SCHEDULE D-1 CHANGE ORDER FORM (for use when the Parties mutually agree upon and execute the Change Order pursuant to Section 6.1B or 6.2C)
Exhibit 10.1
SCHEDULE D-1
CHANGE ORDER FORM
(for use when the Parties mutually agree upon and execute the Change Order pursuant to Section 6.1B or 6.2C)
PROJECT NAME: Alternate Route 42” Single Line Option Creole Trail Pipeline - Segment 3A Project
OWNER: Cheniere Creole Trail Pipeline, L.P.
CONTRACTOR: Xxxxxxx Pipe Line Construction Company (SPLCC)
DATE OF AGREEMENT: January 10, 2007
SUBJECT: Various Additional M-Items |
CHANGE ORDER NUMBER: CCT 3A-027
DATE OF CHANGE ORDER: 01-24-08 |
The Agreement between the Parties listed above is changed as follows: Per the terms and conditions outlined under Article 6.2-B of the Construction Agreement for Segment 3A project between Cheniere Creole Trail Pipeline, L.P. and Xxxxxxx Pipe Line Construction Company dated January 10, 2007; Cheniere will compensate Xxxxxxx Pipe Line Co. for various M-Items including: Item M-10 (3) additional 42” cut and bevels, Item M-26 577 feet of safety fence, Item M-31 additional Depth Ditch (3,536’ of 1’ extra depth, and 3,900’ of 2’ extra depth), and Item M-33 20 cubic yards of flowable fill.
Adjustment to Estimated Contract Price
The original Estimated Contract Price was |
$ | 65,605,739.22 | |
Net change by previously authorized Change Orders |
$ | 15,225,547.21 | |
The Estimated Contract Price prior to this Change Order was |
$ | 80,831,286.43 | |
The Estimated Contract Price will be increased by this Change Order in the amount of |
$ | 31,479.00 | |
The new Estimated Contract Price including this Change Order will be |
$ | 80,862,765.43 | |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A
The Guaranteed Mechanical Completion Date will be unchanged.
The Guaranteed Mechanical Completion Date as of the date of this Change Order therefore is January 31, 2008.
The Guaranteed Substantial Completion Date will be unchanged.
The Guaranteed Substantial Completion Date as of the date of this Change Order therefore is February 29, 2008.
The Guaranteed Final Completion Date will be unchanged.
The Guaranteed Final Completion Date as of the date of this Change Order therefore is March 31, 2008.
Adjustment to other Changed Criteria: N/A
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
Cheniere Creole Trail Pipeline, X.X. |
Xxxxxxx Pipe Line Construction Company | |
Owner |
Contractor | |
/s/ X. Xxxxx Xxxxxx |
/s/ Xxxxxx X. Xxxxx, Xx. | |
Signature |
Signature | |
X. Xxxxx Xxxxxx |
Xxxxxx X. Xxxxx, Xx. | |
Name |
Name | |
President |
President & COO | |
Title |
Title | |
1/29/2008 |
2/6/08 | |
Date of Signing |
Date of Signing |
SCHEDULE D-1
CHANGE ORDER FORM
(for use when the Parties mutually agree upon and execute the Change Order pursuant to Section 6.1B or 6.2C)
PROJECT NAME: Alternate Route 42” Single Line Option Creole Trail Pipeline - Segment 3A Project
OWNER: Cheniere Creole Trail Pipeline, L.P.
CONTRACTOR: Xxxxxxx Pipe Line Construction Company (SPLCC)
DATE OF AGREEMENT: January 10, 2007
SUBJECT: Various Additional M-Items |
CHANGE ORDER NUMBER: CCT 3A-028
DATE OF CHANGE ORDER: 01-29-08 |
The Agreement between the Parties listed above is changed as follows: Per the terms and conditions outlined under Article 6.2-B of the Construction Agreement for Segment 3A project between Cheniere Creole Trail Pipeline, L.P. and Xxxxxxx Pipe Line Construction Company dated January 10, 2007; Cheniere will compensate Xxxxxxx Pipe Line Co. for various M-Items including: Item M-26 694 feet of safety fence, Item M-31 additional Depth Ditch (11,632’ of 1’ extra depth). The total amount of this change order is $28,122.00.
