Transfers and Dispositions. Material furnished to the Joint Property and Material transferred from the Joint Property or disposed of by the Operator, unless otherwise agreed to by the Parties, shall be on the following basis exclusive of cash discounts. A. New Material (Condition A). (1) Tubular Goods Other than Line Pipe. (a) Tubular goods, sized 2-3/8 inches OD and larger, except line pipe, shall be priced at Eastern mill published carload base prices effective as of the date of movement plus transportation cost using the 80,000 pound carload weight basis to the railway receiving point nearest the Joint Property for which published rail rates for tubular goods exist. If the 80,000 pound rail rate is not offered, the 70,000 pound or 90,000 pound rail rate may be used. Freight charges for tubing will be calculated from Lorain, Ohio, and casing from Youngstown, Ohio. (b) For grades which are special to one mill only, prices shall be computed at the mill base of that mill plus transportation cost form that mill to the railway receiving point nearest the Joint Property as provided above in Paragraph 2.A.(1)(a). For transportation cost from points other than Eastern xxxxx, the 30,000 pound Oil Field Haulers Association interstate truck rate shall be used. (c) Macaroni tubing (size less than 2-3/8 inch OD) shall be priced at the lowest published out-of-stock prices f.o.
Appears in 2 contracts
Samples: Joint Operating Agreement, Operating Agreement (New Source Energy Corp)
Transfers and Dispositions. Material furnished to the Joint Property and Material transferred from the Joint Property or disposed of by the Operator, unless otherwise agreed to by the Parties, shall be priced on the following basis exclusive of cash smash discounts.
A. . A New Material (Condition A).
(1) Tubular Goods Other than Line Pipe.
(a) Tubular goods, sized 2-3/8 inches OD and larger, except line pipe, shall be priced at Eastern mill published carload base prices effective as of the date of or movement plus transportation cost using the 80,000 pound carload weight basis to the railway receiving point nearest the Joint Property for which published rail rates for tubular goods exist. exist If the 80,000 pound rail rate is not offered, the 70,000 pound or 90,000 pound rail rate may be used. used Freight charges for tubing will be calculated from Lorain, Ohio, Ohio and casing (from Youngstown, Ohio.
(b) For grades which are special to one mill only, prices shall be computed at the mill base of that mill plus transportation cost form from that mill to the railway receiving point nearest the Joint Property as provided above in Paragraph 2.A.(1)(a2 A (I)(a). For transportation cost from points other than titan Eastern xxxxx, the 30,000 pound Oil Field Haulers Association interstate truck rate shall be he used.
(c) Macaroni tubing (size less than 2-3/8 inch OD) Special end finish tubular goods shall be priced at the lowest published out-of-stock prices price, f.o.
Appears in 2 contracts
Samples: Sale Agreement, Sale of Properties (West Texas Resources, Inc.)
Transfers and Dispositions. Material furnished to the Joint Property and Material transferred from the Joint Property or disposed of by the Operator, unless otherwise agreed to by the Parties, shall be based on price paid per invoice on the following basis exclusive of cash discounts.
A. New Material (Condition A).
(1) Tubular Goods Other than Line Pipe.
(a) Tubular goods, sized 2-3/8 inches OD and larger, except line pipe, shall be priced at Eastern mill published carload base prices effective as of the date of movement plus transportation cost using the 80,000 pound carload weight basis to the railway receiving point nearest the Joint Property for which published rail rates for tubular goods exist. If the 80,000 pound rail rate is not offered, the 70,000 pound or 90,000 pound rail rate may be used. Freight charges for tubing will be calculated from Lorain, Ohio, and casing from Youngstown, Ohio.
(b) For grades which are special to one mill only, prices shall be computed at the mill base of that mill plus transportation cost form that mill to the railway receiving point nearest the Joint Property as provided above in Paragraph 2.A.(1)(a). For transportation cost from points other than Eastern xxxxx, the 30,000 pound Oil Field Haulers Association interstate truck rate shall be used.
