Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement. Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB. Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB. Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project. Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 31 December 2014 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 31 March 2014 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause make the applicable portion of the proceeds of the Loan available to be applied each Project Executing Agency upon terms and conditions mutually agreeable to ADB and the Borrower, and shall cause each Project Executing Agency to apply such proceeds to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 2020 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, procure or cause to be procured, the procured items of expenditure to be financed out of the proceeds of the Loan in accordance with the applicable provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for withdrawals from the Loan Account for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 2015 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause (i) make the proceeds of the Loan available to be applied MORD and the States upon terms and conditions mutually acceptable to ADB and the Borrower, and (ii) cause MORD and the States to apply such proceeds to the financing of expenditures on the Project in accordance with the provisions of this Loan AgreementAgreement and the Project Agreements.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 31 December 2015 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. (a) The Borrower shall relend a part of the proceeds of the Loan to each Pourashava under a Subsidiary Loan Agreement upon terms and conditions satisfactory to ADB.
(b) The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement and the Project Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 8.02 of the Loan Regulations shall be 30 June 2023 31 December 2020 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 2020 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. (a) The Borrower shall cause relend the proceeds of the Loan to be applied NPT under a Subsidiary Loan Agreement upon terms and conditions satisfactory to ADB.
(b) The Borrower shall cause NPT to apply the proceeds of the Loan to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement and the Project Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 31 December 2015 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause make the proceeds of the Loan available to be applied RDA upon terms and conditions satisfactory to ADB and the Borrower and shall cause RDA to apply such proceeds to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement, the Special Operations Loan Agreement and the Project Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 September 2019 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause make available the proceeds of the Loan to be applied each of Azersu and SAWMC (in an amount equivalent to $122,160,000 to Azersu and in an amount equivalent to $27,840,000 to SAWMC) upon terms and conditions satisfactory to ADB and shall cause Azersu and SAWMC to apply such proceeds to the financing of such expenditures on the Project in accordance with the provisions of this Loan AgreementAgreement and the Project Agreements, as applicable.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 31 May 2018 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower through Ministry of Railways shall cause make the proceeds of the Loan available to be applied RVNL under the RVNL MOU for carrying out the Project, and shall cause RVNL to apply such proceeds to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement and the Project Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 2019 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. (a) The Borrower shall cause make the proceeds of the Loan available to be applied each Project Executing Agency upon terms and conditions satisfactory to ADB.
(b) The Borrower shall cause each Project Executing Agency to apply the proceeds of the Loan to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement and the relevant Project Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 September 2014 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations A Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 8.02 of the Loan Regulations General Conditions shall be 30 June 2023 31 December 2020 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 31 May 2020 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 31 August 2020 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 31 October 2017 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. (a) The Borrower shall relend a part of the proceeds of the Loan to each Pourshava under a Subsidiary Loan Agreement upon terms and conditions satisfactory to ADB.
(b) The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement and the Project Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this the ADF Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations ADF Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 8.02 of the Loan Regulations shall be 30 June 2023 31 December 2020 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 31 January 2016 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, procure or cause to be procured, the procured items of expenditure to be financed out of the proceeds of the Loan in accordance with the applicable provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for withdrawals from the Loan Account for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 April 2014 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. (a) The Borrower shall provide the proceeds of the Loan to CEB upon terms and conditions satisfactory to ADB and the Borrower.
(b) The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement and the Project Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 31 March 2020 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. (a) The Borrower shall relend the proceeds of the Loan in Rupees to NTDC under a Subsidiary Loan Agreement upon terms and conditions satisfactory to ADB.
(b) The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement and the Project Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 31 December 2016 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause make the proceeds of the Loan available to be applied NWSDB, under a subsidiary loan agreement, upon terms and conditions satisfactory to ADB and shall cause NWSDB to apply such proceeds to the financing of expenditures on parts A, B and C of the Project in accordance with the provisions of this Loan Agreement and the NWSDB Project Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, procure or cause to be procured, the procured items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations Loan Agreement, as applicable. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for withdrawals from the Loan Account for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 14 August 2017 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 2017 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Ordinary Operations Loan Regulations shall be 30 June 2023 2017 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 3 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 2020 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause (i) make the proceeds of the Loan available to be applied MORD and the States upon terms and conditions mutually agreeable to ADB and the Borrower, and (ii) cause MORD and the States to apply such proceeds to the financing of expenditures on the Project in accordance with the provisions of this Loan AgreementAgreement and the Project Agreements.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 2018 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 2017 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 31 December 2017 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 9 October 2016 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, procure or cause to be procured, the procured items of expenditure to be financed out of the proceeds of the Loan in accordance with the applicable provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for withdrawals from the Loan Account for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 November 2014 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. (a) The Borrower shall make the proceeds of the Loan available to each Project Executing Agency upon terms and conditions satisfactory to ADB.
(b) The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan AgreementAgreement and the Project Agreement (as appropriate).
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 December 2018 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. (a) The Borrower shall relend the proceeds of the Loan to the Bank of Mongolia under a Subsidiary Loan Agreement upon terms and conditions satisfactory to ADB.
(b) The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement and the Project Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 2017 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause (i) make the proceeds of the Loan available to be applied MORD and the States upon terms and conditions mutually acceptable to ADB and the Borrower, and (ii) cause MORD and the States to apply such proceeds to the financing of expenditures on the Project in accordance with the provisions of this Loan AgreementAgreement and the Project Agreements.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 31 December 2017 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. (a) The Borrower shall make the proceeds of the Loan available to FRA under the Financing Arrangement upon terms and conditions satisfactory to ADB.
(b) The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement and the Project Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 31 December 2020 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, procure or cause to be procured, the procured items of expenditure to be financed out of the proceeds of the Loan in accordance with the applicable provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for withdrawals from the Loan Account for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 31 March 2013 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause make the proceeds of the Loan available to be applied NWSDB, under a Subsidiary Loan Agreement upon terms and conditions satisfactory to ADB and the Borrower, and shall cause NWSDB to apply such proceeds to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement and the Project Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 2017 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory acceptable to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 2017 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. (a) The Borrower shall relend the proceeds of the Loan to PGCB under a Subsidiary Loan Agreement upon terms and conditions satisfactory to ADB.
(b) The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement and the Project Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 31 December 2018 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement
Use of Proceeds of the Loan. Section 3.01. The Borrower shall cause the proceeds of the Loan to be applied to the financing of expenditures on the Project in accordance with the provisions of this Loan Agreement.
Section 3.02. The proceeds of the Loan shall be allocated and withdrawn in accordance with the provisions of Schedule 2 3 to this Loan Agreement, as such Schedule may be amended from time to time by agreement between the Borrower and ADB.
Section 3.03. Except as ADB may otherwise agree, the Borrower shall procure, or cause to be procured, the items of expenditure to be financed out of the proceeds of the Loan in accordance with the provisions of Schedule 4 to the Special Operations this Loan Agreement. ADB may refuse to finance a contract where any such item has not been procured under procedures substantially in accordance with those agreed between the Borrower and ADB or where the terms and conditions of the contract are not satisfactory to ADB.
Section 3.04. Except as ADB may otherwise agree, the Borrower shall cause all items of expenditure financed out of the proceeds of the Loan to be used exclusively in the carrying out of the Project.
Section 3.05. The Loan Closing Date for the purposes of Section 9.02 of the Loan Regulations shall be 30 June 2023 31 August 2016 or such other date as may from time to time be agreed between the Borrower and ADB.
Appears in 1 contract
Samples: Loan Agreement