Common use of TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION Clause in Contracts

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety (90) calendar days after the date when the Contract Time commences to run.

Appears in 2 contracts

Samples: Construction Contract, Construction Contract

AutoNDA by SimpleDocs

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety (90) calendar days after in accordance with paragraph 14.07 of the date when the Contract Time commences to runGeneral Conditions on or before September 15th, 2016.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety (90) calendar days after in accordance with paragraph 14.07 of the date when General Conditions on or before January 30th, 2021 and completed ready for final payment in accordance with paragraph 14.07 of the Contract Time commences to runGeneral Conditions on or before February 12th, 2021.

Appears in 1 contract

Samples: Construction Contract Between

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions Conditions, substantially complete on or before November 30th, 2021 and completed and ready for final payment within ninety (90) calendar days after the date when the Contract Time commences to runby January 10, 2022.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty forty-five (8045) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety sixty (9060) calendar days after the date when the Contract Time commences to run.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for by June 11, 2021 with final payment within ninety (90) calendar days after the date when the Contract Time commences to runcompletion no later than June 25, 2021.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete completed within thirty (80) calendar 30 working days after from when traffic is first impacted and that the date when the Contract Time commences to run as provided Work will be substantially completed on or before October 15th, 2020 and completed ready for final payment in accordance with paragraph 2.03 14.07 of the General Conditions and completed and ready for final payment within ninety (90) calendar days after the date when the Contract Time commences to runon or before November 25th, 2020.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven TEN (710) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty ONE HUNDRED THIRTY (80130) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety ONE HUNDRED FIFTY (90150) calendar days after the date when the Contract Time commences to run.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) 45 calendar days after the date when the Contract Time Times commences to run as provided in paragraph 2.03 of the General Conditions Conditions, and completed and ready for final payment in accordance with paragraph 14.07 of the General Conditions within ninety (90) 60 calendar days after the date when the Contract Time Times commences to run.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety (90) calendar days after in accordance with paragraph 14.07 of the date when the Contract Time commences to rungeneral conditions on or before April 25th, 2017.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety (90) calendar days after in accordance with paragraph 14.07 of the date when the Contract Time commences to runGeneral Conditions on or before April 30th, 2017.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed Proceed, which will not be given until after July 4th 2017, and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run by October 13, 2017 as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety (90) calendar days after in accordance with paragraph 14.07 of the date when the Contract Time commences to runGeneral Conditions on or before November 11, 2017.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar 30 working days after from when traffic is first impacted and the date when the Contract Time commences to run as provided Work will be substantially completed on or before October 15th, 2020. Work will be completed ready for final payment in accordance with paragraph 2.03 14.07 of the General Conditions and completed and ready for final payment within ninety (90) calendar days after the date when the Contract Time commences to runon or before November 25th, 2020.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence commences described in Bid Form, such as: within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty sixty (8060) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety (90) calendar days after the date when the Contract Time commences to run.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence commence: within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run on October 15, 2020 as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety forty-one (9041) calendar days after the date when the Contract Time commences to run.of substantial completion

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty four hundred sixty (80460) calendar days after the date when the Contract Time Times commences to run as provided in paragraph 2.03 of the General Conditions Conditions, and completed and ready for final payment in accordance with paragraph 14.07 of the General Conditions within ninety five hundred fifty (90550) calendar days after the date when the Contract Time Times commences to run.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract Contract, as agreed t by the bidder, shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run by September 30, 2017 as provided in paragraph 2.03 of the General Conditions Conditions, and completed and ready for final payment within ninety (90) calendar days after in accordance with paragraph 14.07 of the date when the Contract Time commences to runGeneral Conditions on or before October 31, 2017.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the completed by October 9, 2021. The Contract Time commences to run as provided in paragraph 2.03 and 2.04 of the General Conditions and completed and ready for final payment within ninety (90) calendar days after the date when the Contract Time commences to runConditions.

Appears in 1 contract

Samples: cityoflaramie.org

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty sixty (8060) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety one hundred and one (90101) calendar days after the date when the Contract Time commences to run.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for no later than June 11, 2021, with final payment within ninety (90) calendar days after the date when the Contract Time commences to runcompletion on June 25, 2021.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar 10 days of receipt following issuance of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions completed by November 30th, 2021 and completed final completion by December 31st, 2021 and ready for final payment within ninety (90) calendar days after in accordance with Paragraph 14.07 of the date when the Contract Time commences to runGeneral Conditions.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty three hundred sixty-five (80365) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed Notice to Proceed and ready for final payment within three hundred ninety five (90395) calendar days after the date when the Contract Time commences to run.

