CHANGE ORDER FORM Smokeless Flare Modification Study
Exhibit 10.3
CHANGE ORDER FORM
Smokeless Flare Modification Study
PROJECT NAME: Sabine Pass LNG Stage 2 Liquefaction Facility OWNER: Xxxxxx Xxxx Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 20, 2012 | CHANGE ORDER NUMBER: CO-00021 DATE OF CHANGE ORDER: March 29, 2016 |
The Agreement between the Parties listed above is changed as follows:
1. | Per Article 6.1.B of the Agreement, Parties agree Bechtel is to conduct a study to potentially identify a short-term and a long-term solution to mitigate smoke production in the flare systems to all wet, dry and marine flares. |
2. | The study referenced above will form the estimate for the implementation of short-term and long-term flare modifications. |
3. | The overall cost breakdown for this Change Order is detailed in Exhibit A. |
4. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order. |
Adjustment to Contract Price
The original Contract Price was | $ | 3,769,000,000 | |
Net change by previously authorized Change Orders (#0001-00020) | $ | 31,299,776 | |
The Contract Price prior to this Change Order was | $ | 3,800,299,776 | |
The Contract Price will be (increased) by this Change Order in the amount of | $ | 660,681 | |
The new Contract Price including this Change Order will be | $ | 3,800,960,457 |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): No impact to Project Schedule.
Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary)
Adjustment to Payment Schedule: Yes
Adjustment to Minimum Acceptance Criteria: N/A
Adjustment to Performance Guarantees: N/A
Adjustment to Design Basis: N/A
Other adjustments to liability or obligation of Contractor or Owner under the Agreement: N/A
Select either A or B:
[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials:
/s/ DV Contractor /s/EL Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: ____ Contractor ____ Owner
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
/s/ Xx Xxxxxxxx | /s/ Xxxx Xxxxxxx | |
Owner | Contractor | |
Xx Xxxxxxxx | Xxxx Xxxxxxx | |
Name | Name | |
SVP LNG E&C | Project Manager | |
Title | Title | |
June 16, 2016 | March 29, 2016 | |
Date of Signing | Date of Signing |
CHANGE ORDER FORM
Cable Tray Support and Arc Flash Study
PROJECT NAME: Sabine Pass LNG Stage 2 Liquefaction Facility OWNER: Xxxxxx Xxxx Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 20, 2012 | CHANGE ORDER NUMBER: CO-00022 DATE OF CHANGE ORDER: May 4, 2016 |
The Agreement between the Parties listed above is changed as follows:
1. | Per Article 6.1.B of the Agreement, Parties agree Bechtel will design supplemental cable tray supports, including drawings, details, bill of materials and a cost estimate for the associated material and installation labor. Neither procurement of materials nor installation of the supplemental supports is included in this Change Order. |
2. | Per Article 6.1.B of the Agreement, Parties agree Bechtel will conduct two (2) additional Arc Flash case studies (Tie Open and Tie Closed) for the following scenario: two (2) GTGs in service and a load combination of one (1) train, part of vaporization plant and three (3) BOG compressors. |
3. | The overall cost breakdown for this Change Order is detailed in Exhibit A. |
4. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order. |
Adjustment to Contract Price
The original Contract Price was | $ | 3,769,000,000 | |
Net change by previously authorized Change Orders (#0001-00021) | $ | 31,960,457 | |
The Contract Price prior to this Change Order was | $ | 3,800,960,457 | |
The Contract Price will be (increased) by this Change Order in the amount of | $ | 92,542 | |
The new Contract Price including this Change Order will be | $ | 3,801,052,999 |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A
Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary)
Adjustment to Payment Schedule: Yes. See Exhibit B.
Adjustment to Minimum Acceptance Criteria: N/A
Adjustment to Performance Guarantees: N/A
Adjustment to Design Basis: N/A
Other adjustments to liability or obligation of Contractor or Owner under the Agreement: N/A
Select either A or B:
[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials:
/s/ DV Contractor /s/ EL Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: ____ Contractor ____ Owner
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
/s/ Xx Xxxxxxxx | /s/ Xxxx Xxxxxxx | |
Owner | Contractor | |
Xx Xxxxxxxx | Xxxx Xxxxxxx | |
Name | Name | |
SVP LNG E&C | Principal Vice President | |
Title | Title | |
May 25, 2016 | May 5, 2016 | |
Date of Signing | Date of Signing |
CHANGE ORDER FORM
Re-Orientation of PSV Bypass Valves
PROJECT NAME: Sabine Pass LNG Stage 2 Liquefaction Facility OWNER: Xxxxxx Xxxx Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 20, 2012 | CHANGE ORDER NUMBER: CO-00023 DATE OF CHANGE ORDER: May 17, 2016 |
The Agreement between the Parties listed above is changed as follows:
1. | Per Article 6.1.B of the Agreement, Parties agree Bechtel will modify the current PSV bypass valve orientation on Subprojects 3 and 4 so that the cavity relief vents of the PSV bypass valves are on the high pressure side of the valves. This Change Order includes engineering hours to revise P&IDs and Isometric drawings. |
2. | The cost breakdown for this Change Order is detailed in Exhibit A. |
3. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order. |
Adjustment to Contract Price
The original Contract Price was | $ | 3,769,000,000 | |
Net change by previously authorized Change Orders (#0001-00022) | $ | 32,052,999 | |
The Contract Price prior to this Change Order was | $ | 3,801,052,999 | |
The Contract Price will be (increased) by this Change Order in the amount of | $ | 25,648 | |
The new Contract Price including this Change Order will be | $ | 3,801,078,647 |
Adjustment to dates in Project Schedule
The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A
Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary)
Adjustment to Payment Schedule: Yes. See Exhibit B.
Adjustment to Minimum Acceptance Criteria: N/A
Adjustment to Performance Guarantees: N/A
Adjustment to Design Basis: N/A
Other adjustments to liability or obligation of Contractor or Owner under the Agreement: N/A
Select either A or B:
[A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials:
/s/ DV Contractor /s/ EL Owner
[B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: ____ Contractor ____ Owner
Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.
/s/ Xx Xxxxxxxx | /s/ Xxxx Xxxxxxx | |
Owner | Contractor | |
Xx Xxxxxxxx | Xxxx Xxxxxxx | |
Name | Name | |
SVP LNG E&C | Principal Vice President | |
Title | Title | |
June 16, 2016 | May 17, 2016 | |
Date of Signing | Date of Signing |