(c) Macaroni tubing (size less than 2-3/8 inch OD) shall be priced at the lowest published out-of-stock prices f.o.
Appears in 2 contracts
Samples: Participation Agreement (New Source Energy Partners L.P.), Participation Agreement (New Source Energy Corp)
Transfers and Dispositions. Material furnished to the Joint Property and Material transferred from the Joint Property or disposed of by the Operator, unless otherwise agreed to by the Parties, shall be priced on the following basis exclusive of cash discounts.
A. New Material (Condition A).
(1) Tubular Goods Other than Line Pipe.
(a) Tubular goods, sized 2-3/8 2 1/8 inches OD and larger, except line pipe, shall be priced at Eastern mill published carload base prices effective as of the date of movement plus transportation cost using the 80,000 pound carload weight basis to the railway receiving point nearest the Joint Property for which published rail rates for tubular goods exist. If the 80,000 pound rail rate is not offered, the 70,000 pound or 90,000 pound rail rate may be used. Freight charges for tubing will be calculated from Lorain, Ohio, Ohio and casing from Youngstown, Ohio.
(b) For grades which are special to one mill only, prices shall be computed at the mill base of that mill plus transportation cost form from that mill to the railway receiving point nearest the Joint Property as provided above in Paragraph 2.A.(1)(a2.A.
(1) (a). For transportation cost from points other than Eastern xxxxxmilxx, the xhe 30,000 pound Oil Field Haulers Association interstate truck rate shall be used.
(c) Macaroni tubing (size less than 2-3/8 inch OD) Special end finish tubular goods shall be priced at the lowest published out-of-stock prices price, f.o.
Appears in 1 contract
Transfers and Dispositions. Material furnished to the Joint Property and Material transferred from the Joint Property or disposed of by the Operator, unless otherwise agreed to by the Parties, shall be priced on the following basis exclusive of cash discounts.:
A. New Material (Condition A).
(1) Tubular Goods Other than Line Pipe.
(a) Tubular goods, sized 2-3/8 % inches OD and larger, except line pipe, shall be priced at Eastern mill published carload base prices effective as of the date of movement plus transportation cost using the 80,000 pound carload weight basis to the railway receiving point nearest the Joint Property for which published rail rates for tubular goods exist. If the 80,000 pound rail rate is not offered, the 70,000 pound or 90,000 pound rail rate may be used. Freight charges for tubing will be calculated from Lorain, Ohio, Ohio and casing from Youngstown, Ohio.
(b) For grades which are special to one mill only, prices shall be computed at the mill base of that mill plus transportation cost form from that mill to the railway receiving point nearest the Joint Property as provided above in Paragraph 2.A.(1)(a). For transportation cost from points other than Eastern xxxxxmxxxx, the 30,000 30,000
A. A.P.L. FORM 610 β MODEL FORM OPERATING AGREEMENT- 1989 pound Oil Field Haulers Association interstate truck rate shall be used.
(c) Macaroni tubing (size less than 2-3/8 inch OD) Special end finish tubular goods shall be priced at the lowest published out-of-stock prices price, f.o.
Appears in 1 contract
Transfers and Dispositions. Material furnished to the Joint Property and Material transferred from the Joint Property or disposed of by the Operator, unless otherwise agreed to by the Parties, shall be priced on the following basis exclusive of cash discounts.
A. New Material (Condition A).
(1) Tubular Goods Other than Line Pipe.
(a) Tubular goods, sized 2-3/8 inches OD and larger, except line pipe, shall be priced at Eastern mill published carload base prices effective as of the date of movement plus transportation cost using the 80,000 pound carload weight basis to the railway receiving point nearest the Joint Property for which published rail rates for tubular goods exist. If the 80,000 pound rail rate is not offered, the 70,000 pound or 90,000 pound rail rate may be used. Freight charges for tubing will be calculated from Lorain, Ohio, and casing from Youngstown, Ohio.
