0001193125-08-173247 Sample Contracts

CHANGE ORDER FORM
Cheniere Energy Inc • August 11th, 2008 • Crude petroleum & natural gas

This change order is for accounting purposes to move the charges associated with an electrical cable relocation at Duck Blind road from CO-010 to CO-017. At Cheniere’s direction, Willbros made payments directly to Jeff Davis Electric Coop in the amounts shown on the attached Willbros invoices. Jeff Davis services and the amounts paid were outside Willbros’ construction scope of work covered by CO-010. Originally, Jeff Davis invoices were handled as a provisional amount associated with engineering in CO-010.

AutoNDA by SimpleDocs
SCHEDULE D-1 CHANGE ORDER FORM
Cheniere Energy Inc • August 11th, 2008 • Crude petroleum & natural gas
SCHEDULE D-1 CHANGE ORDER FORM (for use when the Parties mutually agree upon and execute the Change Order pursuant to Section 6.1B or 6.2C)
Cheniere Energy Inc • August 11th, 2008 • Crude petroleum & natural gas

The Agreement between the Parties listed above is changed as follows: Per the terms and conditions outlined under Article 6.1-B of the Construction Agreement for Segment 3A project between Cheniere Creole Trail Pipeline, L.P. and Sheehan Pipe Line Construction Company dated January 10, 2007; Cheniere will compensate Sheehan Pipe Line Co. for various miscellaneous additional items on the Segment 3A pipeline project.

Schedule D-1 CHANGE ORDER FORM
Cheniere Energy Inc • August 11th, 2008 • Crude petroleum & natural gas

To provide materials, equipment, and labor to install 750 sand bags over exposed 42” pipe in Oyster Lake per the attached sketch dated 4/28/08 and the attached cost estimate of 4/29/08.

Schedule D-1 CHANGE ORDER FORM
Cheniere Energy Inc • August 11th, 2008 • Crude petroleum & natural gas

Additional cost for providing equipment, material, and labor for site work at the MLV 2-1 site in the north marsh including rocking and fencing around the valve station site per the attached estimate of May 6, 2008.

SCHEDULE D-1 CHANGE ORDER FORM (for use when the Parties mutually agree upon and execute the Change Order pursuant to Section 6.1B or 6.2C)
Cheniere Energy Inc • August 11th, 2008 • Crude petroleum & natural gas

Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives.

LNG LEASE AGREEMENT
LNG Lease Agreement • August 11th, 2008 • Cheniere Energy Inc • Crude petroleum & natural gas • Texas

This LNG LEASE AGREEMENT (the “Agreement”) is entered into this 24th day of June, 2008 (“Effective Date”) by Cheniere Marketing, Inc., a Delaware corporation with its principle offices located at 700 Milam Street, Suite 500, Houston, Texas (“LESSOR”), and Sabine Pass LNG, L.P., a Delaware partnership with its principle offices located at 700 Milam Street, Suite 800, Houston, Texas (“LESSEE”). LESSOR or LESSEE may be referred to herein individually as a “Party”, and together as the “Parties”.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!