Testing and Inspection of Metering System. 8.2.1 The Seller shall inspect and test at its own expense the Metering System [and the associated SCADA System] and the Purchaser shall inspect and test at its own expense the Backup Metering System [and the associated SCADA System] for accuracy in accordance with Schedule 4 - by the date required for the completion of the Interconnection Facilities under Clause Error! Reference source not found., and thereafter at intervals of not less than hundred and eighty (180) Days. 8.2.2 With respect to each testing of the Metering System [and the associated SCADA System], the Seller shall give the Purchaser no less than forty eight (48) hours advance notice during Business Days of such testing, and the Purchaser shall have a representative present during any such testing, as well as during any inspection of the Metering System [and the associated SCADA System] or adjustment thereof (but the test, inspection or adjustment may be taken if the Purchaser has no representative present if the Purchaser was informed in accordance with this Clause). 8.2.3 With respect to each testing of the Backup Metering System [and the associated SCADA System], the Purchaser shall give the Seller no less than twenty four (24) hours advance notice during Business Days of such testing, and the Seller shall have a representative present during any such testing, as well as during any inspection of the Backup Metering System [and the associated SCADA System] or adjustment thereof (but the test, inspection or adjustment may be taken if the Seller has no representative present if the Seller was informed in accordance with this Clause).
Appears in 2 contracts
Testing and Inspection of Metering System. 8.2.1 The Seller shall inspect and test at its own expense the Metering System [and the associated SCADA System] and the Purchaser shall inspect and test at its own expense the Backup Metering System [and the associated SCADA System] for accuracy in accordance with Schedule 4 - by the date required for the completion of the Interconnection Facilities under Clause Error! Reference source not found., and thereafter at intervals of not less than hundred thanhundred and eighty (180) Days.
8.2.2 With respect to each testing of the Metering System [and the associated SCADA System], the Seller shall give the Purchaser no less than forty eight (48) hours advance notice during Business Days of such testing, and the Purchaser shall have a representative representatives present during any such testing, as well as during any inspection of the Metering System [and the associated SCADA System] or adjustment thereof (but the test, inspection or adjustment may be taken if the Purchaser has no representative present if the Purchaser was informed in accordance with this Clause).
8.2.3 With respect to each testing of the Backup Metering System [and the associated SCADA System], the Purchaser shall give the Seller no less than twenty four (24) hours advance notice during Business Days of such testing, and the Seller shall have a representative present during any such testing, as well as during any inspection of the Backup Metering System [and the associated SCADA System] or adjustment thereof (but the test, inspection or adjustment may be taken if the Seller has no representative present if the Seller was informed in accordance with this Clause).
Appears in 1 contract
Samples: Power Purchase Agreement
Testing and Inspection of Metering System. 8.2.1 The Seller shall inspect and test at its own expense the Metering System [and the associated SCADA System] and the Purchaser shall inspect and test at its own expense the Backup Metering System [and the associated SCADA System] for accuracy in accordance with Schedule 4 - by the date required for the completion of the Interconnection Facilities under Clause Error! Reference source not found.6.1.5, and thereafter at intervals of not less than hundred and eighty (180) Days.
8.2.2 With respect to each testing of the Metering System [and the associated SCADA System], the Seller shall give the Purchaser no less than forty eight (48) hours advance notice of during Business Days of such testing, and the Purchaser shall have a representative present during any such testing, as well as during any inspection of the Metering System [and the associated SCADA System] or adjustment thereof (but the test, inspection or adjustment may be taken if the Purchaser has no representative present if the Purchaser was informed in accordance with this Clause).
8.2.3 With respect to each testing of the Backup Metering System [and the associated SCADA System], the Purchaser shall give the Seller no less than twenty four (24) hours advance notice during Business Days of such testing, and the Seller shall have a representative present during any such testing, as well as during any inspection of the Backup Metering System [and the associated SCADA System] or adjustment thereof (but the test, inspection or adjustment may be taken if the Seller has no representative present if the Seller was informed in accordance with this Clause).