(b) For grades which are special to one mill only, prices shall be computed at the mill base of that mill plus transportation cost form that mill to the railway receiving point nearest the Joint Property as provided above in Paragraph 2.A.(1)(a). For transportation cost from points other than Eastern xxxxx, the 30,000 pound Oil Field Haulers Association interstate truck rate shall be used.
(c) Macaroni tubing (size less than 2-3/8 inch OD) shall be priced at the lowest published out-of-stock prices f.o.
Appears in 1 contract
Transfers and Dispositions. Material furnished to the Joint Property and Material transferred from the Joint Property or disposed of by the Operator, unless otherwise agreed to by the Parties, shall be priced on the following basis exclusive of cash discounts.
A. New Material (Condition A).
(1) Tubular Goods Other than Line Pipe.
(a) Tubular goods, sized 2-3/8 2 1/8 inches OD and larger, except line pipe, shall be priced at Eastern mill published carload base prices effective as of the date of movement plus transportation cost using the 80,000 pound carload weight basis to the railway receiving point nearest the Joint Property for which published rail rates for tubular goods exist. If the 80,000 pound rail rate is not offered, the 70,000 pound or 90,000 pound rail rate may be used. Freight charges for tubing will be calculated from Lorain, Ohio, Ohio and casing from Youngstown, Ohio.
(b) For grades which are special to one mill only, prices shall be computed at the mill base of that mill plus transportation cost form from that mill to the railway receiving point nearest the Joint Property as provided above in Paragraph 2.A.(1)(a2.A.
(1) (a). For transportation cost from points other than Eastern xxxxxmxxxx, the 30,000 pound Oil Field Haulers Association interstate truck rate shall be used.
(c) Macaroni tubing (size less than 2-3/8 inch OD) Special end finish tubular goods shall be priced at the lowest published out-of-stock prices price, f.o.
Appears in 1 contract
Transfers and Dispositions. Material furnished to the Joint Property and Material transferred from the Joint Property or disposed of by the Operator, unless otherwise agreed to by the Parties, shall be priced on the following basis exclusive of cash discounts.:
A. New Material (Condition A).
(1) . Tubular Goods Other than Line Pipe.
(a) Tubular goods, sized 2-2 3/8 inches OD and larger, except line pipe, shall be priced at Eastern mill published carload base prices effective as of the date of movement plus transportation cost using the 80,000 pound carload weight basis to the railway receiving point nearest the Joint Property for which published rail rates for tubular goods exist. If the 80,000 pound rail rate is not offered, the 70,000 pound or 90,000 pound rail rate may be used. Freight charges for tubing will be calculated from Lorain, Ohio, Ohio and casing from Youngstown, Ohio.
(b) For grades which are special to one mill only, prices shall be computed at the mill base of that mill plus transportation cost form from that mill to the railway receiving point nearest the Joint Property as provided above in Paragraph 2.A.(1)(a2.A.
(1) (a). For transportation cost from points other than Eastern xxxxx, the 30,000 pound Oil Field Haulers Association interstate truck rate shall be used.
(c) Macaroni tubing (size less than 2-3/8 inch OD) Special end finish tubular goods shall be priced at the lowest published out-of-stock prices price, f.o.
Appears in 1 contract
Samples: Master Operating Agreement (Mainland Resources Inc.)
Transfers and Dispositions. Material furnished to the Joint Property and Material transferred from the Joint Property or disposed of by the Operator, unless otherwise agreed to by the Parties, shall be priced on the following basis exclusive of cash discounts.:
A. New Material (Condition A).
(1) Tubular Goods Other than Line Pipe.