Adjustment to Estimated Contract Price |
|||
The original Estimated Contract Price was |
$ | 65,605,739.22 | |
Net change by previously authorized Change Orders |
$ | 15,257,026.21 | |
The Estimated Contract Price prior to this Change Order was |
$ | 80,862,765.43 | |
The Estimated Contract Price will be increased by this Change Order in the amount of |
$ | 28,122.00 | |
The new Estimated Contract Price including this Change Order will be |
$ | 80,890,887.43 | |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A
The Guaranteed Mechanical Completion Date will be unchanged.
The Guaranteed Mechanical Completion Date as of the date of this Change Order therefore is January 31, 2008.
The Guaranteed Substantial Completion Date will be unchanged.
The Guaranteed Substantial Completion Date as of the date of this Change Order therefore is February 29, 2008.
The Guaranteed Final Completion Date will be unchanged.
The Guaranteed Final Completion Date as of the date of this Change Order therefore is March 31, 2008.
Adjustment to other Changed Criteria: N/A
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
Cheniere Creole Trail Pipeline, X.X. |
Xxxxxxx Pipe Line Construction Company | |
Owner |
Contractor | |
/s/ X.X. Xxxxxx / X. Xxxxx Xxxxxx |
/s/ Xxxxxx X. Xxxxx, Xx. | |
Signature |
Signature | |
X.X. Xxxxxx / X. Xxxxx Xxxxxx |
Xxxxxx X. Xxxxx, Xx. | |
Name |
Name | |
Director / President |
President & COO | |
Title |
Title | |
2/1/08 |
2/6/08 | |
Date of Signing |
Date of Signing |
SCHEDULE D-1
CHANGE ORDER FORM
(for use when the Parties mutually agree upon and execute the Change Order pursuant to Section 6.1B or 6.2C)
PROJECT NAME: Alternate Route 42” Single Line Option Creole Trail Pipeline - Segment 3A Project
OWNER: Cheniere Creole Trail Pipeline, L.P.
CONTRACTOR: Xxxxxxx Pipe Line Construction Company (SPLCC)
DATE OF AGREEMENT: January 10, 2007
SUBJECT: Additional Road Bore Footages |
CHANGE ORDER NUMBER: CCT 3A-029
DATE OF CHANGE ORDER: 01-30-08 |
The Agreement between the Parties listed above is changed as follows: Per the terms and conditions outlined under Article 6.2-B of the Construction Agreement for Segment 3A project between Cheniere Creole Trail Pipeline, L.P. and Xxxxxxx Pipe Line Construction Company dated January 10, 2007; Cheniere will compensate Xxxxxxx Pipe Line Co. for additional Bore footage installed at B-00.0 Xxxxxx Xxxxxxxx Xxxx M.P. 3-0.5 (additional 29’ for $20,300.00), B-10.2 State Highway 27 M.P. 3-0.0 (additional 43’ for $30,100.00), B-10.14 State Highway 27 M.P. 3-18.7 (additional 13.3’ for $9,310.00), B-10.15 Xxxxxxxx Park Road M.P 3-22.7 (additional 23’ for $16,100.00), B-10.16 Xxxx Xxxxxxx M.P. 3-23.3 (additional 41’ for $28,700.00), B-10.17 State Highway 171 M.P. 10.17 (additional 18’ for $12,600.00), B-11.2 Bored Rail Road Crossing M.P. 3-18.8 (additional 105’ for $73,500.00). These additional bore footages where necessary due to various foreign utility crossings. The total amount for this change order is $193,610.00.
Adjustment to Estimated Contract Price |
|||
The original Estimated Contract Price was |
$ | 65,605,739.22 | |
Net change by previously authorized Change Orders |
$ | 15,285,148.21 | |
The Estimated Contract Price prior to this Change Order was |
$ | 80,890,887.43 | |
The Estimated Contract Price will be increased by this Change Order in the amount of |
$ | 190,610.00 | |
The new Estimated Contract Price including this Change Order will be |
$ | 81,081,497.43 | |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A
The Guaranteed Mechanical Completion Date will be unchanged.
