Common use of TESTING AND INSPECTION Clause in Contracts

TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, Transmission Provider shall test Transmission Provider's Interconnection Facilities and Network Upgrades and Interconnection Customer shall test the Large Generating Facility and Interconnection Customer's Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Each Party shall make any modifications to its facilities that are found to be necessary as a result of such testing. Interconnection Customer shall bear the cost of all such testing and modifications. Interconnection Customer shall generate test energy at the Large Generating Facility only if it has arranged for the delivery of such test energy.

Appears in 25 contracts

Samples: Surplus Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)

AutoNDA by SimpleDocs

TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, the Interconnecting Transmission Provider Owner shall test Interconnecting Transmission Provider's Owner’s Interconnection Facilities and Network Upgrades and Interconnection Customer shall test the Large Generating Facility and the Interconnection Customer's ’s Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Each Party shall make any modifications to its facilities that are found to be necessary as a result of such testing. Interconnection Customer shall bear the cost of all such testing and modifications. Interconnection Customer shall generate test energy at the Large Generating Facility only if it has arranged for the delivery of such test energy.

Appears in 16 contracts

Samples: Large Generator Interconnection Agreement, Interconnection Agreement, Large Generator Interconnection Agreement

TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, Transmission Distribution Provider shall test Transmission Distribution Provider's Interconnection Facilities Facilities, Distribution Upgrades, and Network Upgrades and Interconnection Customer shall test the Large Generating Facility and Interconnection Customer's ’s Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Each Party shall make any modifications to its facilities that are found to be necessary as a result of such testing. Interconnection Customer shall bear the cost of all such testing and modifications. Interconnection Customer shall generate test energy at the Large Generating Facility only if it has arranged for the delivery of such test energy.

Appears in 15 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, Transmission Provider Owner shall test Transmission Provider's Owner’s Interconnection Facilities and Network Upgrades and Interconnection Customer shall test the Large Generating Facility and Interconnection Customer's Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Each Party shall make any modifications to its facilities that are found to be necessary as a result of such testing. Interconnection Customer shall bear the cost of all such testing and modifications. Interconnection Customer shall generate test energy at the Large Generating Facility only if it has arranged for the delivery of such test energy.

Appears in 12 contracts

Samples: Generator Interconnection Agreement, Settlement Agreement, Generator Interconnection Agreement

TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, Transmission Provider shall test Transmission Provider's ’s Interconnection Facilities and Network Upgrades and Interconnection Customer shall test the Large Generating Facility and Interconnection Customer's ’s Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Each Party shall make any modifications to its facilities that are found to be necessary as a result of such testing. Interconnection Customer shall bear the cost of all such testing and modifications. Interconnection Customer shall generate test energy at the Large Generating Facility only if it has arranged for the delivery of such test energy.

Appears in 4 contracts

Samples: Large Generator Interconnection Agreement, Qualifying Facility Large Generator Interconnection Agreement (Qf Lgia), Large Generator Interconnection Agreement

TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, Transmission Distribution Provider shall test Transmission Distribution Provider's Interconnection Facilities Facilities, Distribution Upgrades, and Network Upgrades and Interconnection Customer shall test the Large Generating Facility and Interconnection Customer's ’s Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Each Party shall make any modifications to its facilities that are found to be necessary as a result of such testing. Interconnection Customer shall bear the cost of all such testing and modifications. Interconnection Customer shall generate test energy at the Large Generating Facility only if it has arranged for the delivery of such test energy.

Appears in 4 contracts

Samples: Clustering Large Generator Interconnection Agreement (Clgia), Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement (Lgia)

TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, Transmission Provider shall test Transmission Provider's Interconnection Facilities and Network Upgrades and Interconnection Customer shall test the Large Generating Facility and Interconnection Customer's ’s Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Each Party shall make any modifications to its facilities that are found to be necessary as a result of such testing. Interconnection Customer shall bear the cost of all such testing and modifications. Interconnection Customer shall generate test energy at the Large Generating Facility only if it has arranged for the delivery of such test energy.

Appears in 2 contracts

Samples: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement (Lgia)

AutoNDA by SimpleDocs

TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, Transmission Provider Owner shall test Transmission Provider's Owner’s Interconnection Facilities and Network Upgrades and Interconnection Customer shall test the Large Generating Facility and Interconnection Customer's Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Each Party shall make any modifications to its facilities that are found to be necessary as a result of such testing. Interconnection Customer shall bear the cost of all such testing and modifications. Interconnection Customer shall generate test energy at the Large Generating Facility only if it has arranged for the delivery of such test energy.

Appears in 1 contract

Samples: Interconnection Agreement

TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Modifications.‌ Prior to the Commercial Operation Date, Transmission Provider shall test Transmission Provider's Interconnection Facilities and Network Upgrades and Interconnection Customer shall test the Large Generating Facility and Interconnection Customer's Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Each Party shall make any modifications to its facilities that are found to be necessary as a result of such testing. Interconnection Customer shall bear the cost of all such testing and modifications. Interconnection Customer shall generate test energy at the Large Generating Facility only if it has arranged for the delivery of such test energy.energy.‌

Appears in 1 contract

Samples: Standard Large Generator Interconnection Agreement (Lgia)

TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, Transmission Provider shall test Transmission Provider's ’s Interconnection Facilities and Network Upgrades and Interconnection Customer shall test the Large Generating Facility and Interconnection Customer's ’s Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Each Party shall make any modifications to its facilities that are found to be necessary as a result of such testing. Interconnection Customer shall bear the cost of all such testing and modifications. Interconnection Customer shall generate test energy at the Large Generating Facility only if it has arranged for the delivery of such test energy.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement (Lgia)

TESTING AND INSPECTION. 6.1 Pre-Commercial Pre -Comme rcial Operation Date Testing and Modifications. Prior to the Commercial Commercia l Operation Date, Transmission Provider Owner shall test Transmission Provider's Owner’s Interconnection Facilities and Network Upgrades and Interconnection Customer shall test the Large Generating Facility and Interconnection Customer's Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Each Party shall make any modifications to its facilities that are found to be necessary as a result of such testing. Interconnection Customer shall bear the cost of all such testing and modifications. Interconnection Customer shall generate test energy at the Large Generating Facility only if it has arranged for the delivery of such test energy.

Appears in 1 contract

Samples: Generator Interconnection Agreement