Where Delay is to Non-Controlling Work Item. If the Delay is to a non-Controlling Work Item, then no indirect costs and expenses, and no profit, of Developer or any Contractor are allowable as Delay Costs.
Appears in 5 contracts
Samples: Direct Agreement, Direct Agreement, Direct Agreement