The Guaranteed Mechanical Completion Date as of the date of this Change Order therefore is January 31, 2008.
The Guaranteed Substantial Completion Date will be unchanged.
The Guaranteed Substantial Completion Date as of the date of this Change Order therefore is February 29, 2008.
The Guaranteed Final Completion Date will be unchanged.
The Guaranteed Final Completion Date as of the date of this Change Order therefore is March 31, 2008.
Adjustment to other Changed Criteria: N/A
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
Cheniere Creole Trail Pipeline, X.X. |
Xxxxxxx Pipe Line Construction Company | |
Owner |
Contractor | |
/s/ X. Xxxxx Xxxxxx |
/s/ Xxxxxx X. Xxxxx, Xx. | |
Signature |
Signature | |
X. Xxxxx Xxxxxx |
Xxxxxx X. Xxxxx, Xx. | |
Name |
Name | |
President |
President & COO | |
Title |
Title | |
2/4/08 |
2/6/08 | |
Date of Signing |
Date of Signing |
SCHEDULE D-1
CHANGE ORDER FORM
(for use when the Parties mutually agree upon and execute the Change Order pursuant to Section 6.1B or 6.2C)
PROJECT NAME: Alternate Route 42” Single Line Option Creole Trail Pipeline - Segment 3A Project
OWNER: Cheniere Creole Trail Pipeline, L.P.
CONTRACTOR: Xxxxxxx Pipe Line Construction Company (SPLCC)
DATE OF AGREEMENT: January 10, 2007
SUBJECT: 24-inch Tetco Lateral Pipeline |
CHANGE ORDER NUMBER: CCT 3A-030
DATE OF CHANGE ORDER: 02-15-08 |
The Agreement between the Parties listed above is changed as follows: Xxxxxxx Pipe Line Construction Company (SPLCC) shall install the 24-inch Tetco lateral pipeline and associated items in accordance with all applicable drawings, specifications, permits, contract terms and conditions, and scope-of-work documentation. Payments shall be made in accordance with the attached table. Unit prices are fixed and are not subject to change. Payment will be made in accordance with actual quantities installed for each item, as approved by Owner. This Change Order authorizes work for Project 1102 – the Tetco Interconnect. As such, it is not subject to the pipeline project schedule as listed in the section below. The project schedule for the work authorized by this change order is as follows: The Guaranteed Mechanical Completion Date is April 1, 2008; The Guaranteed Final Completion Date is April 15, 2008. All facilities shall be installed to Company satisfaction in accordance with the preceding schedule dates.
Adjustment to Estimated Contract Price |
|||
The original Estimated Contract Price was |
$ | 65,605,739.22 | |
Net change by previously authorized Change Orders |
$ | 15,475,758.21 | |
The Estimated Contract Price prior to this Change Order was |
$ | 81,081,497.43 | |
The Estimated Contract Price will be increased by this Change Order in the amount of |
$ | 1,723,094.00 | |
The new Estimated Contract Price including this Change Order will be |
$ | 82,804,591.43 | |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A
The Guaranteed Mechanical Completion Date will be unchanged.
The Guaranteed Mechanical Completion Date as of the date of this Change Order therefore is January 31, 2008.
The Guaranteed Substantial Completion Date will be unchanged.
The Guaranteed Substantial Completion Date as of the date of this Change Order therefore is February 29, 2008.
The Guaranteed Final Completion Date will be unchanged.
The Guaranteed Final Completion Date as of the date of this Change Order therefore is March 31, 2008.
