Wetlands, Streams and Riparian Areas. a) Construction of the Project shall be performed in accordance with Mitigating Conditions 1-5 of the Revised Mitigated Determination of Non- Significance issued on April 17, 2018 by EFSEC. b) Prior to construction of the Project, the Certificate Holder shall provide plans to EFSEC for coordination with Ecology to conduct additional wetlands surveys and to identify hydrologic features at each site. The Certificate Holder shall consult with Ecology and comply with any mitigation requirements determined by Ecology to be necessary during that consultation. If any mitigation is required for wetlands or other habitat impacts, the Certificate Holder shall consult with Ecology on appropriate buffer zones and mitigation measures and submit them to EFSEC for approval. c) Construction of the Project shall not result in any temporary or permanent disturbances of streams or other surface waters. If unanticipated disturbances of streams or other surface waters occur, the Certificate Holder shall prepare a Waters Restoration Plan in consultation with the Corps and Ecology and submit it to EFSEC for approval. Prior to any construction work affecting the bed or flow in waters of the state (including seasonally dry channels), the Certificate Holder shall consult with and obtain approval from the Corps and Ecology, and provide documentation of such approval to EFSEC. At least sixty (60) days prior to beginning any such channel work, the Certificate Holder shall submit construction drawings to EFSEC for review and approval. The drawings shall specify the exact locations of work to be conducted, buffers that are required, and best management practices and mitigation measures that will be implemented as required by this article. The Certificate Holder shall not begin channel work prior to obtaining approval of the construction drawings from the Council.
Appears in 3 contracts
Samples: Site Certification Agreement, Site Certification Agreement, Site Certification Agreement
Wetlands, Streams and Riparian Areas. a) Construction of the Project shall be performed in accordance with Mitigating Conditions 1-5 of the Revised Mitigated Determination of Non- Significance issued on April 17, 2018 by EFSEC.
b) Prior to construction of the Project, the Certificate Holder shall provide plans to EFSEC for coordination with Ecology to conduct additional wetlands surveys and to identify hydrologic features at each site. The Certificate Holder shall consult with Ecology and comply with any mitigation requirements determined by Ecology to be necessary during that consultation. If any mitigation is required for wetlands or other habitat impacts, the Certificate Holder shall consult with Ecology on appropriate buffer zones and mitigation measures and submit them to EFSEC for approval.
c) Construction of the Project shall not result in any temporary or permanent disturbances of streams or other surface waters. If unanticipated disturbances of streams or other surface waters occur, the Certificate Holder shall prepare a Waters Restoration Plan in consultation with the Corps and Ecology and submit it to EFSEC for approval. Prior to any construction work affecting the bed or flow in waters of the state (including seasonally dry channels), the Certificate Holder shall consult with and obtain approval from the Corps and Ecology, and provide documentation of such approval to EFSEC. At least sixty (60) days prior to beginning any such channel work, the Certificate Holder shall submit construction drawings to EFSEC for review and approval. The drawings shall specify the exact locations of work to be conducted, buffers that are required, and best management practices and mitigation measures that will be implemented as required by this article. The Certificate Holder shall not begin channel work prior to obtaining approval of the construction drawings from the Council.obtaining
Appears in 1 contract
Samples: Site Certification Agreement