Third Party Verification. 4.8.1 The RPD shall be further required to provide entry to the sites of the Project (from which power under this Agreement is being made available) free of all encumbrances at all times during the Term of the Agreement to SECI and a third Party nominated by any Indian Governmental Instrumentality for inspection and verification of the works being carried out by the RPD at the site of the Power Project. 4.8.2 The third party may verify the construction works/operation of the Project being carried out by the RPD and if it is found that the construction works/operation of the project is not as per the Prudent Utility Practices, it may seek clarifications from RPD or require the works to be stopped or to comply with the instructions of such third party.
Appears in 4 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Third Party Verification. 4.8.1 The RPD shall be further required to provide entry to the sites of the Project (from which power under this Agreement is being made available) free of all encumbrances at all times during the Term of the Agreement to SECI and a third Party nominated by any Indian Governmental Instrumentality for inspection and verification of the works being carried out by the RPD at the site of the Power Project.
4.8.2 The third party may verify the construction works/operation of the Project being carried out by the RPD / thermal generator and if it is found that the construction works/operation of the project is not as per the Prudent Utility Practices, it may seek clarifications from RPD or require the works to be stopped or to comply with the instructions of such third party.
Appears in 2 contracts
Third Party Verification. 4.8.1 The RPD shall be further required to provide entry to the sites of the Project (from which power under this Agreement is being made available) free of all encumbrances at all times during the Term of the Agreement to SECI and a third Party nominated by any Indian Governmental Instrumentality for inspection and verification of the works being carried out by the RPD at the site of the Power Project. The RPD shall provide full support to SECI and/or the third party in this regard.
4.8.2 The third party may verify the construction works/operation of the Project being carried out by the RPD and if it is found that the construction works/operation of the project is not as per the Prudent Utility Practices, it may seek clarifications from RPD or require the works to be stopped or to comply with the instructions of such third party.
Appears in 2 contracts
Third Party Verification. 4.8.1 The RPD shall be further required to provide entry to the sites of the Project (from which power under this Agreement is being made available) free of all encumbrances at all times during the Term of the Agreement to SECI and a third Party nominated by any Indian Governmental Instrumentality for inspection and verification of the works being carried out by the RPD at the site of the Power Project.
4.8.2 The third party may verify the construction works/operation of the Project being carried out by the RPD / non-RE generator and if it is found that the construction works/operation of the project is not as per the Prudent Utility Practices, it may seek clarifications from RPD or require the works to be stopped or to comply with the instructions of such third party.
Appears in 1 contract
Samples: Power Purchase Agreement