Unit Mechanical Completion. “Unit Mechanical Completion” shall be achieved when the conditions as stated in Section 11.4(a) for the commencement of Nuclear Fuel loading the Unit have been achieved. When submitting its written notice of determination for such Unit Mechanical Completion, Contractor shall include notice that Turnover has occurred.
Appears in 4 contracts
Samples: Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement (Scana Corp)
Unit Mechanical Completion. “Unit Mechanical Completion” shall be achieved when the conditions as stated in Section 11.4(a) for the commencement of Nuclear Fuel loading the Unit have been achieved. When submitting its written notice of determination for such Unit Mechanical Completion, Contractor shall include notice that Turnover has occurred.