Variations to the Works. 19.1.1. The Principal‟s Representative may direct the Contractor to carry out a Variation to the Works, which may consist of additions, deletions or alterations to the Works or any portion thereof. 19.1.2. Any adjustment of the Contract Price or Construction Period arising out of any Variations to the Works or alterations to the construction schedule shall be valid only if authorised in a written Variation Order signed by the Principal‟s Representative and countersigned by the Principal. 19.1.3. If a Variation Order is given in accordance with clause 19.1.2, it shall be deemed to be incorporated into this Contract. 19.1.4. The Contractor may add 10% of the price of Variations which constitute additions or alterations on account of management fee, overhead and profit. 19.1.5. Any Variations to the Works for which instructions have been issued by the Principal‟s Representative must be measured in accordance with the Standard 19.1.6. The Works include any Variations directed by the Principal‟s Representative whether or not such Variations affect the Contract Price or Construction Period.
Appears in 2 contracts
Samples: Minor Works Building Works Contract, Minor Works Building Works Contract
Variations to the Works. 19.1.1. The Principal‟s Principal’s Representative may direct the Contractor to carry out a Variation to the Works, which may consist of additions, deletions or alterations to the Works or any portion thereof.
19.1.2. Any adjustment of the Contract Price or Construction Period arising out of any Variations to the Works or alterations to the construction schedule shall be valid only if authorised in a written Variation Order signed by the Principal‟s Principal’s Representative and countersigned by the Principal.
19.1.3. If a Variation Order is given in accordance with clause 19.1.2, it shall be deemed to be incorporated into this Contract.
19.1.4. The Contractor may add 10% of the price of Variations which constitute additions or alterations on account of management fee, overhead and profit.
19.1.5. Any Variations to the Works for which instructions have been issued by the Principal‟s Principal’s Representative must be measured in accordance with the Standard
19.1.6. The Works include any Variations directed by the Principal‟s Principal’s Representative whether or not such Variations affect the Contract Price or Construction Period.
Appears in 1 contract
Samples: Minor Works Building Works Contract
Variations to the Works.
19.1.1. The Principal‟s Principal’s Representative may direct the Contractor to carry out a Variation to the Works, which may consist of additions, deletions or alterations to the Works or any portion thereof.thereof.
19.1.2. Any adjustment of the Contract Price or Construction Period arising out of any Variations to the Works or alterations to the construction schedule shall be valid only if authorised in a written Variation Order signed by the Principal‟s Principal’s Representative and countersigned by the Principal.Principal.
19.1.3. If a Variation Order is given in accordance with clause 19.1.2, it shall be deemed to be incorporated into this Contract.
19.1.4. The Contractor may add 10% of the price of Variations which constitute additions or alterations on account of management fee, overhead and profit.
19.1.5. Any Variations to the Works for which instructions have been issued by the Principal‟s Principal’s Representative must be measured in accordance with the Standard
19.1.6. The Works include any Variations directed by the Principal‟s Principal’s Representative whether or not such Variations affect the Contract Price or Construction Period.