Appears in 1 contract
Samples: Power Purchase Agreement
Testing and Inspection of Metering System. 8.2.1 The Seller shall inspect and test at its own expense the Metering System [and the associated SCADA System] and the Purchaser shall inspect and test at its own expense the Backup Metering System [and the associated SCADA System] for accuracy in accordance with Schedule 4 - by the date required for the completion of the Interconnection Facilities under Clause Error! Reference source not found., and thereafter at intervals of not less than hundred and eighty (180) Days.
8.2.2 With respect to each testing of the Metering System [and the associated SCADA System], the Seller shall give the Purchaser no less than forty eight (48) hours advance notice during Business Days of such testing, and the Purchaser shall have a representative representatives present during any such testing, as well as during any inspection of the Metering System [and the associated SCADA System] or adjustment thereof (but the test, inspection or adjustment may be taken if the Purchaser has no representative present if the Purchaser was informed in accordance with this Clause).
8.2.3 With respect to each testing of the Backup Metering System [and the associated SCADA System], the Purchaser shall give the Seller no less than twenty four (24) hours advance notice during Business Days of such testing, and the Seller shall have a representative present during any such testing, as well as during any inspection of the Backup Metering System [and the associated SCADA System] or adjustment thereof (but the test, inspection or adjustment may be taken if the Seller has no representative present if the Seller was informed in accordance with this Clause).
Appears in 1 contract
Samples: Power Purchase Agreement
Testing and Inspection of Metering System. 8.2.1 The Seller shall inspect and test at its own expense the Metering System [and the associated SCADA System] and the Purchaser shall inspect and test at its own expense the Backup Metering System [and the associated SCADA System] for accuracy in accordance with Schedule 4 - 4- by the date required for the completion of the Interconnection Facilities under Clause Error! Reference source not found., and thereafter at intervals of not less than hundred and eighty (180) Days.
8.2.2 With respect to each testing of the Metering System [and the associated SCADA System], the Seller shall give the Purchaser no less than forty eight (48) hours advance notice during Business Days of such testing, and the Purchaser shall have a representative representatives present during any such testing, as well as during any inspection of the Metering System [and the associated SCADA System] or adjustment thereof (but the test, inspection or adjustment may be taken if the Purchaser has no representative present if the Purchaser was informed in accordance with this Clause).
8.2.3 With respect to each testing of the Backup Metering System [and the associated SCADA System], the Purchaser shall give the Seller no less than twenty four (24) hours advance notice during Business Days of such testing, and the Seller shall have a representative present during any such testing, as well as during any inspection of the Backup Metering System [and the associated SCADA System] or adjustment thereof (but the test, inspection or adjustment may be taken if the Seller has no representative present if the Seller was informed in accordance with this Clause).
Appears in 1 contract
Samples: Power Purchase Agreement
Testing and Inspection of Metering System. 8.2.1 The Seller shall inspect and test at its own expense the Metering System [and the associated SCADA System] and the Purchaser shall inspect and test at its own expense the Backup Metering System [and the associated SCADA System] for accuracy in accordance with Schedule 4 - by the date required for the completion of the Interconnection Facilities under Clause Error! Reference source not found.6.2, and thereafter at intervals of not less than hundred and eighty (180) Days.
8.2.2 With respect to each testing of the Metering System [and the associated SCADA System], the Seller shall give the Purchaser no less than forty eight (48) hours advance notice of during Business Days of such testing, and the Purchaser shall have a representative representatives present during any such testing, as well as during any inspection of the Metering System [and the associated SCADA System] or adjustment thereof (but the test, inspection or adjustment may be taken if the Purchaser has no representative present if the Purchaser was informed in accordance with this Clause).
8.2.3 With respect to each testing of the Backup Metering System [and the associated SCADA System], the Purchaser shall give the Seller no less than twenty four (24) hours advance notice during Business Days of such testing, and the Seller shall have a representative present during any such testing, as well as during any inspection of the Backup Metering System [and the associated SCADA System] or adjustment thereof (but the test, inspection or adjustment may be taken if the Seller has no representative present if the Seller was informed in accordance with this Clause).
Appears in 1 contract
Samples: Power Purchase Agreement