(a) Tubular goods, sized 2-2 3/8 inches OD and larger, except line pipe, shall be priced at Eastern mill published carload base prices effective as of the date of movement plus transportation cost using the 80,000 pound carload weight basis to the railway receiving point nearest the Joint Property for which published rail rates for tubular goods exist. If the 80,000 pound rail rate is not offered, the 70,000 pound or 90,000 pound rail rate may be used. Freight charges for tubing will be calculated from Lorain, Ohio, and casing from Youngstown, Ohio.
(b) For grades which are special special' to one mill only, prices shall be computed at the mill base of that mill plus transportation cost form from that mill to the railway receiving point nearest the Joint Property as provided above in Paragraph 2.A.(1)(a2.A.(l)(a). For transportation cost from points other than Eastern xxxxxmills, the 30,000 pound Oil Field Haulers Hxxxxxs Association interstate truck rate shall be used.
(c) Macaroni tubing (size less than 2-3/8 inch OD) Special end finish tubular goods shall be priced at the lowest published out-of-stock prices price, f.o.
Appears in 1 contract
Samples: Offshore Operating Agreement (Ridgewood Energy P Fund LLC)
Transfers and Dispositions. Material furnished to the Joint Property and Material transferred from the Joint Property or disposed of by the Manager of Operations or Contract Operator, unless otherwise agreed to by the Parties, shall be priced on the following basis exclusive of cash discounts.:
A. 2.1 New Material (Condition A).
(1) Tubular Material(Condition A)Tubular Goods Other than Line Pipe.
(a) Tubular goods, sized 2-2 3/8 inches OD and larger, except line pipe, shall be priced at Eastern mill published carload base prices effective as of the date of movement plus transportation cost using the 80,000 pound carload weight basis to the railway receiving point nearest the Joint Property for which published rail rates for tubular goods exist. If the 80,000 pound rail rate is not offered, the 70,000 pound or 90,000 pound rail rate may be used. Freight charges for tubing will be calculated from Lorain, Ohio, Ohio and casing from Youngstown, Ohio.
(b) For grades which are special to one mill only, prices shall be computed at the mill base of that mill plus transportation cost form from that mill to the railway receiving point nearest the Joint Property as provided above in Paragraph 2.A.(1)(a2.A.(l)(a). For transportation cost from points other than Eastern xxxxxmills, the 30,000 pound Oil Field Haulers Association interstate inxxxxxate truck rate shall be used.
(c) Macaroni tubing (size less than 2-3/8 inch OD) Special end finish tubular goods shall be priced at the lowest published out-of-stock prices price, f.o.
Appears in 1 contract
Samples: Joint Development Agreement (Independence Energy Corp.)
Transfers and Dispositions. Material furnished to the Joint Property and Material transferred from the Joint Property or disposed of by the Operator, unless otherwise agreed to by the Parties, shall be priced on the following basis exclusive of cash discounts.:
A. New Material (Condition A).
(1) Tubular Goods Other than Line Pipe.
(a) Tubular goods, sized 2-3/8 % inches OD and larger, except line pipe, shall be priced at Eastern mill published carload base prices effective as of the date of movement plus transportation cost using the 80,000 pound carload weight basis to the railway receiving point nearest the Joint Property for which published rail rates for tubular goods exist. If the 80,000 pound rail rate is not offered, the 70,000 pound or 90,000 pound rail rate may be used. Freight charges for tubing will be calculated from Lorain, Ohio, Ohio and casing from Youngstown, Ohio.
(b) For grades which are special to one mill only, prices shall be computed at the mill base of that mill plus transportation cost form from that mill to the railway receiving point nearest the Joint Property as provided above in Paragraph 2.A.(1)(a). For transportation cost from points other than Eastern xxxxx, the 30,000 pound Oil Field Haulers Association interstate truck rate shall be used.
(c) Macaroni tubing (size less than 2-3/8 inch OD) shall be priced at the lowest published out-of-stock prices f.o.2.A.
