The Site. The site of the Project (the “Site”) shall comprise the site described in Schedule-A in respect of which the Right of Way shall be progressively in accordance with Clause 8.2, provided by the Authority to the Contractor. The Authority shall be responsible for: a) acquiring and providing Right of Way on the Site free from all encroachments and encumbrances, and free access thereto for the execution of this Agreement; b) [obtaining forest clearance and assistance in approval of Environment Management Plan as per provisions of Clause 4.3.] c) [This Right of Way will not include completely free access to locations where working may affect safety of train traffic (i.e relay room, locations boxes etc). In such cases, right of work will be arranged by the Authority Engineer on written request made by Contractor at least 7 days in advance, if such request is reasonable.]
Appears in 6 contracts
Samples: Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement
The Site. The site of the Railway Project (the “Site”) shall comprise the site described in Schedule-A in respect of which the Right of Way shall be progressively in accordance with Clause 8.2, provided by the Authority to the Contractor. The Authority shall be responsible for:
(a) acquiring and & providing Right of Way on the Site in accordance with the [alignment plan, Longitudinal section, Yard Plans/ESP and electrification sectioning diagram] finalised by the Authority and attached with this document, free from all encroachments and encumbrances, and free access thereto for the execution of this Agreement;
b) [obtaining forest clearance and assistance in approval of Environment Management Plan as per provisions of Clause 4.3.]
c) ; [This Right of Way will not include completely free access to locations where working may affect safety of train traffic (i.e i.e. relay room, locations boxes etc). In such cases, right of work will be arranged by the Authority Engineer on written request made by Contractor contractor at least 7 days in advance, if such request is reasonable.]
(b) obtaining environmental clearance & forest clearance for the Railway Project.
Appears in 4 contracts
Samples: Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement
The Site. The site of the Railway Project (the “Site”) shall comprise the site described in Schedule-A in respect of which the Right of Way shall be progressively in accordance with Clause 8.2, provided by the Authority to the Contractor. The Authority shall be responsible for:
(a) acquiring and providing Right of Way on the Site in accordance with the [alignment plan, Longitudinal section, Yard Plans/ESP and electrification sectioning diagram] finalised by the Authority and attached with this document, free from all encroachments and encumbrances, and free access thereto for the execution of this Agreement;
b) [obtaining forest clearance and assistance in approval of Environment Management Plan as per provisions of Clause 4.3.]
c) ; [This Right of Way will not include completely free access to locations where working may affect safety of train traffic (i.e i.e. relay room, locations boxes etc). In such cases, right of work will be arranged by the Authority Engineer on written request made by Contractor contractor at least 7 days in advance, if such request is reasonable.]
(b) obtaining environmental clearance and forest clearance for the Railway Project.
Appears in 1 contract
Samples: Engineering, Procurement and Construction (Epc) Agreement