SCHEDULE D-1 CHANGE ORDER FORM (for use when the parties mutually agree upon and execute the Change Order Pursuant to Section 6.1B or 6.2C)
Exhibit 10.3
SCHEDULE D-1
CHANGE ORDER FORM
(for use when the parties mutually agree upon and execute the Change Order Pursuant to Section 6.1B or 6.2C)
PROJECT NAME: Creole Trail Pipeline - Segment 2 Project, Alternate Route Single Line Option |
CHANGE ORDER NUMBER: CO 2-002 | |
DATE OF CHANGE ORDER: 03/29/07 | ||
OWNER: Cheniere Creole Trail Pipeline, L.P. | ||
CONTRACTOR: Sunland Construction, Inc. |
DATE OF AGREEMENT: January 5, 2007
The Agreement between the Parties listed above is changed as follows: (attach additional documentation if necessary)
Provide equipment and labor necessary to remove 18 foreign flowlines from the Gulfport Energy East Hackberry Field per the attached Sunland March 13, 2007 T & M estimate of $32,821 per day.
Adjustment to Estimated Contract Price
The original Estimated Contract Price was |
$ | 70,078,195 | |
Net change by previously authorized Change Order (#CO2-001) |
$ | 1,676,000 | |
The Estimated Contract Price prior to this Change Order was |
$ | 71,754,195 | |
The Estimated Contract Price will be increased by this Change Order in the amount of |
$ | 850,000 | |
The new Estimated Contract Price including this Change Order will be |
$ | 72,604,195 | |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified):
The Required Mechanical Completion Date will be unchanged by ( ) Days
The Required Mechanical Completion Date as of the date of this Change Order therefore is March 15, 2008
(attach additional documentation if necessary) No Attachment
The Required Substantial Completion Date will be unchanged by ( ) Days
The Required Substantial Completion Date as of the date of this Change Order therefore is
(attach additional documentation if necessary) No Attachment
The Required Final Completion Date will be unchanged by ( ) Days
The Required Final Completion Date as of the date of this Change Order therefore is
(attach additional documentation if necessary) No Attachment
Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary) N/A
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previous issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
Cheniere Creole Trail Pipeline, L.P. |
Sunland Construction, Inc. | |||
Owner | Contractor | |||
/s/ X. Xxxxx Xxxxxx |
/s/ Xxxxx Xxxxxxxx | |||
Name | Name | |||
President |
Project Manager | |||
Title | Title | |||
Sept. 25, 2007 |
April 4, 2007 | |||
Date of Signing | Date of Signing |
SCHEDULE D-1
CHANGE ORDER FORM
(for use when the parties mutually agree upon and execute the Change Order Pursuant to Section 6.1B or 6.2C)
PROJECT NAME: Creole Trail Pipeline - Segment 2 Project, Alternate Route Single Line Option |
CHANGE ORDER NUMBER: CO 2-003 | |
DATE OF CHANGE ORDER: 08/07/07 | ||
OWNER: Cheniere Creole Trail Pipeline, L.P. | ||
CONTRACTOR: Sunland Construction, Inc. |
DATE OF AGREEMENT: January 5, 2007
The Agreement between the Parties listed above is changed as follows: (attach additional documentation if necessary)
Provide equipment and labor necessary to perform a horizontal directional drill along the 42” Creole Trail Segment 2 pipeline centerline beneath the two Xxxxxx Xxxxxx pipelines in Lake Calcasieu. Price is outlined in the attached 8/1/07
e-mail message.
Adjustment to Estimated Contract Price
The original Estimated Contract Price was |
$ | 70,078,195 | |
Net change by previously authorized Change Orders (#CO2-001 and CO2-002) |
$ | 2,526,000 | |
The Estimated Contract Price prior to this Change Order was |
$ | 72,604,195 | |
The Estimated Contract Price will be increased by this Change Order in the amount of |
$ | 3,095,100 | |
The new Estimated Contract Price including this Change Order will be |
$ | 75,699,295 | |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified):
The Required Mechanical Completion Date will be unchanged by ( ) Days
The Required Mechanical Completion Date as of the date of this Change Order therefore is , 2008
(attach additional documentation if necessary) No Attachment
The Required Substantial Completion Date will be unchanged by ( ) Days
The Required Substantial Completion Date as of the date of this Change Order therefore is
(attach additional documentation if necessary) No Attachment
The Required Final Completion Date will be unchanged by ( ) Days
The Required Final Completion Date as of the date of this Change Order therefore is
(attach additional documentation if necessary) No Attachment
Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary)
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previous issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
Cheniere Creole Trail Pipeline, L.P. |
Sunland Construction, Inc. | |||
Owner | Contractor | |||
/s/ X. Xxxxx Xxxxxx |
/s/ Xxxxx Xxxxxxxx | |||
Name | Name | |||
President |
Project Manager | |||
Title | Title | |||
Sept. 25, 2007 |
September 14, 2007 | |||
Date of Signing | Date of Signing |
SCHEDULE D-1
CHANGE ORDER FORM
(for use when the parties mutually agree upon and execute the Change Order Pursuant to Section 6.1B or 6.2C)
PROJECT NAME: Creole Trail Pipeline - Segment 2 Project, Alternate Route Single Line Option |
CHANGE ORDER NUMBER: CO 2-007 | |
DATE OF CHANGE ORDER: 08/27/07 | ||
OWNER: Cheniere Creole Trail Pipeline, L.P. | ||
CONTRACTOR: Sunland Construction, Inc. |
DATE OF AGREEMENT: January 5, 2007
The Agreement between the Parties listed above is changed as follows: (attach additional documentation if necessary)
Additional cost for providing inspection of long seam grinding at Bayou Pipe Coating on a T & M basis per item 13 in the attached 8/23/07 cost summary and spreadsheet.
Adjustment to Estimated Contract Price
The original Estimated Contract Price was |
$ | 70,078,195 | |
Net change by previously authorized Change Order (#CO 2-001, 002, 003, 004, 005, and 006) |
$ | 7,144,959 | |
The Estimated Contract Price prior to this Change Order was |
$ | 77,223,154 | |
The Estimated Contract Price will be increased by this Change Order in the amount of |
$ | 77,044.50 | |
The new Estimated Contract Price including this Change Order will be |
$ | 77,300,198.50 | |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified):
The Required Mechanical Completion Date will be unchanged by ( ) Days
The Required Mechanical Completion Date as of the date of this Change Order therefore is , 2008
(attach additional documentation if necessary) No Attachment
The Required Substantial Completion Date will be unchanged by ( ) Days
The Required Substantial Completion Date as of the date of this Change Order therefore is
(attach additional documentation if necessary) No Attachment
The Required Final Completion Date will be unchanged by ( ) Days
The Required Final Completion Date as of the date of this Change Order therefore is
(attach additional documentation if necessary) No Attachment
Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary)
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previous issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
Cheniere Creole Trail Pipeline, L.P. |
Sunland Construction, Inc. | |||
Owner | Contractor | |||
/s/ X. Xxxxx Xxxxxx |
/s/ Xxxxx Xxxxxxxx | |||
Name | Name | |||
President |
Project Manager | |||
Title | Title | |||
Sept. 25, 2007 |
September 14, 2007 | |||
Date of Signing | Date of Signing |