Appears in 1 contract
Transfers and Dispositions. Material furnished to the Joint Property and Material transferred from the Joint Property or disposed of by the Operator, unless otherwise agreed to by the Parties, shall be priced on the following basis exclusive of cash discounts.:
A. New Material (Condition A).
(1) Tubular Goods Other than Line Pipe.
(a) Tubular goods, sized 2-3/8 % inches OD and larger, except line pipe, shall be priced at Eastern mill published carload base prices effective as of the date of movement plus transportation cost using the 80,000 pound carload weight basis to the railway receiving point nearest the Joint Property for which published rail rates for tubular goods exist. If the 80,000 pound rail rate is not offered, the 70,000 pound or 90,000 pound rail rate may be used. Freight charges for tubing will be calculated from Lorain, Ohio, Ohio and casing from Youngstown, Ohio.
(b) For grades which are special to one mill only, prices shall be computed at the mill base of that mill plus transportation cost form from that mill to the railway receiving point nearest the Joint Property as provided above in Paragraph 2.A.(1)(a). For transportation cost from points other than Eastern xxxxxmxxxx, the 30,000 pound Oil Field Haulers Association interstate truck rate shall be used.
(c) Macaroni tubing (size less than 2-3/8 inch OD) Special end finish tubular goods shall be priced at the lowest published out-of-stock prices price, f.o.
Appears in 1 contract
Transfers and Dispositions. Material furnished to the Joint Property and Material transferred from the Joint Property or disposed of by the Operator, unless otherwise agreed to by the Parties, shall be priced on the following basis exclusive of cash discounts.:
A. New Material (Condition A).
(1) Tubular Goods Other than Line Pipe.
(a) Tubular goods, sized 2-3/8 % inches OD and larger, except line pipe, shall be priced at Eastern mill published carload base prices effective as of the date of movement plus transportation cost using the 80,000 pound carload weight basis to the railway receiving point nearest the Joint Property for which published rail rates for tubular goods exist. If the 80,000 pound rail rate is not offered, the 70,000 pound or 90,000 pound rail rate may be used. Freight charges for tubing will be calculated from Lorain, Ohio, Ohio and casing from Youngstown, Ohio.
(b) For grades which are special to one mill only, prices shall be computed at the mill base of that mill plus transportation cost form from that mill to the railway receiving point nearest the Joint Property as provided above in Paragraph 2.A.(1)(a2.A.
(1) (a). For transportation cost from points other than Eastern xxxxx, the 30,000 pound Oil Field Haulers Association interstate truck rate shall be used.
(c) Macaroni tubing (size less than 2-3/8 inch OD) Special end finish tubular goods shall be priced at the lowest published out-of-stock prices price, f.o.
Appears in 1 contract
Transfers and Dispositions. Material furnished to the Joint Property and Material transferred from the Joint Property or disposed of by the Operator, unless otherwise agreed to by the Parties, shall be priced on the following basis exclusive of cash discounts.:
A. New Material (Condition A).
(1) Tubular Goods Other than Line Pipe.
(a) Tubular goods, sized 2-2 3/8 inches OD and larger, except line pipe, shall be priced at Eastern mill published carload base prices effective as of the date of movement plus transportation cost using the 80,000 pound carload weight basis to the railway receiving point nearest the Joint Property for which published rail rates for tubular goods exist. If the 80,000 pound rail rate is not offered, the 70,000 pound or 90,000 pound rail rate may be used. Freight charges for tubing will be calculated from Lorain, Ohio, Ohio and casing from Youngstown, Ohio.
(b) For grades which are special to one mill only, prices shall be computed at the mill base of that mill plus transportation cost form from that mill to the railway receiving point nearest the Joint Property as provided above in Paragraph 2.A.(1)(a). For transportation cost from points other than Eastern xxxxx, the 30,000 pound Oil Field Haulers Association interstate truck rate shall be used.
(c) Macaroni tubing (size less than 2-3/8 inch OD) Special end finish tubular goods shall be priced at the lowest published out-of-stock prices price, f.o.