Withholding of Retainage; Conversion to Lump Sum. Retainage shall be withheld from each Application for Payment to the Design-Builder in the amount of ten percent of the sum of the total cost for original Contract Work, Change Order Work, materials stored on the Site and Design-Builder Fee earned. After one-half of the Contract Sum, including Change Orders, becomes due and the Work meets all of the following conditions:
Appears in 12 contracts
Samples: Design Build Contract, Design Build Contract, Design Build Contract