Appears in 1 contract

Samples: Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions on or before July 21, 2020 and completed and ready for final payment within ninety (90) calendar days after in accordance with paragraph 14.07 of the date when the Contract Time commences to runGeneral Conditions on or before August 7, 2020.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions Substantially Complete on or before October 31, 2024, and completed Finally Complete and ready for final payment within ninety (90) calendar days after in accordance with paragraph 14.07 of the date when the Contract Time commences to runGeneral Conditions on or before December 13, 2024.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty forty-five (8045) calendar working days after from when traffic is first impacted and that the date when the Contract Time commences to run as provided workwill be substantially completed on or before October 15th, 2020 and completed ready for final payment in accordance with paragraph 2.03 14.07 of the General Conditions and completed and ready for final payment within ninety (90) calendar days after the date when the Contract Time commences to runon or before November 25th, 2020.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence as described in Bid Form, such as: within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (8030) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety forty five (9045) calendar days after the date when the Contract Time commences to run.

Appears in 1 contract

Samples: Construction Contract

AutoNDA by SimpleDocs

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven nine (79) calendar days weeks of receipt of Notice to Proceed and will be substantially complete completed within thirty fourteen (8014) calendar days after the date when the Contract Time commences weeks of receipt of Notice to run as provided in paragraph 2.03 of the General Conditions Proceed with final completion and completed and ready for final payment within ninety (90) calendar days after the date when the Contract Time commences to runno later than June 3, 2022.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and as described in Bid Form, that the Work will be substantially complete within thirty (80) 30 calendar days after the date when the Contract Time Times commences to run as provided in paragraph 2.03 of the General Conditions Conditions, and completed and ready for final payment in accordance with paragraph 14.07 of the General Conditions within ninety (90) 45 calendar days after the date when the Contract Time Times commences to run.

Appears in 1 contract

Samples: Construction Contract Between

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty sixty (8060) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety one hundred one (90101) calendar days after the date when the Contract Time commences to run.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions by October 31, 2018 and completed and ready for final payment within ninety (90) calendar days after the date when the Contract Time commences to runby November 30, 2018.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed July 1, 2025 and ready for final payment within ninety (90) calendar days after the date when the Contract Time commences to runby August 1, 2025.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (8030) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety forty-five (9045) calendar days after the date when the Contract Time commences to run. In no case, shall completion be later than June 30, 2017.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty three hundred (80300) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety three hundred fifteen (90315) calendar days after the date when the Contract Time commences to run.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety (90) calendar days after in accordance with paragraph 14.07 of the date when the Contract Time commences to runGeneral Conditions on or before October 15th, 2016.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty fifty (8050) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety ninety-one (9091) calendar days after the date when the Contract Time commences to run.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed by August 31, 2021 and ready for final payment within ninety (90) calendar days after the date when the Contract Time commences to runby October 1, 2021.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence 6. Xxxxxx agrees that the Work shall commence within seven (7) calendar 14 days of receipt following issuance of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions completed and completed and ready for final payment in accordance with paragraph 14.07 of the General Conditions within ninety (90) 500 calendar days after as indicated in the date when the Contract Time commences to runAgreement.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and Contractor agrees that the Work will be substantially complete within thirty (80) 270 calendar days after the date when the Contract Time Times commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment in accordance with paragraph 14.07 of the General Conditions within ninety (90) 300 calendar days after the date when the Contract Time Times commences to run.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions on or before August 18, 2017 and completed and ready for final payment within ninety (90) calendar days after in accordance with paragraph 14.07 of the date when the Contract Time commences to runGeneral Conditions on or before August 25, 2017.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar 7 days of receipt following issuance of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety (90) calendar days after in accordance with paragraph 14.07 of the date when the Contract Time commences to runGeneral Conditions on or before August 31st, 2021.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty sixty (8060) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety ninety-one (9091) calendar days after the date when the Contract Time commences to run.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven TEN (710) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty ONE HUNDRED FIFTY (80150) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety ONE HUNDRED EIGHTY (90180) calendar days after the date when the Contract Time commences to run.

Appears in 1 contract

Samples: Construction Contract

TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION. (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty two hundred ten (80210) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety two hundred fifty-one (90251) calendar days after the date when the Contract Time commences to run.

Appears in 1 contract

Samples: Construction Contract

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!