Adjustment to other Changed Criteria: N/A
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
Cheniere Creole Trail Pipeline, X.X. | Xxxxxxx Pipe Line Construction Company | |||
Owner | Contractor | |||
/s/ X. Xxxxx Xxxxxx | /s/ Xxxxxx X. Xxxxx, Xx. | |||
Signature | Signature | |||
X. Xxxxx Xxxxxx | Xxxxxx X. Xxxxx, Xx. | |||
Name | Name | |||
President | President & COO | |||
Title | Title | |||
2/21/2008 | March 3, 2008 | |||
Date of Signing | Date of Signing |
SCHEDULE D-1
CHANGE ORDER FORM
(for use when the Parties mutually agree upon and execute the Change Order pursuant to Section 6.1B or 6.2C)
PROJECT NAME: Alternate Route 42” Single Line Option Creole Trail Pipeline - Segment 3A Project
OWNER: Cheniere Creole Trail Pipeline, L.P.
CONTRACTOR: Xxxxxxx Pipe Line Construction Company (SPLCC)
DATE OF AGREEMENT: January 10, 2007
SUBJECT: 17,720’ of Class 2 Warning Tape |
CHANGE ORDER NUMBER: CCT 3A-031
DATE OF CHANGE ORDER: 03-06-08 |
The Agreement between the Parties listed above is changed as follows: Per the terms and conditions outlined under Article 6.2-B of the Construction Agreement for Segment 3A project between Cheniere Creole Trail Pipeline, L.P. and Xxxxxxx Pipe Line Construction Company dated January 10, 2007; Cheniere will compensate Xxxxxxx Pipe Line Co. for installing 17,720 feet of warning tape in all class 2 areas. This warning tape shall be installed to Company satisfaction in accordance with this change order.
Adjustment to Estimated Contract Price |
|||
The original Estimated Contract Price was |
$ | 65,605,739.22 | |
Net change by previously authorized Change Orders |
$ | 17,198,852.21 | |
The Estimated Contract Price prior to this Change Order was |
$ | 82,804,591.43 | |
The Estimated Contract Price will be increased by this Change Order in the amount of |
$ | 35,440.00 | |
The new Estimated Contract Price including this Change Order will be |
$ | 82,840,031.43 | |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A
The Guaranteed Mechanical Completion Date will be unchanged.
The Guaranteed Mechanical Completion Date as of the date of this Change Order therefore is January 31, 2008.
The Guaranteed Substantial Completion Date will be unchanged.
The Guaranteed Substantial Completion Date as of the date of this Change Order therefore is February 29, 2008.
The Guaranteed Final Completion Date will be unchanged.
The Guaranteed Final Completion Date as of the date of this Change Order therefore is March 31, 2008.
Adjustment to other Changed Criteria: N/A
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
Cheniere Creole Trail Pipeline, X.X. | Xxxxxxx Pipe Line Construction Company | |||
Owner | Contractor | |||
/s/ XX Xxxxxx | /s/ Xxxxxx X. Xxxxxx | |||
Signature | Signature | |||
XX Xxxxxx | Xxxxxx X. Xxxxxx | |||
Name | Name | |||
Director | Manager, Projects | |||
Title | Title | |||
3/12/08 | 03/21/08 | |||
Date of Signing | Date of Signing |
SCHEDULE D-1
CHANGE ORDER FORM
(for use when the Parties mutually agree upon and execute the Change Order pursuant to Section 6.1B or 6.2C)
PROJECT NAME: Alternate Route 42” Single Line Option Creole Trail Pipeline - Segment 3A Project
OWNER: Cheniere Creole Trail Pipeline, L.P.
CONTRACTOR: Xxxxxxx Pipe Line Construction Company (SPLCC)
DATE OF AGREEMENT: January 10, 2007
SUBJECT: Reduction to one 42” Launcher / Receiver |
CHANGE ORDER NUMBER: CCT 3A-032
DATE OF CHANGE ORDER: 03-10-08 |
The Agreement between the Parties listed above is changed as follows: Per the terms and conditions outlined under Article 6.1-B of the Construction Agreement for Segment 3A project between Cheniere Creole Trail Pipeline, L.P. and Xxxxxxx Pipe Line Construction Company dated January 10, 2007; Due to a reduction to one 42” Launcher / Receiver, contract item # B-6 will be reduced to $423,000.00. The previous amount of this item number was $940,000.00. This is a total reduction of the contract by $517,000.00.
