Timing of Preliminary Advice and Survey Report. After the last day of fieldwork for a Survey (Last Fieldwork Day) if either the Proponent or SWALSC is contracting the Aboriginal Heritage Service Provider, the Proponent or SWALSC, as the case may be, will ensure that Aboriginal Heritage Service Provider or the Principal Aboriginal Heritage Consultant provides the Parties with: (a) Preliminary Advice (if requested by the Proponent in the Activity Notice or at any other time under clause 12.2), as soon as reasonably practicable, and in any event to SWALSC within 5 Business Days after the Last Fieldwork Day and, after taking into account any comments from SWALSC, to the Proponent within 12 Business Days after the Last Fieldwork Day; (b) a draft Survey Report (if requested by the Proponent in the Activity Notice or at any other time under clause 12.2), as soon as reasonably practicable, and in any event to SWALSC within 15 Business Days after the Last Fieldwork Day, to enable SWALSC to comment on it; and after taking into account any comments from SWALSC, to the Proponent within 25 Business Days after the Last Fieldwork Day; (c) a final Survey Report, taking into account any comments from the Proponent about any identified technical, factual or typographical errors or any issues of non-compliance with the guidelines in part 1, part 2 and/or part 3 of Schedule 6, within 35 Business Days after the Last Fieldwork Day.
Appears in 4 contracts
Samples: Noongar Standard Heritage Agreement, Noongar Standard Heritage Agreement, Noongar Standard Heritage Agreement
Timing of Preliminary Advice and Survey Report. After the last day of fieldwork for a Survey (Last Fieldwork Day) if either the Proponent or SWALSC the RC is contracting the Aboriginal Heritage Service Provider, the Proponent or SWALSCthe RC, as the case may be, will ensure that Aboriginal Heritage Service Provider or the Principal Aboriginal Heritage Consultant provides the Parties with:
(a) Preliminary Advice (if requested by the Proponent in the Activity Notice or at any other time under clause 12.2), as soon as reasonably practicable, and in any event to SWALSC the RC within 5 Business Days after the Last Fieldwork Day and, after taking into account any comments from SWALSCthe RC, to the Proponent within 12 Business Days after the Last Fieldwork Day;
(b) a draft Survey Report (if requested by the Proponent in the Activity Notice or at any other time under clause 12.2), as soon as reasonably practicable, and in any event to SWALSC the RC within 15 Business Days after the Last Fieldwork Day, to enable SWALSC the RC to comment on it; and after taking into account any comments from SWALSCthe RC, to the Proponent within 25 Business Days after the Last Fieldwork Day;
(c) a final Survey Report, taking into account any comments from the Proponent about any identified technical, factual or typographical errors or any issues of non-compliance with the guidelines in part 1, part 2 and/or part 3 of Schedule 6, within 35 Business Days after the Last Fieldwork Day.. 202
Appears in 2 contracts
Samples: Noongar Standard Heritage Agreement, Noongar Standard Heritage Agreement
Timing of Preliminary Advice and Survey Report. After the last day of fieldwork for a Survey (Last Fieldwork Day) if either the Proponent or SWALSC the RC is contracting the Aboriginal Heritage Service Provider, the Proponent or SWALSCthe RC, as the case may be, will ensure that Aboriginal Heritage Service Provider or the Principal Aboriginal Heritage Consultant provides the Parties with:
(a) Preliminary Advice (if requested by the Proponent in the Activity Notice or at any other time under clause 12.2), as soon as reasonably practicable, and in any event to SWALSC the RC within 5 Business Days after the Last Fieldwork Day and, after taking into account any comments from SWALSCthe RC, to the Proponent within 12 Business Days after the Last Fieldwork Day;
(b) a draft Survey Report (if requested by the Proponent in the Activity Notice or at any other time under clause 12.2), as soon as reasonably practicable, and in any event to SWALSC the RC within 15 Business Days after the Last Fieldwork Day, to enable SWALSC the RC to comment on it; and after taking into account any comments from SWALSCthe RC, to the Proponent within 25 Business Days after the Last Fieldwork Day;
(c) a final Survey Report, taking into account any comments from the Proponent about any identified technical, factual or typographical errors or any issues of non-compliance with the guidelines in part 1, part 2 and/or part 3 of Schedule 6, within 35 Business Days after the Last Fieldwork Day.
Appears in 1 contract
Samples: Heritage Agreement
Timing of Preliminary Advice and Survey Report. After the last day of fieldwork for a Survey (Last Fieldwork Day) if either the Proponent or SWALSC the RC is contracting the Aboriginal Heritage Service Provider, the Proponent or SWALSCthe RC, as the case may be, will ensure that Aboriginal Heritage Service Provider or the Principal Aboriginal Heritage Consultant provides the Parties with:
(a) Preliminary Advice (if requested by the Proponent in the Activity Notice or at any other time under clause 12.2), as soon as reasonably practicable, and in any event to SWALSC the RC within 5 Business Days after the Last Fieldwork Day and, after taking into account any comments from SWALSCthe RC, to the Proponent within 12 Business Days after the Last Fieldwork Day;
(b) ; a draft Survey Report (if requested by the Proponent in the Activity Notice or at any other time under clause 12.2), as soon as reasonably practicable, and in any event to SWALSC the RC within 15 Business Days after the Last Fieldwork Day, to enable SWALSC the RC to comment on it; and after taking into account any comments from SWALSCthe RC, to the Proponent within 25 Business Days after the Last Fieldwork Day;
(c) ; a final Survey Report, taking into account any comments from the Proponent about any identified technical, factual or typographical errors or any issues of non-compliance with the guidelines in part 1, part 2 and/or part 3 of Schedule 6, within 35 Business Days after the Last Fieldwork Day.
Appears in 1 contract
Samples: Noongar Standard Heritage Agreement