VARIATION ORDERS. 18.1 In cases where the estimated value of the envisaged changes in purchase does not vary more than 15% of the total value of the original contract, the contractor may be instructed to deliver the goods or render the services as such. In cases of measurable quantities, the contractor may be approached to reduce the unit price, and such offers may be accepted provided that there is no escalation in price.
Appears in 22 contracts
Samples: Tender Document, www.thekwini.edu.za, Health and Safety
VARIATION ORDERS. 18.1 In cases where the estimated value of the envisaged changes in purchase does not vary more than 15% of the total value of the original contract, the contractor may be instructed to deliver the goods or render the services as such. For construction related goods, services and/or infrastructure project, contracts may be expanded or varied by not more than 20%. In cases of measurable quantities, the contractor may be approached to reduce the unit price, and such offers may be accepted provided that there is no escalation in price.
Appears in 4 contracts
Samples: www.capewinelands.gov.za, www.capewinelands.gov.za, www.capewinelands.gov.za
VARIATION ORDERS. 18.1 In cases where the estimated value of the envisaged changes in purchase does not vary more than 15% of the total value of the original contract, the contractor may be instructed to deliver the goods or render the services as such. In cases of measurable quantities, the contractor may be approached to reduce the unit price, and such offers may be accepted provided that there is no escalation in price.
Appears in 3 contracts
Samples: tenderbulletins.co.za, tenderbulletins.co.za, tenderbulletins.co.za
VARIATION ORDERS. 18.1 (a) In cases where the estimated value of the envisaged changes in purchase does not vary more than 15% of the total value of the original contract, the contractor may be instructed to deliver the goods or render the services as such. In cases of measurable quantities, the contractor may be approached to reduce the unit price, and such offers may be accepted provided that there is no escalation in price.
Appears in 1 contract
Samples: Safety and Emergency Services
VARIATION ORDERS. 18.1 18.1. In cases where the estimated value of the envisaged changes in purchase does not vary more than 15% of the total value of the original contract, the contractor may be instructed to deliver the goods or render the services as such. In cases of measurable quantities, the contractor may be approached to reduce the unit price, and such offers may be accepted provided that there is no escalation in price.
Appears in 1 contract
Samples: etenders.treasury.gov.za
VARIATION ORDERS. 18.1 In cases where the estimated value of the envisaged changes in purchase does not vary more than 15tha15% of the total value of the original contract, the contractor may be instructed to deliver the goods or render the services as such. In cases of measurable quantities, the contractor may be approached to reduce the unit price, price and such offers offers, may be accepted provided that there is no escalation in price.
Appears in 1 contract
Samples: ngqushwamun.gov.za