Adjustment to Estimated Contract Price |
||||
The original Estimated Contract Price was |
$ | 65,605,739.22 | ||
Net change by previously authorized Change Orders |
$ | 17,234,292.21 | ||
The Estimated Contract Price prior to this Change Order was |
$ | 82,840,031.43 | ||
The Estimated Contract Price will be decreased by this Change Order in the amount of |
$ | (517,000.00 | ) | |
The new Estimated Contract Price including this Change Order will be |
$ | 82,323,031.43 | ||
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A
The Guaranteed Mechanical Completion Date will be unchanged.
The Guaranteed Mechanical Completion Date as of the date of this Change Order therefore is January 31, 2008.
The Guaranteed Substantial Completion Date will be unchanged.
The Guaranteed Substantial Completion Date as of the date of this Change Order therefore is February 29, 2008.
The Guaranteed Final Completion Date will be unchanged.
The Guaranteed Final Completion Date as of the date of this Change Order therefore is March 31, 2008.
Adjustment to other Changed Criteria: N/A
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
Cheniere Creole Trail Pipeline, X.X. | Xxxxxxx Pipe Line Construction Company | |||
Owner | Contractor | |||
/s/ X. Xxxxx Xxxxxx | /s/ Xxxxxx X. Xxxxxx | |||
Signature | Signature | |||
X. Xxxxx Xxxxxx | Xxxxxx X. Xxxxxx | |||
Name | Name | |||
President | Manager, Projects | |||
Title | Title | |||
3/13/2008 | 03/21/08 | |||
Date of Signing | Date of Signing |
SCHEDULE D-1
CHANGE ORDER FORM
(for use when the Parties mutually agree upon and execute the Change Order pursuant to Section 6.1B or 6.2C)
PROJECT NAME: Alternate Route 42” Single Line Option Creole Trail Pipeline - Segment 3A Project
OWNER: Cheniere Creole Trail Pipeline, L.P.
CONTRACTOR: Xxxxxxx Pipe Line Construction Company (SPLCC)
DATE OF AGREEMENT: January 10, 2007
|
CHANGE ORDER NUMBER:
DATE OF CHANGE ORDER: |
CCT 3A-033
03-19-08 | ||
SUBJECT: Correction to Change Order #CCT 3A-025 |
The Agreement between the Parties listed above is changed as follows: Per the terms and conditions outlined under Article 6.1-B of the Construction Agreement for Segment 3A project between Cheniere Creole Trail Pipeline, L.P. and Xxxxxxx Pipe Line Construction Company dated January 10, 2007; Change Order #CCT 3A-033 is to correct Change Order #CCT 3A-025.
Through mutual agreement between Xxxxxxxx and Xxxxxxx, change order CCT 3A-025 is null and void. This decreases the Estimated Contract Price by ($597,274).
The I-10 HDD is inserted as a new line into the contract with a value of $707,025. As the I-10 HDD was done in lieu of the I-10 Bore, this change order also decreases line item B-10.9 by ($224,000). This change covers all costs associated with the utilization of horizontal directional drilling instead of a bore to cross I-10.
The various scope changes (see attachment #2 “Various Scope Changes”) are inserted as a new line into the contract with a value of $226,799.
This change order results in a net increase to the Estimated Contract Price of $112,550. Please reference the attached spreadsheets (Attachment #1 & #2 to Change Order No: CCT 3A-033) for a summary of the changes.
Adjustment to Estimated Contract Price |
|||
The original Estimated Contract Price was |
$ | 65,605,739.22 | |
Net change by previously authorized Change Orders |
$ | 16,717,292.21 | |
The Estimated Contract Price prior to this Change Order was |
$ | 82,323,031.43 | |
The Estimated Contract Price will be increased by this Change Order in the amount of |
$ | 112,550.00 | |
The new Estimated Contract Price including this Change Order will be |
$ | 82,435,581.43 | |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A
The Guaranteed Mechanical Completion Date will be unchanged.
