EXHIBIT 10.1
Montebello Developments
(a style name of 2062331 ONTARIO INC.)
TEL: 000.000.0000
February 10, 2005
Salchi S.A. De C.V cba
Pueblomex Project
Salichi Bay, Huatuico
Oaxaca, Mexico
ATTN: Xxxx Page
---------------
Dear Xxxx,
This letter shall form the basis for entering into a more formal agreement with
you to develop the Salchi Bay, Villa Development (the "project") in Huatulco,
Mexico.
We will pay USD $ 1,100 per square meter of building living space
(approximately 140 sq. meters per house), land (approximately 160 sq. meters
per house) included to construct the houses on the property. Six houses will be
completed at each phase. A deposit will be made at the start of construction
for each house and the balance paid over construction milestones outlined in
the attached schedule 'A'. Once the first six are completed we will immediately
begin with the next phase of six and repeat the process for each six homes. We
will have the rights to all remaining lots and houses to be built thereon.
You will remain with the project and we will employ our own property manager
and site supervisor. This agreement will also include land for grounds
development and the construction of a pool and common elements to include
swimming pool, tennis court, bachi court, exercise room and marine equipment
room. Prices for each ancillary item listed in schedule 'B'.
Upon acceptance of this agreement, we will direct a deposit of USD $50,000 to
be transferred to your account by bank wire and thereafter to be credited to
the construction of the first houses. We will have the opportunity for 30 days
to conduct our due diligence into all costs and the feasibility of the project.
Upon being satisfied with the due diligence the parties shall enter into a
detailed purchase agreement, construction agreement and property management
agreement all to be negotiated in good faith on reasonable terms and to be
finalized within 30 days of the due diligence.
We appreciate the opportunity to enter into this agreement with you and look
forward to a prosperous relationship. I trust the above meets with your
approval, kindly sign and return the letter at your very earliest convenience
by fax at 0.000.000.0000.
The undersigned hereby agree to the terms and conditions set out herein.
Dated this 25th day of February, 2005.
Signed by: /s/ Xxx Xxxxxxxxx Signed by: /s/ Xxxx Page
-------------------- --------------------
Vic Xxxxxxxxx Xxxx Page
On Behalf of: On behalf of: Salchi S.A. De C.V. and
2062331 Ontario Inc. Pueblo Mex
-------------------- ------------------------
the "buyer" the "seller"
SCHEDULE 'A'
------------
Option Payment Schedule 1
1. 25% Down payment
2. 70% Over Six Equal Monthly Installments in Arrears
3. 5% Final Payment
Option Payment Schedule 2
1. 30% Down Payment
2. 30% At Completion of Concrete work of Foundation, Main Floor and Walls up
to Second Floor
3. 20% At Completion of Complete Interior and Exterior structure, Plumbing,
Electrical and Plaster Finish
4. 20% Upon Final Completion including Fixtures, Painting, Tile Work
SCHEDULE 'B'
------------
Open Space Terrace
Open spaced terrace integrated to the villa. Including tile floors, hand
railings made of rustic varnished wood, 'palapa' (thatched roof), sink,
electric and sanitary installations in addition to gas installation for
barbeque.
Price: USD $250.00 per square meter
Retaining Wall (Brick)
Retaining wall made of bricks and concrete with foundation, finishing with
a sealant and paint.
Price: USD $37.50 per linear meter
(Up to half a meter)
Retaining Wall (Stone)
Retaining wall adorned with stones on concrete base. Including excavation
of 50 cm depth and width.
Price: USD $120.00 per square meter
Walkways
Walkways constructed of concrete and rustic wood a sealer and paint.
Fully equipped with electrical lighting along the sides, made out of clay
lamps.
Price: USD $47.00 per linear meter
Rain Water Collector Drain
Price: USD $12.60 per linear meter
Berm
Soil bank covered with a wire mesh and wire net finish. Sealed and
painted.
Price: USD $37.50 per square meter