TERMINATION FOR CONVENIENCE AND RIGHT OF SUSPENSION. 19.1 Owner shall have the right to terminate this Agreement without cause upon seven (7) calendar days written notice to Contractor. In the event of such termination for convenience, Contractor's recovery against Owner shall be limited to that portion of the Contract Amount earned through the date of termination, together with any retainage withheld and reasonable termination expenses incurred, but Contractor shall not be entitled to any other or further recovery against Owner, including, but not limited to, damages or any anticipated profit on portions of the Work not performed. 19.2 Owner shall have the right to suspend all or any portions of the Work upon giving Contractor not less than two (2) calendar days' prior written notice of such suspension. If all or any portion of the Work is so suspended, Contractor's sole and exclusive remedy shall be to seek an extension of time to its schedule in accordance with the procedures set forth in the Contract Documents. In no event shall the Contractor be entitled to any additional compensation or damages. Provided, however, if the ordered suspension exceeds six (6) months, the Contractor shall have the right to terminate the Agreement with respect to that portion of the Work which is subject to the ordered suspension.
Appears in 12 contracts
Samples: Construction Agreement, Construction Agreement, Construction Agreement
TERMINATION FOR CONVENIENCE AND RIGHT OF SUSPENSION. 19.1 22.1 Owner shall have the right to terminate this Agreement Contract without cause upon seven (7) calendar days written notice to Construction Contractor. In the event of such termination for convenience, Construction Contractor's ’s recovery against Owner shall be limited to that portion of the Contract Amount earned through the date of termination, together with any retainage withheld and reasonable termination expenses incurred, but Construction Contractor shall not be entitled to any other or further recovery against Owner, including, but not limited to, damages or any anticipated profit on portions of the Work not performed.
19.2 22.2 Owner shall have the right to suspend all or any portions of the Work upon giving Construction Contractor not less than two (2) calendar days' ’ prior written notice of such suspension. If all or any portion of the Work is so suspended, Construction Contractor's ’s sole and exclusive remedy shall be to seek an extension of time to its schedule the Contract Time in accordance with the procedures set forth in the Contract Documents. In no event shall the Construction Contractor be entitled to any additional compensation or damagesdamages except as otherwise expressly provided for in the Contract Documents. Provided, however, if the ordered suspension exceeds six ninety (690) monthscalendar days, the Construction Contractor shall have the right to terminate the Agreement Contract with respect to that portion of the Work which is subject to the ordered suspension.
Appears in 3 contracts
Samples: Project Construction Management Contract, Project Construction Management Contract, Project Construction Management Contract
TERMINATION FOR CONVENIENCE AND RIGHT OF SUSPENSION. 19.1 6.2.1 Owner shall have the right to terminate this Agreement agreement without cause upon seven (7) calendar days days’ written notice to Contractor. In the event of such termination for convenience, Contractor's ’s recovery against Owner shall be limited to that portion of the Contract Amount contract amount earned through the date of termination, together with any retainage withheld and reasonable termination expenses incurred, but Contractor shall not be entitled to any other or further recovery against Owner, including, but not limited to, to damages or any anticipated profit on portions of the Work work not performed.
19.2 6.2.2 Owner shall have the right to suspend all or any portions of the Work work upon giving Contractor not less than two (2) calendar days' ’ prior written notice of such suspension. If all or any portion of the Work work is so suspended, Contractor's ’s sole and exclusive remedy shall be to seek an extension of time to its schedule in accordance with the procedures set forth in the Contract Documentscontract documents. In no event shall the Contractor be entitled to any additional compensation or damages. Provided, however, if the ordered suspension exceeds six three (63) months, the Contractor shall have the right to terminate the Agreement agreement with respect to that portion of the Work work which is subject to the ordered suspension.
Appears in 2 contracts
Samples: Standard Form of Agreement Between Owner and Contractor, Standard Form of Agreement Between Owner and Contractor
TERMINATION FOR CONVENIENCE AND RIGHT OF SUSPENSION. 19.1 19.1. Owner shall have the right to terminate this Agreement without cause upon seven (7) calendar days written notice to Contractor. In the event of such termination for convenience, Contractor's recovery against Owner shall be limited to that portion of the Contract Amount earned through the date of termination, together with any retainage withheld and reasonable termination expenses incurred, but Contractor shall not be entitled to any other or further recovery against Owner, including, but not limited to, damages or any anticipated profit on portions of the Work not performed.
19.2 19.2. Owner shall have the right to suspend all or any portions of the Work upon giving Contractor not less than two (2) calendar days' prior written notice of such suspension. If all or any portion of the Work is so suspended, Contractor's sole and exclusive remedy shall be to seek an extension of time to its schedule in accordance with the procedures set forth in the Contract Documents. In no event shall the Contractor be entitled to any additional compensation or damages. Provided, however, if the ordered suspension exceeds six (6) months, the Contractor shall have the right to terminate the Agreement with respect to that portion of the Work which is subject to the ordered suspension.
Appears in 2 contracts
Samples: Construction Agreement, Construction Agreement
TERMINATION FOR CONVENIENCE AND RIGHT OF SUSPENSION. 19.1 19.1. Owner shall have the right to terminate this Agreement without cause upon seven (7) calendar days written notice to ContractorDesign Builder. In the event of such termination for convenience, ContractorDesign Builder's recovery against Owner shall be limited to that portion of the Contract Amount earned through the date of termination, together with any retainage withheld and reasonable termination expenses incurred, but Contractor Design Builder shall not be entitled to any other or further recovery against Owner, including, but not limited to, damages or any anticipated profit on portions of the Work not performed.
19.2 19.2. Owner shall have the right to suspend all or any portions of the Work upon giving Contractor Design Builder not less than two five (25) calendar days' prior written notice of such suspension. If all or any portion of the Work is so suspended, ContractorDesign Builder's sole and exclusive remedy shall be to seek an extension of time to its schedule in accordance with the procedures set forth in the Contract Documents. In no event shall the Contractor Design Builder be entitled to any additional compensation or damages. Provided, however, if the ordered suspension exceeds six (6) months, the Contractor Design Builder shall have the right to terminate the Agreement with respect to that portion of the Work which is subject to the ordered suspension.
Appears in 1 contract
Samples: Design Build Services Agreement