The Guaranteed Mechanical Completion Date as of the date of this Change Order therefore is January 31, 2008.
The Guaranteed Substantial Completion Date will be unchanged.
The Guaranteed Substantial Completion Date as of the date of this Change Order therefore is February 29, 2008.
The Guaranteed Final Completion Date will be unchanged.
The Guaranteed Final Completion Date as of the date of this Change Order therefore is March 31, 2008.
Adjustment to other Changed Criteria: N/A
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
Cheniere Creole Trail Pipeline, X.X. | Xxxxxxx Pipe Line Construction Company | |||
Owner | Contractor | |||
/s/ X. Xxxxx Xxxxxx | /s/ Xxxxxx X. Xxxxx, Xx. | |||
Signature | Signature | |||
X. Xxxxx Xxxxxx | Xxxxxx X. Xxxxx, Xx. | |||
Name | Name | |||
President | President & COO | |||
Title | Title | |||
4/1/2008 | April 8, 2008 | |||
Date of Signing | Date of Signing |
SCHEDULE D-1
CHANGE ORDER FORM
(for use when the Parties mutually agree upon and execute the Change Order pursuant to Section 6.1B or 6.2C)
PROJECT NAME: Alternate Route 42” Single Line Option Creole Trail Pipeline - Segment 3A Project
OWNER: Cheniere Creole Trail Pipeline, L.P.
CONTRACTOR: Xxxxxxx Pipe Line Construction Company (SPLCC)
DATE OF AGREEMENT: January 10, 2007
SUBJECT: Additional Bore Footage |
CHANGE ORDER NUMBER:
DATE OF CHANGE ORDER: |
CCT 3A-034
04-14-08 |
The Agreement between the Parties listed above is changed as follows: Per the terms and conditions outlined under Article 6.1-B of the Construction Agreement for Segment 3A project between Cheniere Creole Trail Pipeline, L.P. and Xxxxxxx Pipe Line Construction Company dated January 10, 2007; Cheniere will compensate Xxxxxxx Pipe Line Co. for additional Bore footage installed at various crossings on the Segment 3A pipeline project.
Through mutual agreement between Xxxxxxxx and Xxxxxxx, additional footage was necessary to complete the crossings due to foreign utilities and other construction obstacles.
Please reference attachment #1 for previous estimate and actual footages.
Adjustment to Estimated Contract Price |
|||
The original Estimated Contract Price was |
$ | 65,605,739.22 | |
Net change by previously authorized Change Orders |
$ | 16,829,842.21 | |
The Estimated Contract Price prior to this Change Order was |
$ | 82,435,581.43 | |
The Estimated Contract Price will be increased by this Change Order in the amount of |
$ | 403,760.00 | |
The new Estimated Contract Price including this Change Order will be |
$ | 82,839,341.43 | |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A
The Guaranteed Mechanical Completion Date will be unchanged.
The Guaranteed Mechanical Completion Date as of the date of this Change Order therefore is January 31, 2008.
The Guaranteed Substantial Completion Date will be unchanged.
The Guaranteed Substantial Completion Date as of the date of this Change Order therefore is February 29, 2008.
The Guaranteed Final Completion Date will be unchanged.
The Guaranteed Final Completion Date as of the date of this Change Order therefore is March 31, 2008.
Adjustment to other Changed Criteria: N/A
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
Cheniere Creole Trail Pipeline, X.X. | Xxxxxxx Pipe Line Construction Company | |||||||
Owner | Contractor | |||||||
/s/ X.X. Xxxxxx | /s/ X. Xxxxx Xxxxxx | /s/ Xxxxxx X. Xxxxx, Xx. | ||||||
Signature | Signature | |||||||
X.X. Xxxxxx | X. Xxxxx Xxxxxx | Xxxxxx X. Xxxxx, Xx. | ||||||
Name | Name | |||||||
Director | President | President & COO | ||||||
Title | Title | |||||||
4/18/08 | 4/18/08 | April 24, 2008 | ||||||
Date of Signing | Date of Signing |