Work as ordered and take immediate affirmative measures to protect such Work from loss or damage. C. The CONSULTANT specifically agrees that such suspension, interruption, or delay of the performance of the Work pursuant to this Item shall not increase the cost of performance of the Work of this Contract. D. Time of Completion of the Work may be extended to such time as the OWNER DASNY determines shall compensate for the time lost by the suspension, interruption, or delay, such determination to be set forth in writing.

Appears in 1 contract

Samples: Consulting Agreement

AutoNDA by SimpleDocs

SUSPENSION OR ALTERATION. A. The OWNER DASNY may order the CONSULTANT in writing to suspend, delay, or interrupt performance of all or any part or the Work for a reasonable period of time as the OWNER DASNY may determine. The order shall contain the reason or reasons for issuance which may include, but shall not be limited to, the following: latent field conditions, substantial program revisions, acquisition of rights-of-way or real property, financial crisis, labor disputes, civil unrest, or Acts of God. B. Upon receipt of a suspension order, the CONSULTANT shall, as soon as practicable, cease performance of the Work as ordered and take immediate affirmative measures to protect such Work from loss or damage. C. The CONSULTANT specifically agrees that such suspension, interruption, or delay of the performance of the Work pursuant to this Item shall not increase the cost of performance of the Work of this Contract. D. Time of Completion of the Work may be extended to such time as the OWNER DASNY determines shall compensate for the time lost by the suspension, interruption, or delay, such determination to be set forth in writing.

Appears in 1 contract

Samples: Consulting Agreement

SUSPENSION OR ALTERATION. A. The OWNER may order the CONSULTANT CONSTRUCTION MANAGER in writing to suspend, delay, or interrupt performance of all or any part or the Work for a reasonable period of time as the OWNER may determine. The order shall contain the reason or reasons for issuance which may include, but shall not be limited to, the following: latent field conditions, substantial program revisions, acquisition of rights-of-way or real property, financial crisis, labor disputes, civil unrest, or Acts of God. B. Upon receipt of a suspension order, the CONSULTANT CONSTRUCTION MANAGER shall, as soon as practicable, cease performance of the Work as ordered and take immediate affirmative measures to protect such Work from loss or damage. C. The CONSULTANT CONSTRUCTION MANAGER specifically agrees that such suspension, interruption, or delay of the performance of the Work pursuant to this Item shall not increase the cost of performance of the Work of this Contract. D. Time of Completion of the Work may be extended to such time as the OWNER determines shall compensate for the time lost by the suspension, interruption, or delay, such determination to be set forth in writing.

Appears in 1 contract

Samples: Construction Management Agreement